MahaRERA Application

General Information

Other Than Individual

Organization

MOHAN LIFESPACES LLP
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

G1
MOHAN PLAZA
WAYLE NAGAR
KHADAKPADA
KALYAN
MAHARASHTRA
Konkan
Thane
Kalyan
Kalyan
421301

Organization Contact Details

02512305998
www.mohan-group.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Mohan HighlandsResidentialNA14770Badlapur67/1,67/2,68,69145412017-01-122017-01-12
2Mohan PlazaCommercialNA6069Wayle Nagar khadakpada Kalyan WestKalyan2602009-12-312009-12-31
3Mohan HeightsResidentialNA20000Bhiwandi Murbad Road Khadakpada Kalyan WestKalyan82702007-12-312007-12-31
4Mohan ParkResidentialNA28000Godrej Hills Road Khadakpada Kalyan WestKalyan163302002-12-312002-12-31
5Mohan RegencyResidentialNA30000Adarwadi Kalyan WestKalyan144502003-12-312003-12-31
6Mohan ParadiseResidentialNA12138Wayle Nagar khadakpada Kalyan WestKalyan92502006-12-312006-12-31
7Mohan PuramResidentialNA36000Near Dr. Gautam Jatale Hospital Kansai Section Ambernath EastAmbernath164502005-12-312005-12-31
8Mohan JyotResidentialNA8000Shiv Mandir Road Ambernath EastAmbernath41252006-12-312006-12-31
9Mohan GardenResidentialNA8000Rameshwadi Badlapur Gaon Road Badlapur WestBadlapur91502002-12-312002-12-31
10Manav ParkResidentialNA24000Rameshwadi Badlapur Gaon Road Badlapur WestBadlapur264652000-12-312000-12-31
11Mohan PrideResidentialNA28000Wayle Nagar khadakpada Kalyan WestKalyan64402009-12-312009-12-31
12Mohan SrishtiResidentialNA20000Kachore Patri Pull Kalyan EastKalyan63002010-12-312010-12-31
13Mohan ValleyResidentialNA16000Ganeshwadi Badlapur WestBadlapur144252011-12-312011-12-31
14Mohan Plaza IICommercialNA4000Wayle Nagar khadakpada Kalyan WestKalyan1242013-12-312013-12-31
15Mohan Palms I/IIResidentialNA27670Badlapur14/1,14/2A,14/2B,14/2C,15/2217662013-12-312013-12-31
16Mohan Palms IIIResidentialNA14973.58Badlapur13/8, 12/1, 12/2P196192016-12-312016-12-31
17Mohan GreenwoodsResidentialNA15603.59BadlapurGut No 1pt,Gut No 5pt156272017-04-302017-04-30
18Mohan Suburbia Oxford Phase IResidentialNA76080Ambernath25/9,25/10,25/11,25/12,25/14,35/2,36/3 to 36/15,36/16p,37,39/2,178,25/15196172014-12-312014-12-31
19Mohan Suburbia Salisbury Phase IIResidentialNA76080Ambernath25/9,25/10,25/11,25/12,25/14,35/2,36/3 to 36/15,36/16p,37,39/2,178,25/15206262016-12-312016-12-31
20Mohan Suburbia SchoolOthersSchool2300AmbernathReservation AMC 88112016-12-312016-12-31
21Mohan GalleriaCommercialNA1700AmbernathReservation1492017-03-212017-03-21

Member Information

Member Name Designation Photo
MAMTA AMAR BHATIA Partner View Photo
DEEPAK GOBIND MANCHANDYA Partner View Photo
DHIRAJ HARI BHATIA Partner View Photo
GEETU JEETENDER LALCHANDANI Partner View Photo
KUMAR GOBINDRAM VIDHANI Partner View Photo
LAKHI RAVI SHRINGI Partner View Photo
MANISH PARSRAM BAHRANI Partner View Photo
RAJESH CHANDIRAM KISHINSINGHANI Partner View Photo
SUNIL MOHANDAS HARCHANDANI Partner View Photo
AJIT RAMESHLAL GANDHI Partner View Photo
JEETENDER MOHANDAS LALCHANDANI Authorized Signatory View Photo
HARI MULCHAND BHATIA Authorized Signatory View Photo
OMPRAKASH NANDLAL MANCHANDYA Authorized Signatory View Photo
MANOHAR HARIRAM MANCHANDYA Authorized Signatory View Photo
AMIT RAMESHLAL GANDHI Authorized Signatory View Photo
HITESH NARI RAMCHANDANI Partner View Photo
CHIRAG MANOHAR MANCHANDYA Partner View Photo
TUSHAR JEETENDER LALCHANDANI Authorized Signatory View Photo

Project

Mohan Areca
On-Going Project
31/08/2019
31/12/2019
30/12/2022
No
Residential
No
SURVEY NO 4/HISSA NO 1P
RESERVATION NO 25 PLAY GROUND
RESERVATION NO 29
15MT DP ROAD
SURVEY NO 3
MAHARASHTRA
Konkan
Thane
Ambarnath
Badlapur (M Cl)
NEAR MOHAN PALMS
KATRAP, SHIRGAON
421503
7272.65
4
4
0
727.26

FSI Details

9788.62
0
9788.62

Details of RERA Designated Separate Bank Account

HDFC BANK
HDFC0001804

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 58 0 90

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 -
Water Conservation, Rain water Harvesting : YES 100 -
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 50 -
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 -
AC Library : YES 0 -
Acupressure Track : YES 0 -
Aerobics / Meditation Room : YES 0 -
Amphitheater : YES 0 -
Archery Net : YES 0 -
Art and Craft Room : YES 0 -
Children’s Play Area : YES 0 -
Club House : YES 0 -
Gazebo : YES 0 -
Gymnasium : YES 0 -
Indoor Badminton Court : YES 0 -
Indoor Games : YES 0 -
Jacuzzi, Steam & Sauna : YES 0 -
Jogging Track : YES 0 -
Landscape Garden : YES 0 -
Mini Theater : YES 0 -
Net Café : YES 0 -
Rock Climbing : YES 0 -
SOLAR POWER : YES 0 -
Swimming Pool : YES 0 -
Table Tennis : YES 0 -
Virtual Games ( Golf & Car Racing) : YES 0 -
Aggregate area of recreational Open Space : YES 0 -
Open Parking : YES 0 -
Water Supply : YES 100 -
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 -
Storm Water Drains : YES 100 -
Landscaping & Tree Planting : YES 90 -
Street Lighting : YES 100 -
Community Buildings : YES 50 -
Treatment And Disposal Of Sewage And Sullage Water : YES 100 -
Solid Waste Management And Disposal : YES 0 -

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Mohan Areca A WING 31/12/2019 0 1 0 17 1 8 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 39.10 8 8
2 2BHK 39.51 8 8
3 2BHK 35.50 16 16
4 2BHK 40.12 32 32
5 2BHK 41.62 8 8
6 2BHK 35.51 16 16
7 2BHK 38.7 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Mohan Areca B WING 31/12/2019 0 1 0 17 1 8 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 28 8 8
2 1BHK 28.13 8 8
3 1BHK 29.23 8 8
4 1BHK 29.27 8 8
5 2BHK 35.87 8 8
6 2BHK 36.25 8 8
7 2BHK 36.36 8 8
8 2BHK 36.74 8 8
9 2BHK 38.16 16 16
10 2BHK 38.63 8 8
11 2BHK 38.64 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Mohan Areca C WING 31/12/2019 0 1 0 4 1 8 22
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 39.1 2 2
2 2BHK 39.51 1 1
3 2BHK 35.5 2 2
4 2BHK 40.12 8 8
5 2BHK 41.62 1 1
6 2BHK 35.51 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Mohan Areca D WING 31/12/2019 0 1 0 1 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 13.62 1 1
2 Shop 22.7 1 1
3 Shop 24.58 2 2
4 Shop 29.41 1 1
5 Shop 39.02 1 1
6 Shop 47.32 1 1
7 Shop 48.4 6 6
8 Shop 32.25 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Shagun Infra NA Contractor
RAJ ASSOCIATES NA Architect
Vinayak Chopdekar & Associates NA Engineer
THE MW GROUP A51700000482 Real Estate Agent
Abhijiit Ashwin Tayade A51900002546 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Sunil Subhash Shelke A51700000840 Real Estate Agent
OXYZEN-UG A51700000351 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
ARUN KUMAR VEER BAHADUR SINGH A51700000202 Real Estate Agent
Paresh Shanker Nagrani A51800000874 Real Estate Agent
LANDMARK REALTORS A51800001093 Real Estate Agent
Ideal Properties A51700001298 Real Estate Agent
MAKWANA MAKANWALA A51800001394 Real Estate Agent
DEEPU J SHETTY A51700001868 Real Estate Agent
Shiv prasad Maurya A51700002135 Real Estate Agent
NILESH SINGH A51700015070 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 CERSAI details
1 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other – Legal
1 Other – Finance
1 Other – Technical

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000220812 DILIP BHASKAR PATIL View Orders
2 CC006000000292379 PRUTHVI VIRESH JADHAV View Orders
3 CC006000000292379 PRUTHVI VIRESH JADHAV View Orders
4 CC006000000292618 Abhay anant Gaikar View Orders
5 CC006000000292635 Vinayak Ganesh Asore View Orders
6 CC006000000292592 Rushikesh Prakash Patil View Orders
7 CC006000000251560 Sipin Dhirendra Rai View Orders
8 CC006000000334115 Mahadev Babu Karkhane View Orders
9 CC006000000364771 Rahul Ravindra Dond View Orders
10 CC006000000374809 Tejal Mahesh Gavade View Orders
11 CC006000000396305 Ajay Nandkumar Dombe View Orders
12 CC006000000302979 Bipin Dhirendra Rai View Orders