MahaRERA Application

General Information

Other Than Individual

Organization

MACROTECH DEVELOPERS LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

412, Floor 4 17G
Vardhaman Chamber
Cawasji Patel Road
Fort
Horniman Circle
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400001

Organization Contact Details

02261334761
www.lodhagroup.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1PALAVA SAVANNA AND SIENAResidentialNA3294Kalyan Shilphata road76/2 PT 76/4 PT 76/3 Pt44232020-08-312018-09-12

Member Information

Member Name Designation Photo
RAJENDRA NARPATMAL LODHA Chairperson View Photo
Bankim Doshi Authorized Signatory View Photo

Project

Lodha Lower Parel Project
New Project
30/12/2024
Yes
Residential
No
C.S No 1/157
CS No 2 by 157 and 156
30 Wide Sun Mill Road
CS No 155 and 156
50 Wide Sun Mill Road
MAHARASHTRA
Konkan
Mumbai City
Ward GSouth
GSouth-400013
Sita Ram Jadhav Marg
Lower Parel
400013
3626.03
1
1
0
732.12

FSI Details

0
10890
10890.00

Bank Details

Ratnakar bank Ltd
RATN0000070

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 117 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 80 NA
Water Conservation, Rain water Harvesting : YES 0 NA
Energy management : YES 0 NA
Fire Protection And Fire Safety Requirements : YES 80 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 NA
Close Parking : YES 70 NA
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : NO 0 NA
Water Supply : YES 90 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 NA
Storm Water Drains : YES 60 NA
Landscaping & Tree Planting : YES 90 NA
Street Lighting : YES 50 NA
Community Buildings : YES 80 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 90 NA
Solid Waste Management And Disposal : YES 90 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Lodha Lower Parel Project Lodha Lower Parel Project 30/12/2024 0 1 10 33 1 0 117
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 60.85 41 22
2 2BHK 61.78 26 18
3 2BHK 56.48 1 1
4 2BHK 57.23 1 0
5 2BHK 60.01 43 16
6 2BHK 60.76 23 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 98
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

75
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.3

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Vilas Desai and Associates NA Architect
K C SHAH CONSULTANTS NA Engineer
B B JAIN & ASSOCIATES NA Chartered Accountant
MSKA & ASSOCIATES NA Chartered Accountant
A NA Contractor
SHASHI KUMAR SHARMA A52100034329 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Lodha Lower Parel Project Small Causes Court Mumbai 499 Civil No Suit NA 2015 Part Heard
NA
Lodha Lower Parel Project Small Causes Court Mumbai 426 Civil No Appeal NA 2014 Part Heard
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
6 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement