MahaRERA Application

General Information

Other Than Individual

Organization

Himgiri Buildcon & Industries Ltd
Company
NA
Do you have any Past Experience ?
No

Address Details

Khasra No.130 & 131/1
Richmond Greens
Main Koradi Road
Mouza Zingabai Takli
Near Koradi Naka
MAHARASHTRA
Nagpur
Nagpur
Nagpur (Urban)
Nagpur (M Corp.)
440030

Organization Contact Details

01141602309

Past Experience Details

Member Information

Member Name Designation Photo
Ravi Agarwal Authorized Signatory View Photo
Ram Charan Agarwal Director View Photo
Rakhi Agarwal Director View Photo
Kamla Agarwal Director View Photo

Project

Richmond Greens Block A Tower G
New Project
30/03/2023
No
Residential
No
2
Block F
Road
Podium
Road
MAHARASHTRA
Nagpur
Nagpur
Nagpur (Urban)
Nagpur (M Corp.)
Khasra No.130 & 131/1 Main Koradi Road
Mouza Zingabai Takli Nagpur
440030
1684
1
1
0
253

FSI Details

3535
707
4242.00

Bank Details

Bank of India
BKID0008757

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Richmond Greens Block A Tower G Himgiri Buildcon & Industries Ltd Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 36 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 under construction
Water Conservation, Rain water Harvesting : YES 0 under construction
Energy management : YES 0 under construction
Fire Protection And Fire Safety Requirements : YES 0 under construction
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 under construction
Aggregate area of recreational Open Space : YES 0 under construction
Open Parking : YES 0 under construction
Water Supply : YES 0 under construction
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 under construction
Storm Water Drains : YES 0 under construction
Landscaping & Tree Planting : YES 0 under construction
Street Lighting : YES 0 under construction
Community Buildings : YES 0 under construction
Treatment And Disposal Of Sewage And Sullage Water : YES 0 under construction
Solid Waste Management And Disposal : YES 0 under construction

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Richmond Greens Block A Tower G Richmond Greens Tower A Block G 31/03/2022 0 1 1 13 1 12 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Type II 69.30 24 0
2 3bhk Type I 77.00 24 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Choudahry Consultants NA Architect
Juniper Softwares NA Engineer
Yogi Constructions NA Contractor
SMC REAL ESTATE ADVISORS PRIVATE LIMITED A51900000042 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement