MahaRERA Application

General Information

Other Than Individual

Organization

D'Silva Niketan Co-Op. Hsg. Soc. Ltd.
Societies
NA
Do you have any Past Experience ?
No

Address Details

Survey No 85/2 CTS 264
D'Silva
Gurunath Warda Marg (Premier Road)
Kurla -West
Near Croma
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400070

Organization Contact Details

09820795099

Past Experience Details

Member Information

Member Name Designation Photo
Bennett Buthello Secretory View Photo

Project

DSilva Niketan
New Project
30/09/2023
No
Residential
No
264
CTS No 268B
18 30mt Wide Road
CTS No 266A
CTS No 262
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
Premier Road
Near Croma, Kurla
400070
700.66
1
1
0
0

FSI Details

677.25
1567.83
2245.08

Bank Details

Citizen Credit Co-Op Bank Ltd
CCBL0209006

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 29 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 As per the condition of Plan Passing Permission
Energy management : YES 0 Solar Panel and DG set Provided
Fire Protection And Fire Safety Requirements : YES 0 Will be Provided
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As Per MCGM
Aggregate area of recreational Open Space : YES 0 As per the condition of Plan Passing Permission
Open Parking : NO 0 NA
Water Supply : YES 0 As per the norms of Local Authority/Civic Body
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per the condition of Plan Passing Permission
Storm Water Drains : YES 0 As per the norms of Local Authority/Civic Body
Landscaping & Tree Planting : YES 0 As per the condition of Plan Passing Permission
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per the condition of Plan Passing Permission
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 DSilva Niketan Dsilva Niketan 30/09/2023 0 1 0 10 1 0 29
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 64.07 2 0
2 2BHK 68.82 7 0
3 2BHK 75.77 7 0
4 3BHK 79.92 2 0
5 1BHK 45.14 9 0
6 1BHK 45.98 8 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Eco Safe NA Engineer
Kamlesh Bhatt A51800000446 Real Estate Agent
K R Rege & Associates NA Architect
C K Doshi & Co NA Chartered Accountant
B Chopda Construction Pvt Ltd NA Contractor

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement