Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
Azure Aster G and H
|
Azure Aster G
|
28/02/2025
|
0
|
1
|
1
|
13
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
60.95 |
9 |
1 |
2 |
2BHK |
61.60 |
3 |
1 |
3 |
1BHK |
39.33 |
19 |
0 |
4 |
1BHK |
39.35 |
3 |
0 |
5 |
1BHK |
39.76 |
1 |
0 |
6 |
1BHK |
39.78 |
1 |
0 |
7 |
1BHK |
44.06 |
1 |
0 |
8 |
1BHK |
44.46 |
1 |
0 |
9 |
2BHK |
61.16 |
9 |
0 |
10 |
2BHK |
61.28 |
9 |
0 |
11 |
2BHK |
62.34 |
3 |
0 |
12 |
2BHK |
62.19 |
1 |
0 |
13 |
2BHK |
62.22 |
1 |
0 |
14 |
1BHK |
39.33 |
2 |
1 |
15 |
2BHK |
63.43 |
7 |
0 |
16 |
2BHK |
63.46 |
3 |
0 |
17 |
2BHK |
63.96 |
1 |
0 |
18 |
2BHK |
61.63 |
9 |
0 |
19 |
2BHK |
61.87 |
3 |
0 |
20 |
2BHK |
61.93 |
3 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
Azure Aster G and H
|
Azure Aster H
|
28/02/2025
|
0
|
1
|
1
|
13
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
39.33 |
19 |
0 |
2 |
1BHK |
39.35 |
3 |
0 |
3 |
1BHK |
39.76 |
1 |
0 |
4 |
1BHK |
39.78 |
1 |
0 |
5 |
1BHK |
44.06 |
1 |
0 |
6 |
1BHK |
44.46 |
1 |
0 |
7 |
2BHK |
60.95 |
9 |
0 |
8 |
2BHK |
61.16 |
9 |
0 |
9 |
2BHK |
61.28 |
9 |
0 |
10 |
2BHK |
61.60 |
3 |
0 |
11 |
2BHK |
61.63 |
9 |
0 |
12 |
2BHK |
61.87 |
3 |
0 |
13 |
2BHK |
61.93 |
3 |
0 |
14 |
2BHK |
62.19 |
1 |
0 |
15 |
2BHK |
62.22 |
1 |
0 |
16 |
2BHK |
62.34 |
3 |
0 |
17 |
2BHK |
63.43 |
7 |
0 |
18 |
2BHK |
63.46 |
3 |
0 |
19 |
2BHK |
63.96 |
1 |
0 |
20 |
1BHK |
39.33 |
2 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|