MahaRERA Application

General Information

Other Than Individual

Organization

VINI BUILDERS AND DEVELOPERS
Others
PARTNERSHIP FIRM WITH HUF PARTNER
Do you have any Past Experience ?
No

Address Details

GAT NO 187,188
ARYAA DREAM TOWN
CHANDOLI
RAJGURUNAGAR
NEAR GOVERNMENT HOSPITAL
MAHARASHTRA
Pune
Pune
Khed
Chandoli
410505

Organization Contact Details

07776044044

Past Experience Details

Other Organization Type Member Information

Name Member Type
NILESH SHANTARAM KSHIRSAGAR Individual
YOGESH KSHIRSAGAR Individual
VINAY ZUMBARLAL BALDOTA HUF Others

Project

ARYAA DREAM TOWN
New Project
31/12/2024
No
Residential
No
187 PART, 188
GAT NO 187 PART AGRICULTURAL LAND
GAT NO 189 AGRICULTURAL LAND
VILLAGE ROAD
GAT NO 183 PART AGRICULTIRAL LANS
MAHARASHTRA
Pune
Pune
Khed
Chandoli
CHANDOLI
CHANDOLI
410505
6115
4
4
0
596.3

FSI Details

5989.19
0
5989.19

Bank Details

KOTAK MAHINDRA BANK LTD
KKBK0001790

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 28 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 0
Water Conservation, Rain water Harvesting : YES 0 0
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 0
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 0
CLUB HOUSE : YES 0 0
ENTRANCE GATE WITH SECURITY CABIN : YES 0 0
GARDEN : YES 0 0
GYM : YES 0 0
LIFT WITH GENRATOR BACK UP : YES 0 0
SENIOR CITIZEN SITOUT : YES 0 0
SOLOR WATER SYSTEM : YES 0 0
SWIMMING POOL : YES 0 0
Aggregate area of recreational Open Space : YES 0 0
Open Parking : YES 0 0
Water Supply : YES 0 0
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 0
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : YES 0 0
Street Lighting : YES 0 0
Community Buildings : YES 0 0
Treatment And Disposal Of Sewage And Sullage Water : YES 0 0
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ARYAA DREAM TOWN ARYAA DREAM TOWN BLDG D 31/12/2023 0 1 0 12 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 34.36 22 0
2 1BHK 37.17 21 0
3 1BHK 37.8 11 0
4 1BHK 41.21 6 0
5 1BHK 40.22 5 0
6 1BHK 39.9 6 0
7 1BHK 38.75 5 0
8 1BHK 32.22 6 0
9 1BHK 32.60 12 0
10 1BHK 31.02 10 0
11 1BHK 31.15 5 0
12 1RK 19.82 22 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ARYAA DREAM TOWN ARYAA DREAM TOWN -ROW HOUAES A TO H 31/12/2022 0 1 0 3 0 06 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 ROW HOUSES 87.72 8 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 ARYAA DREAM TOWN ARYAA DREAM TOWN ROW HOUSES I TO P 31/12/2022 0 1 0 3 0 3 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 ROW HOUSES 87.72 8 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 ARYAA DREAM TOWN ARYAA DREAM TOWN BLDG A1 31/12/2024 0 1 0 3 0 2 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.48 4 0
2 Shop 13.50 1 0
3 Shop 27.77 1 0
4 Shop 18.17 1 0
5 Shop 18.26 1 0
6 2BHK 56.09 1 0
7 1BHK 39.08 1 0
8 1BHK 39.91 1 0
9 1BHK 38.47 1 0
10 2BHK 54.35 1 0
11 2BHK 52.55 1 0
12 1BHK 37.8 1 0
13 1BHK 39.31 1 0
14 1BHK 39.89 1 0
15 2BHK 44.60 1 0
16 2BHK 58.07 1 0
17 1BHK 36.74 1 0
18 1BHK 37.33 1 0
19 1BHK 36.10 1 0
20 2BHK 52.76 1 0
21 2BHK 52.32 1 0
22 1BHK 38.20 1 0
23 1BHK 39.51 1 0
24 1BHK 39.67 1 0
25 2BHK 45.19 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
PRATIK PATOLE NA Architect
RAVINDRA KARNAVAT NA Engineer
YOGESH TANPURE NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement