MahaRERA Application

General Information

Other Than Individual

Organization

SAIESHWAR PROJECTSS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

302/304
PARK PLAZA
DR KETKAR ROAD
ERANDWANE
KAMLA NEHRU PARK
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02025665100

Past Experience Details

Member Information

Member Name Designation Photo
Sanjay Shamsundar Bihani Partner View Photo
Vijay Narayan Jalan Partner View Photo
Shrikant Hiralal Unecha Authorized Signatory View Photo
Rajendra Shamsundar Bihani Partner View Photo
Sameer Dwarkaprasad Jalan Partner View Photo

Project

SAI SQUARE
On-Going Project
28/12/2016
31/12/2018
30/12/2024
Yes
Others
No
CTS NO 1187/69/1 F.P. NO 548
BY ROAD
BY CST NO 1187-69-2 AND 1187-68 SHIVAJINAGAR
BY CTS NO 1187-67 SHIVAJINAGAR
BY ROAD
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004
834
1
1
0
0

FSI Details

936.96
553.04
1490.00

Bank Details

bank of maharashtra
MAHB0000001

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 18 6 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 YET TO BE STARTED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 YET TO BE STARTED
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 YET TO BE STARTED
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 YET TO BE STARTED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 YET TO BE STARTED
Storm Water Drains : YES 0 YET TO BE STARTED
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SAI SQUARE SAI SQUARE 31/12/2018 0 0 0 4 1 0 18
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 7.74 1 1
2 Shop 8.09 1 0
3 Office space 8.13 1 0
4 Office space 11.23 1 1
5 Shop 11.72 1 1
6 1RK 14.5 1 1
7 Shop 16.46 1 1
8 1RK 17.68 2 2
9 2BHK 55.83 2 1
10 Shop 77.72 1 1
11 1RK 20.03 1 1
12 1RK 20.45 1 1
13 1RK 22.19 1 0
14 Shop 22.45 1 1
15 Shop 22.55 1 1
16 1RK 23.58 1 1
17 1BHK 27.1 1 0
18 1BHK 28.75 1 0
19 1BHK 29.1 1 1
20 1BHK 29.27 1 0
21 1BHK 32.34 1 1
22 Shop 41.19 1 1
23 2BHK 46.43 1 1
24 2BHK 50.36 1 1
25 2BHK 50.68 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
VINAY WAKALKAR NA Architect
SPECTRUM PARAG CHOPDA NA Engineer
Mayur Mundada NA Other Professional
PRERANA VENTURES LLP A52100001056 Real Estate Agent
SK Consultants & Engineers NA Engineer
Vidya S. Bhure & Co. NA Chartered Accountant
Gaurav S Rajpal & Co NA Chartered Accountant
RERA Easy NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
SAI SQUARE Addl Small Cause Judge and Civil Judge Senior Division Pune 1403/2007 Civil No Suit NA 2007 Hearing on Amendment Application
NA
SAI SQUARE Honourable Civil Judge Senior Division Pune 913/2007 Civil No Suit NA 2007 Hearing on Amendment Application
NA
SAI SQUARE Addl Small Cause Judge Pune 259/14 Civil No Suit NA 2014 At the stage of evidence
NA
SAI SQUARE Hon Civil PMC Court Pune 477/15 Civil No Suit NA 2015 Hearing on Exh five Application for Temporary Injunction
NA
SAI SQUARE Addl Small Cause Judge Pune 362/2015 Civil No Suit NA 2015 At the stage of evidence
NA
SAI SQUARE Addl Small Cause Judge Pune 350/2014 Civil No Suit NA 2014 At the stage of evidence
NA
SAI SQUARE Addl Small Cause Judge Pune 349/2014 Civil No Suit NA 2014 At the stage of evidence
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement