MahaRERA Application

General Information

Other Than Individual

Organization

Tirth Home Developers
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

3rd Floor
595/D Narendra Villa
Dr. Ambedkar Road
Matunga
Kapole Nivas
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400019

Organization Contact Details

02026357731
www.vasupujya.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Neco GharkulResidentialNA1000Dhankawadi Pune-411043321202015-12-312015-12-31
2Neco SkyPark Phase IResidentialNA12619Pimple Nilakh Pune - 4110272041842013-12-312014-03-31

Member Information

Member Name Designation Photo
Suresh Ajmera Authorized Signatory View Photo
Rahul Ajmera Partner View Photo
Dhanesh Ajmera Partner View Photo
Siddharth Ajmera Partner View Photo

Project

Neco SkyPark Phase III
On-Going Project
31/12/2021
30/12/2022
Yes
Residential
No
20
Part of land bearing Sr No 20 Hissa 13
9 metre wide road
12 metre wide DP road and plot B and private land
24 metre wide DP road and Wings A B C D
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
Wakad-Baner DP Road
Vishalnagar, Pimple Nilakh
411027
5119.29
2
2
0
1369.52

FSI Details

5868.48
33
5901.48

Details of RERA Designated Separate Bank Account

Kotak Mahindra Bank
KKBK0001771

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 69 69 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Completed
Water Conservation, Rain water Harvesting : YES 100 Completed
Energy management : YES 100 Solar Water Heating System
Fire Protection And Fire Safety Requirements : YES 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 As per MSEDCL norms
Aggregate area of recreational Open Space : YES 100 Open Space with Football Ground completed
Open Parking : YES 100 Completed
Water Supply : YES 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 100 Completed
Landscaping & Tree Planting : YES 100 More than 200 full grown trees in project
Street Lighting : YES 100 Completed
Community Buildings : YES 100 Club House & Swimming Pool operational
Treatment And Disposal Of Sewage And Sullage Water : YES 100 STP fully operational
Solid Waste Management And Disposal : YES 100 Completed

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Neco SkyPark Phase III Wing E 31/07/2018 1 1 0 12 1 12 32
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 68.4 2 2
2 2 BHK 64.07 1 1
3 1 BHK 47.16 1 1
4 2 BHK 61.57 4 4
5 2 BHK 61.69 1 1
6 2 BHK 58.17 2 2
7 2 BHK 67.83 1 1
8 1 BHK 51.2 1 1
9 1 BHK 47.76 2 2
10 2 BHK 65.14 16 16
11 2 BHK 68.58 2 2
12 2 BHK 68.68 8 8
13 2 BHK 71.75 1 1
14 3 BHK 89.77 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Neco SkyPark Phase III Wing F 31/12/2020 1 1 0 12 1 10 37
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 71.25 1 1
2 2 BHK 57.54 1 1
3 1 BHK 43.64 1 1
4 1 BHK 46.88 1 1
5 2 BHK 58.17 18 18
6 2 BHK 61.41 8 8
7 3 BHK 71.84 9 9
8 3 BHK 78.22 1 1
9 2 BHK 63.07 2 2
10 2 BHK 67.67 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Solespace NA Architect
Kishor P Jain NA Engineer
Realtors Compass A52100001849 Real Estate Agent
MAISON CHASSE PRIVATE LIMITED A52100000327 Real Estate Agent
SPACEINDIA NEST LLP A52100002248 Real Estate Agent
PROPENGINE REALTECH LLP A52100000628 Real Estate Agent
CORAZON HOMES AND SECURITIES A52100000096 Real Estate Agent
WISTERIA REAL VISION PVT LTD A52100003089 Real Estate Agent
chirag brijpuria A52100007920 Real Estate Agent
NANASAHEB YADAVRAO BHAVARPATIL A52200013849 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Neco SkyPark Phase III Civil Court Senior Division 202569/2012 Civil No Suit NA 2012 Evidence Part Heard
NA
Neco SkyPark Phase III Civil Court Senior Division 200766/2015 Civil No Suit NA 2015 Filing of Say on Exh Unready
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
5 Copy of the legal title report
6 Copy of the legal title report
7 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
2 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other – Legal
1 Other – Finance
1 Other – Technical

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000022233 Yashraj Developers View Orders