MahaRERA Application

General Information

Other Than Individual

Organization

SAI INFRA
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Shop No. 12
Precious Residency
Plot No. 16/16A
Sector 19
Sector 19
MAHARASHTRA
Konkan
Raigarh
Panvel
Kamothe
410206

Organization Contact Details

02227453238

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SAI DARSHANOthersResidential and Commercial319.8Shop No. 3 and 4 Plot no. 412 Sector 24 UlwePlot No-412, Sec-24, Pushpak Node, Ulwe1102020-11-012020-11-01

Member Information

Member Name Designation Photo
HARESH BHOPI Partner View Photo
Nikita Koparkar Partner View Photo
Vikram Thakur Partner View Photo
Deepak Gondhali Partner View Photo
Deepak Gondhali Authorized Signatory View Photo
Jayendra Joshi Partner View Photo

Project

SAI PLAZA
New Project
30/12/2022
No
Others
No
PLOT NO-359
9 MTR WIDE ROAD
PLOT NO-373
PLOT NO-358
PLOT NO-360
MAHARASHTRA
Konkan
Raigarh
Panvel
Ulawe
Plot No. 359, Sector -24
Pushpak Node
410206
339.73
1
1
0
0

FSI Details

339.73
0
339.73

Bank Details

BANK OF INDIA
BKID0000142

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SAI PLAZA SAI INFRA Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) NA NA 0
Covered Parking ( In Numbers) NA NA 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : NO 0 NA
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : NO 0 NA
Electrical fittings : YES 0 Work yet to be commenced
Electrical Meter Room, Sub-Station, Receiving Station : NO 0 NA
Electro Mechanical Equipment : YES 0 Work yet to be commenced
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : NO 0 NA
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : NO 0 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : NO 0 NA
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SAI PLAZA SAI PLAZA 31/12/2021 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 11 2 0
2 1RK 17 3 0
3 1BHK 26 5 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 90
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 9

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement