MahaRERA Application

General Information

Other Than Individual

Organization

REGENT BUILDERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

603
INIZIO
CARDINAL GRACIOUS ROAD
CHAKALA ANDHERI EAST
OPP P & G PLAZA MUMBAI
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400099

Organization Contact Details

02261668883

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1RADHA RESIDENCYResidentialNA673.1ISMALIA VILLAGE SARASWAT BAUGJOGESHWARI EAST MUMBAI-400060CTS NO 111 111/11202016-03-312016-02-24

Member Information

Member Name Designation Photo
RAMESHCHAND BABULALJI BOHRA Authorized Signatory View Photo
KANWAL RAMESHCHAND BOHRA Authorized Signatory View Photo
RAMESHCHAND BABULALJI BOHRA Partner View Photo
KANWAL RAMESHCHAND BOHRA Partner View Photo
KETAN RAMESHCHAND BOHRA Partner View Photo
PRATIK HIRALAL BOHRA Partner View Photo

Project

AUDUMBAR CHS LTD
New Project
30/03/2022
No
Residential
No
CTS NO 1281
CTS NO 1274B CTS NO1272 CTS NO 1270
TILAK MANDIR ROAD
CTS NO 1280
CTS NO 1282
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
19 TILAK MANDIR ROAD
VILE PARLE EAST
400057
831.1
1
1
0
0

FSI Details

2148.86
0
2148.86

Bank Details

RBL BANK LTD
RATN0000192

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 33 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 RECHARGE PIT PROPOSED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 AS PER CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER REQUIREMENT BY TATA/RELIANCE ENERGY
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 ON COMPLETION OF BUILDING
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 INTERNAL CHAMBERS AND INTERCONNECTION LINES PROPOS
Storm Water Drains : YES 0 INTERNAL SWD PROPOSED TO MUNICIPAL STORM WATER DRA
Landscaping & Tree Planting : YES 0 AS PER TREE NOC
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 100 VERMICULTURE BIN WILL BE PROVIDED AS PER MCGM

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 AUDUMBAR CHS LTD AUDUMBAR CHS LTD 31/03/2021 0 1 0 8 0 1 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 71.40 1 1
2 3bhk 50.91 1 1
3 2BHK 9.48 1 1
4 3BHK 20.35 4 4
5 2BHK 68.19 1 1
6 2BHK 68.21 1 1
7 3BHK 87.65 1 1
8 2BHK 69.77 3 2
9 2BHK 69.79 2 2
10 3BHK 89.37 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SYNERGY ARCHITECTS AND CONSULTANTS NA Architect
ASHISH SOLANKI NA Architect
JIGAR JAYANTILAL SHAH A51800000376 Real Estate Agent
PIYUSH SURA NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
2 Certificates of Architect (Form 4)
3 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement