MahaRERA Application

General Information

Other Than Individual

Organization

ADITI BUILDERS & DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO 20
GAGAN ARCADE
LINK ROAD
VASAI EAST
EVERSHINE CITY
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
401208

Organization Contact Details

02506058585

Past Experience Details

Member Information

Member Name Designation Photo
AJEET YOGENDRA SINGH Partner View Photo
GORAKH AMARSINGH CHAVHAN Partner View Photo
NITIN BHIMASHANKAR GOPALE Authorized Signatory View Photo

Project

RUKMINI ENCLAVE
New Project
30/06/2023
31/12/2026
No
Residential
Yes
GUT NO 108,111,112,113,115,116 AND 118
BUILDING NO 6
BUILDING NO 4 WING A AND B
12M WIDE ROAD
OPEN SPACE
MAHARASHTRA
Konkan
Palghar
Palghar
Betegaon
TATA HOUSING ROAD
BOISER EAST
401501
1528.36
2
2
0
0

FSI Details

1528.36
0
1528.36

Bank Details

BASSEIN CATHOLIC CO OP BANK LIMITED
BACB0000018

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
RUKMINI ENCLAVE SAI CRYSTAL HOMES Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 50 WORK IN PROGRESS
Water Conservation, Rain water Harvesting : YES 0 WORK IN PROGRESS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WORK IN PROGRESS
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 WORK IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WORK IN PROGRESS
Storm Water Drains : YES 0 WORK IN PROGRESS
Landscaping & Tree Planting : YES 0 WORK IN PROGRESS
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WORK IN PROGRESS
Solid Waste Management And Disposal : YES 0 WORK IN PROGRESS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 RUKMINI ENCLAVE RUKMINI ENCLAVE BUILDING NO 4 WING C 30/06/2022 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 12.81 2 2
2 SHOP 11.45 4 3
3 FLAT 31.03 1 1
4 FLAT 18.27 1 1
5 FLAT 28.03 2 2
6 FLAT 26.74 8 5
7 FLAT 28.77 6 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 20
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 RUKMINI ENCLAVE RUKMINI ENCLAVE BUILDING NO 4 WING D 30/06/2022 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 12.81 2 1
2 SHOP 11.45 4 3
3 FLAT 31.03 1 1
4 FLAT 18.27 1 1
5 FLAT 28.03 2 2
6 FLAT 26.74 8 5
7 FLAT 26.77 6 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 20
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 24
11 Overall Percentage of Completion of the work done For the entire Building /Wing 67.4

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AJAY WADE AND ASSOCIATES NA Architect
JAY SHREE KRISHNA NA Engineer
CHANDAN CHOUDHARY AND ASSOCIATES NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement