MahaRERA Application

General Information

Other Than Individual

Organization

S S Properties
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

101 201 301
B A Gateway
Baner Road
Sakalnagar
Lagu Bandhu Showroom
MAHARASHTRA
Pune
Pune
Haveli
Baner
411007

Organization Contact Details

02025603900

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
132 Pinewood DriveResidentialNA25260S No 31 and 32 Bhoirwadi Tal Mulshi Dist PuneS No 31 and 3243362020-12-312020-12-31

Member Information

Member Name Designation Photo
Sagar Rikhablal Bhandari Partner View Photo
Sachin Rikhablal Bhandari Authorized Signatory View Photo
Ghanshyam Jhangaldas Sukhwani Partner View Photo
Raj Deepak Shah Partner View Photo
Vicky Ghansham Sukhwani Partner View Photo
Jay Shailesh Shah Authorized Signatory View Photo

Project

43 Privet Drive- C Building
New Project
30/06/2023
Yes
Residential
No
S.NO.43H.NO,8,9,10,11,12A, 12B, 13/1,2, 14/1,2, 44 8/1 Balewadi
S No 03
S No 04
S No 43 P
30m Wide Road
MAHARASHTRA
Pune
Pune
Haveli
Baner
High Street
Balewadi
411045
4209.21
1
1
0
2560.04

FSI Details

7500
5524.74
13024.74

Bank Details

State Bank Of India
SBIN0001110

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 86 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Internal roads are in tremix
Water Conservation, Rain water Harvesting : YES 80 Rainwater harvesting scheme is operational
Energy management : YES 70 As per MSEDCL norms
Fire Protection And Fire Safety Requirements : YES 80 Fire protection for 3 bldgs. is completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Completed in all respects
Aggregate area of recreational Open Space : YES 100 Open space on podium is completed.
Open Parking : YES 80 Open parking work of previous 3 bldgs completed
Water Supply : YES 80 Watersupply of previous 3 bldgs completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 80 Sewerage lines of previous 3 bldgs completed
Storm Water Drains : YES 80 Stomwater scheme of previous 3 bldgs operational
Landscaping & Tree Planting : YES 90 Podium landscape is completed
Street Lighting : YES 90 Streetlights are operational
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 STP is commissioned and operational
Solid Waste Management And Disposal : YES 100 OWC is operational

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 43 Privet Drive- C Building C 30/06/2023 0 1 1 20 1 80 80
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 126.58 1 0
2 3BHK 131.38 1 0
3 3BHK 136.11 1 0
4 3BHK 136.14 4 0
5 2BHK 107.70 1 0
6 3BHK 122.06 2 0
7 3BHK 132.84 10 0
8 3BHK 133.76 10 0
9 3BHK 131.65 2 0
10 3BHK 126.55 18 0
11 3BHK 130.45 1 0
12 3BHK 130.73 1 0
13 3BHK 125.59 19 4
14 3BHK 135.16 9 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 67
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 22
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 4
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.3

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Golden Elite Builldcon NA Contractor
Ar Milind Patil NA Architect
G A Bhilare NA Engineer
R V Porwal and associates NA Chartered Accountant

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
43 Privet Drive- C Building High Court WP 10053/2009 Civil No Writ Petition 2009 Pending for final hearing
NA
43 Privet Drive- C Building High Court WP 1410/2018 Civil No Writ Petition 2018 Pending for admission
NA
43 Privet Drive- C Building Civil Court Junior Division RCS 63/20 Civil No Suit 2020 Notices to all defendants yet to serve and reply of defendants yet to be filed
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval / NA Order for plotted development
Building Plan Approval / NA Order for plotted development
Building Plan Approval / NA Order for plotted development
Building Plan Approval / NA Order for plotted development
Building Plan Approval / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other