MahaRERA Application

General Information

Other Than Individual

Organization

RELIABLE CONSTRUCTIONS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

BLDG NO. 10 1ST FLOOR
ROHINI CHS LTD
JN OF 1ST RD & LINK RD
SHASTRI NAGAR GOREGAON WEST
NR SHASTRI NAGAR PLAY GROUND
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400104

Organization Contact Details

02228765233

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1ROHINI CHS LTDResidentialNA1015BLDG NO 10 JN OF RD NO 1 AND LINK ROAD SHASTRI NAGAR GOREGAON WEST MUMBAI 40010410 CITY SURVEY NO 222P, 222/41 TO 222/48 VILLAGE PAHADI NAGAR, GOREGAON WEST, MUMBAI 4001041492010-12-252011-02-28
2KAPIL VASTU CHS LTDResidentialNA755.97BLDG NO 4 SHASTRI NAGAR NR SIDDHARTH HOSPITAL GOREGAON WEST MUMBAI 400 104CTS NO 217 VILLAGE PAHADI NAGAR GOREGAON WEST MUMBAI 4001041422009-11-302010-01-20
3DIVYA JYOTI CHS LTDResidentialNA1190BLDG NO. 25 SHASTRI NAGAR GOREGAON WEST MUMBAI 400104CTS NO 220 PART 25 - 32 VILLAGE PAHADI NAGAR GOREGAON WEST MUMBAI 4001041642007-01-312007-03-15
4PRABHAT CHS LTD - Phase IResidentialNA1069.72BLDG NO 20 SHASTRI NAGAR GOREGAON WEST MUMBAI 400104CTS NO 217 PT VILLAGE PAHADI GOREGAON WEST SHASTRI NAGAR TALUKA BORIVALIMUMBAI 40010411012017-02-282017-05-31
5VASUNDHARA CHS LTD - Phase I Wing A and BResidentialNA1376.12Bldg No 6 Road No 1 Shastri Nagar Goregaon west Mumbai - 400 104CTS NO 219PT Divn Konkan Village Pahadi Goregaon Taluka Borivali District Mumbai 4001041802015-04-302015-06-30

Member Information

Member Name Designation Photo
HANIF ISMAILBHAI AGWAN Partner View Photo
IRSHAD HANIF MULLA Partner View Photo
MOHAMMAD MAAZ HANIF AGWAN Partner View Photo
IMRAN RAFIQ FARAS Authorized Signatory View Photo

Project

Laxmi Nagar
On-Going Project
31/12/2019
30/12/2023
29/12/2024
No
Residential
No
Plot No B-1 CTS 1A170-B Pahadi Goregaon W Tal Borivali Dist Mumbai 400090
36Mt wide Link Road
CTS No 1A 170-A
Vasant Galaxy CHS Ltd
18 Wide DP Road
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
Mahakali Mandir Marg
Goregaon West
400090
7400
6
3
3
436.28

FSI Details

26761.51
0
26761.51

Bank Details

HDFC BANK
HDFC0000322

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 124 44 70

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Work Not Started
Water Conservation, Rain water Harvesting : YES 0 Work Not Started
Energy management : YES 0 Work Not Started
Fire Protection And Fire Safety Requirements : YES 0 Work Not Started
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Work Not Started
Health Club : NO 0 NA
Swimming Pool : NO 0 NA
Aggregate area of recreational Open Space : YES 0 Work Not Started
Open Parking : NO 0 NA
Water Supply : YES 0 Work Not Started
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Work Not Started
Storm Water Drains : YES 0 Work Not Started
Landscaping & Tree Planting : YES 0 Work Not Started
Street Lighting : YES 0 Work Not Started
Community Buildings : YES 0 Work Not Started
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Work Not Started
Solid Waste Management And Disposal : YES 0 Work Not Started

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Laxmi Nagar BLDG NO 1 Rehab 30/12/2023 0 1 0 15 0 2 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 5.02 1 1
2 ResI.Cum.Commercial 25.06 2 2
3 Shop 5.22 1 1
4 Shop 5.95 1 1
5 Shop 6.53 1 1
6 Shop 15.78 1 1
7 Shop 17.11 1 1
8 Shop 13.46 1 1
9 Shop 35.11 1 1
10 Shop 29.79 1 1
11 Shop 8.51 1 1
12 Shop 8.51 1 1
13 Shop 9.11 1 1
14 Shop 9.62 1 1
15 Shop 10.87 2 2
16 Shop 11.05 1 1
17 Shop 11.31 2 2
18 Shop 11.7 1 1
19 Shop 13.92 4 4
20 Shop 14.85 1 1
21 Shop 15.69 1 1
22 Shop 15.75 1 1
23 Shop 8.27 1 1
24 Shop 18.34 1 1
25 Shop 19.26 1 1
26 Shop 21.39 2 2
27 Shop 29.79 1 1
28 Shop 32.12 1 1
29 Shop 12.01 1 1
30 Shop 12.27 1 1
31 Shop 13.03 1 1
32 Shop 13.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Laxmi Nagar Bldg No 2 Laxmi Nagar Development CHS - Wing A 30/12/2023 0 1 0 22 1 1 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 11.35 1 1
2 Shop 11.84 1 1
3 Shop 12.38 1 1
4 Shop 13.41 1 1
5 Shop 15.13 1 1
6 Shop 18.94 1 1
7 Shop 19.96 1 1
8 Shop 20.32 1 1
9 Shop 21.77 1 1
10 Shop 23.05 1 1
11 Shop 25.04 1 1
12 Shop 2.68 1 1
13 Shop 8.38 1 1
14 Shop 8.74 1 1
15 Shop 8.83 1 1
16 Shop 10.04 1 1
17 Shop 10.44 1 1
18 Shop 10.75 1 1
19 Shop 7.34 5 5
20 Shop 9.18 3 3
21 Shop 14.94 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 86
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 86
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 86
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 86
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

86
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 78
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Laxmi Nagar BLDG NO 2 CONFARE HEIGHTS - Wing B and C 30/12/2023 0 1 0 22 1 0 89
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 30.75 39 8
2 1BHK 26.48 131 66
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

50
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Laxmi Nagar BLDG NO 3 - Contare Heights 30/12/2023 0 1 6 28 1 0 126
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 62.83 24 16
2 2BHK 74.04 32 22
3 2.5 BHK 72.49 9 6
4 2.5 BHK 84.92 13 6
5 3.5BHK 91.53 24 15
6 3.5 BHK 122.07 32 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 95
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Laxmi Nagar BLDG NO 4 - Religious Structure 30/12/2023 0 0 0 0 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Religious Structure 249.78 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 Laxmi Nagar BLDG NO 5 - Religious Structure 30/12/2023 0 0 0 0 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Religious Structure 235.29 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
T N Hasan of Punar Vikas Vastushastra NA Architect
Siddique Sunasara of Frame Design NA Engineer
Mani Ram of MAK MEP Consultants NA Other Professional
Adv P M Vyas NA Other Professional
MURTUZA SULAMAN A51800004657 Real Estate Agent
RITA SANDEEP SHAH A51900003120 Real Estate Agent
SAI ESTATE CONSULTANTS CHEMBUR PRIVATE LIMITED A51800000147 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
8 Commencement Certificates / NA Order for plotted development
9 Commencement Certificates / NA Order for plotted development
10 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
3 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
2 Disclosure of Interest in Other Real Estate Organizations
3 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
2 Proforma of Agreement for sale
3 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000196200 Rajiv Prakash and Sonie Rajiv Prakash View Orders
2 CC006000000196202 Amit Raj and Meghna Raj View Orders
3 CC006000000196201 Rajiv Prakash and Sonie Rajiv Prakash View Orders
4 CC006000000196202 Amit Raj and Meghna Raj View Orders
5 CC006000000196200 Rajiv Prakash and Sonie Rajiv Prakash View Orders
6 CC006000000196201 Rajiv Prakash and Sonie Rajiv Prakash View Orders