MahaRERA Application

General Information

Other Than Individual

Organization

SHREE SACHDHANAND DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

C/104
PALACIA PHASE-II
NA
NEAR CORSICA BUILDING
BEHIND HIRANANDANI ESTATE
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400615

Organization Contact Details

08082000005
www.palacia.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1PALACIA PHASE-IIOthersRESIDENTIAL 12978.29Near Corscia Building Behind Hiranandani Estate Thane West 400615S NO-226 HISSA NO-1,2,3 S NO-227 HISSA NO-3,4 AND 2B AND S NO-22864362015-06-012016-01-14
2PALACIA PHASE IIOthersRESIDENTIAL AND COMMERCIAL33000WAGHBIL GAON AT THANES NO 227, 228, 22932712019-06-302019-06-30

Member Information

Member Name Designation Photo
GOPE MADHAVDAS ROCHLANI Partner View Photo
RAJA GOPE ROCHLANI Partner View Photo
VANDANA GOPE ROCHLANI Partner View Photo
JANVI RAJA ROCHLANI Partner View Photo
RAJA GOPE ROCHLANI Authorized Signatory View Photo

Project

PALACIA PHASE-II
On-Going Project
30/06/2019
30/12/2019
30/12/2020
Yes
Others
No
S NO 226 HISSA NO 1,2,3, S NO 227 HISSA NO 3,4,2B AND S NO-228
BHOOMI ACRES
SWASTIK REGALIYA
WAGHBIL GAON
VIJAY NAGARI
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
WAGHBIL
KAVESAR
400615
8801.62
3
3
0
3298.49

FSI Details

15883.24
0
15883.24

Bank Details

DCB BANK
DCBL0000086

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 368 147 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Completed
Water Conservation, Rain water Harvesting : YES 100 Completed
Energy management : YES 100 Completed
Fire Protection And Fire Safety Requirements : YES 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Completed
ELEVATED RG : YES 100 Completed
Gymnasium : YES 100 Completed
Indoor games : YES 100 Completed
Mini Theatre : YES 100 Completed
Party hall : YES 100 Completed
Swimming pool : YES 100 Completed
Yoga Hall : YES 100 Completed
Aggregate area of recreational Open Space : YES 100 Completed
Open Parking : YES 100 Completed
Water Supply : YES 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 100 Completed
Landscaping & Tree Planting : YES 100 Completed
Street Lighting : YES 100 Completed
Community Buildings : YES 100 Completed
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Completed
Solid Waste Management And Disposal : YES 100 Completed

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 PALACIA PHASE-II BLDG A 30/12/2019 0 1 0 21 1 1 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 11.37 2 0
2 SHOP 12.90 2 0
3 SHOP 15.50 1 0
4 SHOP 15.51 3 0
5 2BHK 46.54 77 30
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 PALACIA PHASE-II BLDG B 30/12/2019 0 1 0 21 1 2 116
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 15.90 2 0
2 SHOP 17.85 2 0
3 SHOP 12.54 2 0
4 SHOP 15.49 1 0
5 SHOP 15.50 1 0
6 SHOP 15.51 2 0
7 2BHK 56.69 97 49
8 2BHK 54.86 20 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 PALACIA PHASE-II BLDG C 30/12/2019 0 1 0 21 1 1 117
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 70.30 40 23
2 2.5 BHK 62.14 20 14
3 2BHK 55.62 17 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Proponline Business Solutions Pvt Ltd A51700000287 Real Estate Agent
Harai Ramijani Patel NA Contractor
Anil Jagwani NA Architect
Anand J. Sawant NA Engineer

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
PALACIA PHASE-II SPECIAL CIVIL COURT 498 Civil No Suit NA 2016 PENDING
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
5 Copy of the legal title report
6 Copy of the legal title report
7 Copy of the legal title report
8 Copy of the legal title report
9 Copy of the legal title report
10 Copy of the legal title report
11 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement