MahaRERA Application

General Information

Other Than Individual

Organization

MD REALTORS & DEVELOPERS LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

301-304
VIKAS CHAMBER
JUNCITON OF LINK AND MARVE ROAD
MITH CHOWKI
OBOVE ORIENTAL BANK OF COMMERCE
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400064

Organization Contact Details

02228824106

Past Experience Details

Member Information

Member Name Designation Photo
PANKAJ SHANTILAL PARIKH Partner View Photo
PANKAJ SHANTILAL PARIKH Authorized Signatory View Photo
CHETAN SHANTILAL PARIKH Partner View Photo
VINOD SHANTILAL PARIKH Partner View Photo

Project

YASH PLATINA
New Project
30/09/2025
No
Residential
Yes
SURVEY NO. 346B AND 356B HISSA NO. B1 to B5, C AND SURVEY NO. 347C HISSA NO. 1 and 2 AND SURVEY NO. 347A HISSA NO. 4 OF VILLAGE BOLINJ AND SURVEY NO. 21B HISSA NO. 3 OF VILLAGE DONGARE.
S NO 356 H NO 9 10 AND CHANNEL RESERVATION
20 MT WIDE PROPOSED DP ROAD
BUILDING NO 2 AND CFC 1
S NO 356 H NO 8 10 11 AND CHANNEL RESERVATION
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
OFF D MART ROAD
NEAR PENINSNULA PARK VIRAR WEST
401303
4896.56
3
3
0
750.03

FSI Details

15325
0
15325.00

Details of RERA Designated Separate Bank Account

ICICI BANK LTD
ICIC0000951

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
YASH PLATINA RAJ ENTERPRISES Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 78 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 AS PER LAYOUT PLAN
Internal Roads & Footpaths : YES 0 AS PER LAYOUT
Internal Roads & Footpaths : YES 0 AS PER LAYOUT PLAN
Internal Roads & Footpaths : YES 100 AS PER LAYOUT PLAN
Water Conservation, Rain water Harvesting : YES 0 AS PER REQUIREMENTS
Water Conservation, Rain water Harvesting : YES 10 AS PER REQUIREMENTS
Energy management : NO 0 NA
Energy management : YES 0 AS PER REQUIREMENTS
Fire Protection And Fire Safety Requirements : YES 0 WILL BE PROVIDED AS PER CFO NOC
Fire Protection And Fire Safety Requirements : YES 10 WILL BE PROVIDED AS PER CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WILL BE PROVIDED
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WILL BE PROVIDED AS PER REQUIREMENTS
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 WILL BE PROVIDED
Aggregate area of recreational Open Space : YES 77 AS PER PART OF LAYOUT
Aggregate area of recreational Open Space : YES 0 AS PER PART OF LAYOUT
Open Parking : YES 0 WILL BE PROVIDED AS PER APPROVED PLAN
Open Parking : YES 10 WILL BE PROVIDED AS PER APPROVED PLAN
Water Supply : YES 0 AS PER REQUIREMENTS
Water Supply : YES 10 AS PER REQUIREMENTS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER REQUIREMENTS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 10 AS PER REQUIREMENTS
Storm Water Drains : YES 0 AS PER REQUIREMENTS
Storm Water Drains : YES 10 AS PER REQUIREMENTS
Landscaping & Tree Planting : YES 0 AS PER LAYOUT PLAN
Landscaping & Tree Planting : YES 50 AS PER LAYOUT PLAN
Street Lighting : YES 0 AS PER REQUIREMENTS
Street Lighting : YES 10 AS PER REQUIREMENTS
Community Buildings : YES 0 AS PER LAYOUT PLAN
Community Buildings : YES 50 AS PER LAYOUT PLAN
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER REQUIREMENTS
Treatment And Disposal Of Sewage And Sullage Water : YES 10 AS PER REQUIREMENTS
Solid Waste Management And Disposal : YES 0 AS PER REQUIREMENTS
Solid Waste Management And Disposal : YES 10 AS PER REQUIREMENTS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 YASH PLATINA YASH PLATINA WING-A 31/03/2025 0 1 0 22 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 52.59 42 19
2 2BHK 55.44 39 34
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 YASH PLATINA YASH PLATINA WING-B 31/03/2025 0 1 0 22 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.86 21 1
2 1BHK 35.84 21 2
3 1BHK 37.62 18 6
4 1BHK 34.38 39 25
5 1BHK 36.32 21 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 YASH PLATINA YASH PLATINA WING-C 31/03/2025 0 1 0 22 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 38.53 21 0
2 2BHK 51.38 20 0
3 1BHK 44.50 21 7
4 1BHK 35.71 18 2
5 2BHK 52.14 20 12
6 1BHK 45.24 21 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SANJAY NARANG NA Architect
PARESH UNNARKAR NA Engineer
MANSI ASSOCIATES NA Contractor
MANSI CONSTRUCTION NA Contractor
AKBINDER KAUR SAINI NA Chartered Accountant
SANJAY BANSAL NA Chartered Accountant
BHARAT DHONDE NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other – Legal
1 Other – Finance
1 Other – Technical