MahaRERA Application

General Information

Other Than Individual

Organization

Onyx Promoters LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Office no 301
Marvel Alaina
Lane no 5
Koregaon Park
Above Kargo Restaurant
MAHARASHTRA
Pune
Pune
Haveli
KOREGAON PARK
411001

Organization Contact Details

02049165111

Past Experience Details

Member Information

Member Name Designation Photo
Pushparaj Krishan LAL Khanna Partner View Photo
Rohit Sureshchand Garg Authorized Signatory View Photo
Rahul Sureshchand Garg Partner View Photo

Project

Gagan Avencia
On-Going Project
31/03/2021
31/03/2021
30/09/2024
Yes
Others
Yes
S.no 63/1/1 & 63/2
Road
S No 63
S No 63
S No 63
MAHARASHTRA
Pune
Pune
Haveli
KHARADI
Grant Road
KHARADI, PUNE
411014
14024.87
5
5
0
906.99

FSI Details

30888.75
00
30888.75

Bank Details

ICICI Bank
ICIC0004103

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Avencia Gagan Landmarks LLP Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Avencia Westfield Properties LLP Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Avencia Gagan Spaces Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Avencia Bay Point Realty LLP Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Avencia Gagan Township LLP Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 369 337 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 50 After completion of Main Buildings
Water Conservation, Rain water Harvesting : YES 50 After completion of Main Buildings
Energy management : YES 0 After completion of Main Buildings
Fire Protection And Fire Safety Requirements : YES 0 After completion of Main Buildings
Electrical Meter Room, Sub-Station, Receiving Station : YES 10 After completion of Main Buildings
Aggregate area of recreational Open Space : YES 0 After completion of Main Buildings
Open Parking : NO 0 NA
Water Supply : YES 0 After completion of Main Buildings
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 80 After completion of Main Buildings
Storm Water Drains : YES 90 After completion of Main Buildings
Landscaping & Tree Planting : YES 0 After completion of Main Buildings
Street Lighting : YES 0 After completion of Main Buildings
Community Buildings : YES 50 After completion of Main Buildings
Treatment And Disposal Of Sewage And Sullage Water : YES 80 After completion of Main Buildings
Solid Waste Management And Disposal : YES 10 After completion of Main Buildings

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Gagan Avencia A 30/03/2023 3 1 0 18 0 0 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 71.26 1 1
2 2BHK 62.49 9 9
3 2BHK 62.77 9 9
4 2 BHK 72.31 1 1
5 3BHK 117.64 1 1
6 3BHK 120.30 1 1
7 3BHK 88.39 9 8
8 3 BHK 88.44 8 7
9 2 BHK 87.66 1 1
10 3 BHK 89.50 13 13
11 3 BHK 88.99 1 1
12 2 BHK 63.62 12 12
13 2BHK 86.32 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 87
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 82
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 62
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.1
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Gagan Avencia B 30/03/2023 3 1 0 18 0 0 75
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 86.32 3 3
2 3BHK 88.44 6 6
3 2BHK 71.26 1 1
4 2BHK 62.49 9 9
5 2BHK 62.77 9 8
6 3BHK 88.39 8 8
7 2BHK 63.62 13 12
8 3BHK 89.50 13 13
9 3BHK 87.66 1 1
10 3BHK 88.99 1 1
11 3BHK 117.34 1 1
12 3BHK 120.30 1 1
13 2BHK 72.31 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 91
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 81
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

87
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Gagan Avencia Commercial and Mhada 30/03/2022 3 1 0 14 0 0 67
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 office 24.59 6 6
2 Office 37.39 36 28
3 MHADA 31.11 28 24
4 Shop 76.15 1 1
5 Shop 35.66 1 1
6 Shop 55.24 5 5
7 Office 38 6 3
8 MHADA 36.32 4 3
9 MHADA 39.16 5 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 82
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

93
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 62
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Gagan Avencia C 30/03/2023 2 1 0 18 0 0 75
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 67.65 61 54
2 3BHK 94.83 2 2
3 3BHK 94.66 2 2
4 1BHK 47.78 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 88
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 81
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

86
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
11 Overall Percentage of Completion of the work done For the entire Building /Wing 81.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Gagan Avencia D 30/03/2023 2 1 0 18 0 0 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 95.18 2 2
2 2BHK 60.05 9 8
3 3BHK 82.03 2 2
4 1BHK 47.90 2 0
5 2BHK 60.08 9 9
6 2BHK 67.65 30 23
7 2BHK 59.94 14 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 86
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 81
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

86
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
11 Overall Percentage of Completion of the work done For the entire Building /Wing 81.3

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Mr.Mukesh Satav NA Contractor
Mr.Soudagar NA Contractor
Mr.Tambe NA Contractor
Mr.Ajay NA Contractor
Mr Malwadkar NA Architect
Mr.Rajesh Mankani NA Engineer
Abhay Motilal Bhurat A52100001258 Real Estate Agent
Sanjay Haribhau Gargate A52100001552 Real Estate Agent
VIKAS SATISH GUPTA A52100002607 Real Estate Agent
Addressofchoice Realty Pvt Ltd A52100000116 Real Estate Agent
Premlata Estate Solutions Pvt. Ltd. A52100000033 Real Estate Agent
Thomas C Abraham A52100000927 Real Estate Agent
Kirankumar Tarachand Chopda A52100002190 Real Estate Agent
MINT LIFESPACES A52100007639 Real Estate Agent
Bhisham Suresh Parwani A52100007974 Real Estate Agent
Signet Space Realty Private Limited A52100007915 Real Estate Agent
OPTIMUS REALTORS A52100000310 Real Estate Agent
AKASH AMOLOKCHAND KHATER A52100006171 Real Estate Agent
Bluenest Properties LLP A52100007204 Real Estate Agent
AMIT ARVIND SODANI A52100001140 Real Estate Agent
Saroj Vinod Jain a52100008304 Real Estate Agent
ROHIT SATPATHY a52100007862 Real Estate Agent
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
PROPERTY CHEF CONSULTING SERVICES a52100000044 Real Estate Agent
PRAVIN DEOCHANDRA JHA a52100001546 Real Estate Agent
Saroj Vinod Jain a52100008304 Real Estate Agent
RAVIRAJ GANGAPRASAD THANVI A52100007495 Real Estate Agent
INVESTADVISE WEALTH MANAGEMENT PRIVATE LIMITED A52100002914 Real Estate Agent
VIKAS SATISH GUPTA a52100002607 Real Estate Agent
RAVIRAJ GANGAPRASAD THANVI a52100007495 Real Estate Agent
AMIT ARVIND SODANI a52100001140 Real Estate Agent
Salman Mansoor Shaikh a52100002502 Real Estate Agent
AMIT ARVIND SODANI a52100001140 Real Estate Agent
FLATONS ADVISORS A52100004415 Real Estate Agent
NIKHIL RAGHUNATH KHAIRMODE A52100013709 Real Estate Agent
Jay Aeram and Associates NA Architect

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Gagan Avencia Civil Court Senior Division Pune 680 Civil No Suit NA 2018 Awaiting Summons
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
21 Building Plan Approval (IOD)
22 Building Plan Approval (IOD)
23 Building Plan Approval (IOD)
24 Building Plan Approval (IOD)
25 Building Plan Approval (IOD)
26 Building Plan Approval (IOD)
27 Building Plan Approval (IOD)
28 Building Plan Approval (IOD)
29 Building Plan Approval (IOD)
30 Building Plan Approval (IOD)
31 Building Plan Approval (IOD)
32 Building Plan Approval (IOD)
33 Building Plan Approval (IOD)
34 Building Plan Approval (IOD)
35 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
21 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
22 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
23 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
24 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
2 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement