Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
Puneville Phase II Cluster A
|
G
|
31/12/2021
|
0
|
1
|
0
|
23
|
1 |
0 |
85 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
67.13 |
85 |
85 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
Puneville Phase II Cluster A
|
H
|
31/12/2021
|
0
|
1
|
0
|
23
|
1 |
0 |
85 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
70.55 |
43 |
43 |
2 |
2BHK |
70.56 |
42 |
42 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
Puneville Phase II Cluster A
|
I
|
31/12/2021
|
0
|
1
|
0
|
23
|
1 |
0 |
129 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
60.36 |
1 |
1 |
2 |
2.5 BHK |
76.88 |
43 |
43 |
3 |
2BHK |
60.37 |
20 |
20 |
4 |
2.5 BHK |
77.04 |
44 |
44 |
5 |
2BHK |
60.24 |
21 |
21 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
Puneville Phase II Cluster A
|
J
|
31/12/2021
|
0
|
1
|
0
|
23
|
1 |
0 |
129 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
59.71 |
44 |
44 |
2 |
2BHK |
60.34 |
20 |
20 |
3 |
2BHK |
59.74 |
43 |
43 |
4 |
1BHK |
47.90 |
1 |
1 |
5 |
2BHK |
60.23 |
21 |
21 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|