MahaRERA Application

General Information

Other Than Individual

Organization

BHAGWATI VENTURES LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

1306
REAL TECH PARK
PLOT NO39/2, SEC 30A
VASHI
OPP. VASHI RAILWAY STATION
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02227816115

Past Experience Details

Member Information

Member Name Designation Photo
DHARMENDRA MANJI PATEL Partner View Photo
KULIN SHANTILAL VORA Authorized Signatory View Photo

Project

BHAGWATI BELMONT
New Project
30/06/2025
No
Others
Yes
21/15, 20/1 pt, 20/2 pt
12 MTR WIDE ROAD
SURVEY NO 21 HISSA NO 16
SURVEY NO 21 HISSA NO 14
40 MTR WIDE DP ROAD
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
HAWARE CITI ROAD
VADAVALI
400607
4100.00
3
2
1
624.97

FSI Details

6929.45
1500
8429.45

Bank Details

KOTAK MAHINDRA BANK
KKBK0000669

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
BHAGWATI BELMONT M/S HAWARE HOUSING Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 90 90 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 RWH TANK TO BE PROVIDED
Energy management : YES 0 WORK NOT YET COMMENCED ON SITE
Fire Protection And Fire Safety Requirements : YES 0 WORK TO BE COMMENCE
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WORK TO BE COMMENCE
Aggregate area of recreational Open Space : YES 0 WORK NOT YET COMMENCE ON SITE
Open Parking : NO 0 NA
Water Supply : YES 0 PROVIDED UPTO SITE BY CIDCO
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WORK TO BE COMMENCE
Storm Water Drains : YES 0 WORK TO BE COMMENCE
Landscaping & Tree Planting : YES 0 WORK TO COMMENCE
Street Lighting : NO 0 PROVIDED UPTO SITE BY CIDCO
Community Buildings : NO 0 21 NO. OF TREES
Treatment And Disposal Of Sewage And Sullage Water : YES 0 NA
Solid Waste Management And Disposal : YES 0 WORK TO BE COMMENCE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 BHAGWATI BELMONT BHAGWATI BELMONT Ground TO 27th FLOORS 30/06/2024 0 1 0 28 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE12 38.92 10 9
2 TYPE 13 38.59 10 10
3 TYPE 14 38.31 12 12
4 TYPE 15 37.98 1 1
5 TYPE 16 37.68 1 1
6 UNIT 1 14.47 1 0
7 UNIT 2 13.41 1 0
8 UNIT 3 36.65 1 0
9 UNIT 4 15.04 1 0
10 UNIT 5 12.47 1 0
11 UNIT 6 18.45 1 0
12 UNIT 7 17.31 1 0
13 UNIT 8 13.99 1 0
14 UNIT 9 26.10 1 0
15 TYPE 2 60.62 18 8
16 TYPE 8 41.66 18 15
17 UNIT 10 20.34 1 0
18 UNIT 11 22.55 1 0
19 UNIT 12 17.87 1 0
20 UNIT 13 48.27 1 0
21 UNIT 14 24.61 1 0
22 UNIT 15 16.32 1 0
23 UNIT 16 24.00 1 0
24 UNIT 17 20.52 1 0
25 TYPE 4 50.04 11 4
26 TYPE 5 56.40 1 1
27 TYPE 6 56.33 1 0
28 UNIT 18 23.90 1 0
29 UNIT 19 20.31 1 0
30 UNIT 20 19.85 1 0
31 UNIT 21 13.99 1 0
32 TYPE 3 57.12 1 0
33 TYPE 10 41.62 18 7
34 TYPE 11 41.30 18 2
35 TYPE 7 41.76 18 15
36 TYPE 1 60.69 15 5
37 TYPE 9 39.63 12 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 50
5 X number of Slabs of Super Structure 92
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 54
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 23
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 18
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

39
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.6
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 BHAGWATI BELMONT BHAGWATI BELMONT 28th TO 31st FLOORS PROPOSED BUT NOT SANCTIONED 30/06/2024 0 1 0 4 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 1 41.66 4 0
2 TYPE 2 60.62 4 0
3 TYPE 3 41.62 4 0
4 TYPE 4 41.30 4 0
5 TYPE 5 41.76 4 0
6 TYPE 6 60.69 3 0
7 TYPE 7 39.63 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 80
5 X number of Slabs of Super Structure 95
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 74
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 8
11 Overall Percentage of Completion of the work done For the entire Building /Wing 71.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 BHAGWATI BELMONT BHAGWATI BELMONT 32nd TO 33rd FLOORS PROPOSED BUT NOT SANCTIONED 30/06/2024 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 5 41.30 2 0
2 TYPE 6 41.76 2 0
3 TYPE 7 39.63 1 0
4 TYPE 1 41.66 2 0
5 TYPE 2 60.62 2 0
6 TYPE 3 41.62 2 0
7 TYPE 4 60.69 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 50
5 X number of Slabs of Super Structure 92
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 54
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 23
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 18
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

39
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.6

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SAAKAR ARCHITECTS NA Architect
PENTACON STRUCTURAL CONSULTANTS PVT LTD NA Engineer
BH PATEL & ASSOCIATES NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement