Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA K
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
35.37 |
2 |
2 |
2 |
1BHK |
41.74 |
2 |
2 |
3 |
1BHK |
45.02 |
9 |
9 |
4 |
1BHK |
46.31 |
1 |
1 |
5 |
1BHK |
46.98 |
9 |
9 |
6 |
2BHKULTIMA |
56.60 |
1 |
1 |
7 |
2BHKULTIMA |
57.09 |
1 |
1 |
8 |
1BHK |
42.41 |
30 |
30 |
9 |
1BHK |
44.72 |
8 |
8 |
10 |
1BHK |
42.11 |
34 |
33 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA L
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
56 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKOPTIMA |
55.28 |
34 |
31 |
2 |
2BHKOPTIMA |
55.34 |
30 |
26 |
3 |
1BHK |
45.92 |
1 |
1 |
4 |
1BHK |
42.47 |
1 |
1 |
5 |
2BHKOPTIMA |
51.61 |
1 |
1 |
6 |
2BHKOPTIMA |
55.06 |
1 |
1 |
7 |
3BHKOPTIMA |
86.12 |
1 |
1 |
8 |
3BHKOPTIMA |
86.06 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA M
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
90 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
46.31 |
1 |
1 |
2 |
1BHK |
46.68 |
8 |
8 |
3 |
1BHK |
46.98 |
9 |
9 |
4 |
2BHKULTIMA |
56.60 |
1 |
1 |
5 |
1BHK |
42.11 |
34 |
34 |
6 |
1BHK |
35.37 |
2 |
2 |
7 |
1BHK |
41.74 |
2 |
2 |
8 |
1BHK |
42.41 |
30 |
30 |
9 |
1BHK |
44.35 |
1 |
1 |
10 |
1BHK |
44.72 |
8 |
8 |
11 |
1BHK |
45.02 |
9 |
9 |
12 |
2BHKULTIMA |
57.09 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA N
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
55 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
45.92 |
1 |
0 |
2 |
1BHK |
42.47 |
1 |
0 |
3 |
2BHKOPTIMA |
51.61 |
1 |
0 |
4 |
2BHKOPTIMA |
55.06 |
1 |
0 |
5 |
2BHKOPTIMA |
55.34 |
30 |
19 |
6 |
3BHKOPTIMA |
86.12 |
1 |
0 |
7 |
3BHKOPTIMA |
86.06 |
1 |
0 |
8 |
2BHKOPTIMA |
55.28 |
34 |
23 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA O
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
90 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
44.35 |
1 |
0 |
2 |
2BHKULTIMA |
56.60 |
1 |
0 |
3 |
2BHKULTIMA |
57.09 |
1 |
0 |
4 |
1BHK |
46.31 |
1 |
0 |
5 |
1BHK |
35.37 |
2 |
2 |
6 |
1BHK |
41.74 |
2 |
2 |
7 |
1BHK |
44.72 |
8 |
4 |
8 |
1BHK |
45.02 |
9 |
5 |
9 |
1BHK |
46.98 |
9 |
6 |
10 |
1BHK |
46.68 |
8 |
2 |
11 |
1BHK |
42.41 |
30 |
25 |
12 |
1BHK |
42.11 |
34 |
29 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA P
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
90 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
35.37 |
2 |
2 |
2 |
1BHK |
41.74 |
2 |
2 |
3 |
1BHK |
44.72 |
8 |
4 |
4 |
1BHK |
42.11 |
34 |
26 |
5 |
1BHK |
45.02 |
9 |
7 |
6 |
1BHK |
46.31 |
1 |
0 |
7 |
1BHK |
44.35 |
1 |
0 |
8 |
2BHKULTIMA |
56.60 |
1 |
0 |
9 |
2BHKULTIMA |
57.09 |
1 |
0 |
10 |
1BHK |
42.41 |
30 |
25 |
11 |
1BHK |
46.98 |
9 |
2 |
12 |
1BHK |
46.68 |
8 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA Q
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
55 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKOPTIMA |
86.12 |
1 |
0 |
2 |
3BHKOPTIMA |
86.06 |
1 |
0 |
3 |
2BHKOPTIMA |
55.34 |
30 |
19 |
4 |
2BHKOPTIMA |
55.28 |
34 |
18 |
5 |
2BHKOPTIMA |
51.61 |
1 |
0 |
6 |
2BHKOPTIMA |
55.06 |
1 |
0 |
7 |
1BHK |
45.92 |
1 |
0 |
8 |
1BHK |
42.47 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA R
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
90 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
41.74 |
2 |
2 |
2 |
1BHK |
42.41 |
30 |
22 |
3 |
1BHK |
42.11 |
34 |
30 |
4 |
1BHK |
45.02 |
9 |
7 |
5 |
1BHK |
46.31 |
1 |
0 |
6 |
1BHK |
46.98 |
9 |
4 |
7 |
1BHK |
46.68 |
8 |
0 |
8 |
1BHK |
44.72 |
8 |
5 |
9 |
1BHK |
44.35 |
1 |
0 |
10 |
2BHKULTIMA |
56.60 |
1 |
0 |
11 |
2BHKULTIMA |
57.09 |
1 |
0 |
12 |
1BHK |
35.37 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA S
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
55 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKOPTIMA |
55.06 |
1 |
0 |
2 |
2BHKOPTIMA |
55.28 |
34 |
17 |
3 |
2BHKOPTIMA |
55.34 |
30 |
12 |
4 |
3BHKOPTIMA |
86.12 |
1 |
0 |
5 |
3BHKOPTIMA |
86.06 |
1 |
0 |
6 |
1BHK |
45.92 |
1 |
0 |
7 |
1BHK |
42.47 |
1 |
0 |
8 |
2BHKOPTIMA |
51.61 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
EVIVA T
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
90 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
44.72 |
8 |
3 |
2 |
1BHK |
44.35 |
1 |
0 |
3 |
2BHKULTIMA |
56.60 |
1 |
0 |
4 |
2BHKULTIMA |
57.09 |
1 |
0 |
5 |
1BHK |
35.37 |
2 |
2 |
6 |
1BHK |
41.74 |
2 |
2 |
7 |
1BHK |
42.11 |
34 |
31 |
8 |
1BHK |
45.02 |
9 |
4 |
9 |
1BHK |
46.98 |
9 |
7 |
10 |
1BHK |
42.41 |
30 |
20 |
11 |
1BHK |
46.68 |
8 |
7 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
11 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO I
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKULTIMA |
85.21 |
1 |
0 |
2 |
3BHKULTIMA |
85.56 |
1 |
0 |
3 |
2BHKULTIMA |
56.54 |
1 |
0 |
4 |
2BHKULTIMA |
52.86 |
1 |
1 |
5 |
2BHKULTIMA |
63.98 |
1 |
1 |
6 |
2BHKULTIMA |
61.47 |
2 |
2 |
7 |
2BHKULTIMA |
61.79 |
15 |
11 |
8 |
2BHKULTIMA |
64.51 |
8 |
5 |
9 |
2BHKULTIMA |
66.25 |
8 |
6 |
10 |
2BHKULTIMA |
66.04 |
9 |
7 |
11 |
2BHKULTIMA |
61.84 |
15 |
13 |
12 |
2BHKULTIMA |
62.14 |
34 |
29 |
13 |
2BHKULTIMA |
64.30 |
9 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
12 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO A
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
61.84 |
15 |
13 |
2 |
2BHKULTIMA |
66.25 |
8 |
6 |
3 |
2BHKULTIMA |
63.98 |
1 |
0 |
4 |
2BHKULTIMA |
62.14 |
34 |
29 |
5 |
2BHKULTIMA |
61.79 |
15 |
10 |
6 |
2BHKULTIMA |
66.04 |
9 |
9 |
7 |
3BHKULTIMA |
85.21 |
1 |
0 |
8 |
3BHKULTIMA |
85.56 |
1 |
0 |
9 |
2BHKULTIMA |
64.30 |
9 |
0 |
10 |
2BHKULTIMA |
64.51 |
8 |
1 |
11 |
2BHKULTIMA |
52.86 |
1 |
1 |
12 |
2BHKULTIMA |
56.54 |
1 |
1 |
13 |
2BHKULTIMA |
61.47 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
13 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO B
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
65.72 |
1 |
0 |
2 |
3BHKULTIMA |
85.21 |
1 |
0 |
3 |
3BHKULTIMA |
85.56 |
1 |
0 |
4 |
2BHKULTIMA |
63.98 |
1 |
0 |
5 |
2BHKULTIMA |
61.47 |
2 |
2 |
6 |
2BHKULTIMA |
56.54 |
2 |
1 |
7 |
2BHKULTIMA |
61.84 |
15 |
14 |
8 |
2BHKULTIMA |
62.14 |
34 |
27 |
9 |
2BHKULTIMA |
64.30 |
9 |
4 |
10 |
2BHKULTIMA |
66.04 |
9 |
3 |
11 |
2BHKULTIMA |
66.25 |
8 |
4 |
12 |
2BHKULTIMA |
61.79 |
15 |
13 |
13 |
2BHKULTIMA |
64.51 |
8 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
14 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO J
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
15 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO K
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
66.25 |
8 |
6 |
2 |
2BHKULTIMA |
65.72 |
1 |
0 |
3 |
2BHKULTIMA |
64.30 |
9 |
3 |
4 |
2BHKULTIMA |
66.04 |
9 |
4 |
5 |
3BHKULTIMA |
85.21 |
1 |
0 |
6 |
3BHKULTIMA |
85.56 |
1 |
0 |
7 |
2BHKULTIMA |
56.54 |
2 |
0 |
8 |
2BHKULTIMA |
63.98 |
1 |
0 |
9 |
2BHKULTIMA |
61.47 |
2 |
0 |
10 |
2BHKULTIMA |
61.84 |
15 |
10 |
11 |
2BHKULTIMA |
64.51 |
8 |
4 |
12 |
2BHKULTIMA |
62.14 |
34 |
27 |
13 |
2BHKULTIMA |
61.79 |
15 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
16 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO L
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
65.72 |
1 |
0 |
2 |
3BHKULTIMA |
85.21 |
1 |
0 |
3 |
3BHKULTIMA |
85.56 |
1 |
0 |
4 |
2BHKULTIMA |
52.86 |
1 |
0 |
5 |
2BHKULTIMA |
63.98 |
1 |
0 |
6 |
2BHKULTIMA |
61.47 |
2 |
0 |
7 |
2BHKULTIMA |
64.30 |
9 |
5 |
8 |
2BHKULTIMA |
66.04 |
9 |
4 |
9 |
2BHKULTIMA |
64.51 |
8 |
6 |
10 |
2BHKULTIMA |
66.25 |
8 |
2 |
11 |
2BHKULTIMA |
56.54 |
1 |
1 |
12 |
2BHKULTIMA |
61.79 |
15 |
8 |
13 |
2BHKULTIMA |
61.84 |
15 |
13 |
14 |
2BHKULTIMA |
62.14 |
34 |
24 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
17 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO M
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKULTIMA |
85.56 |
1 |
0 |
2 |
2BHKULTIMA |
56.54 |
1 |
0 |
3 |
2BHKULTIMA |
52.86 |
1 |
0 |
4 |
2BHKULTIMA |
63.98 |
1 |
0 |
5 |
2BHKULTIMA |
61.47 |
2 |
0 |
6 |
2BHKULTIMA |
64.30 |
9 |
4 |
7 |
2BHKULTIMA |
66.04 |
9 |
6 |
8 |
2BHKULTIMA |
61.84 |
15 |
13 |
9 |
2BHKULTIMA |
64.51 |
8 |
6 |
10 |
2BHKULTIMA |
66.25 |
8 |
3 |
11 |
2BHKULTIMA |
65.72 |
1 |
0 |
12 |
3BHKULTIMA |
85.21 |
1 |
0 |
13 |
2BHKULTIMA |
62.14 |
34 |
24 |
14 |
2BHKULTIMA |
61.79 |
15 |
7 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
18 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO N
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
63.98 |
1 |
0 |
2 |
2BHKULTIMA |
61.47 |
2 |
0 |
3 |
2BHKULTIMA |
62.14 |
34 |
23 |
4 |
2BHKULTIMA |
66.04 |
9 |
4 |
5 |
2BHKULTIMA |
61.84 |
15 |
10 |
6 |
2BHKULTIMA |
64.51 |
8 |
5 |
7 |
2BHKULTIMA |
66.25 |
8 |
3 |
8 |
2BHKULTIMA |
65.72 |
1 |
0 |
9 |
3BHKULTIMA |
85.21 |
1 |
0 |
10 |
3BHKULTIMA |
85.56 |
1 |
0 |
11 |
2BHKULTIMA |
56.54 |
2 |
0 |
12 |
2BHKULTIMA |
61.79 |
15 |
5 |
13 |
2BHKULTIMA |
64.30 |
9 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
19 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO C
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
65.72 |
1 |
0 |
2 |
3BHKULTIMA |
85.21 |
1 |
0 |
3 |
3BHKULTIMA |
85.56 |
1 |
0 |
4 |
2BHKULTIMA |
63.98 |
1 |
0 |
5 |
2BHKULTIMA |
56.54 |
1 |
1 |
6 |
2BHKULTIMA |
61.79 |
15 |
12 |
7 |
2BHKULTIMA |
62.14 |
34 |
26 |
8 |
2BHKULTIMA |
66.04 |
9 |
2 |
9 |
2BHKULTIMA |
52.86 |
1 |
1 |
10 |
2BHULTIMA |
61.47 |
2 |
2 |
11 |
2BHKULTIMA |
61.84 |
15 |
12 |
12 |
2BHKULTIMA |
64.30 |
9 |
3 |
13 |
2BHKULTIMA |
64.51 |
8 |
6 |
14 |
2BHKULTIMA |
66.25 |
8 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
20 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO O
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
55 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKOPTIMA |
74.81 |
31 |
23 |
2 |
4BHKOPTIMA |
115.82 |
1 |
0 |
3 |
2BHKULTIMA |
65.23 |
2 |
0 |
4 |
3BHKOPTIMA |
75.64 |
2 |
0 |
5 |
3BHKOPTIMA |
74.67 |
34 |
22 |
6 |
1BHK |
41.39 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
21 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO F
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
55 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKOPTIMA |
74.67 |
34 |
13 |
2 |
2BHKULTIMA |
65.23 |
2 |
0 |
3 |
3BHKOPTIMA |
75.64 |
2 |
0 |
4 |
1BHK |
41.39 |
1 |
0 |
5 |
4BHKOPTIMA |
115.82 |
1 |
0 |
6 |
3BHKOPTIMA |
74.81 |
31 |
24 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
22 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO P
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
55 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
41.39 |
1 |
0 |
2 |
4BHKOPTIMA |
115.82 |
1 |
0 |
3 |
2BHKOPTIMA |
65.13 |
1 |
0 |
4 |
2BHKULTIMA |
65.23 |
2 |
0 |
5 |
3BHKOPTIMA |
75.64 |
1 |
0 |
6 |
3BHKOPTIMA |
74.67 |
34 |
16 |
7 |
3BHKOPTIMA |
74.81 |
31 |
25 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
23 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO Q
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHKULTIMA |
61.47 |
2 |
0 |
2 |
2BHKULTIMA |
60.91 |
15 |
8 |
3 |
2BHKOPTIMA |
54.64 |
18 |
1 |
4 |
2BHKOPTIMA |
52.82 |
1 |
0 |
5 |
2BHKOPTIMA |
56.38 |
17 |
0 |
6 |
2BHKULTIMA |
60.96 |
15 |
4 |
7 |
2BHKULTIMA |
61.26 |
34 |
18 |
8 |
3BHKULTIMA |
86.12 |
1 |
0 |
9 |
3BHKULTIMA |
86.47 |
1 |
0 |
10 |
2BHKULTIMA |
56.54 |
1 |
0 |
11 |
2BHKULTIMA |
52.86 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
24 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO R
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
73 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
5BHKOPTIMA |
125.58 |
1 |
0 |
2 |
3BHKULTIMA |
80.27 |
34 |
17 |
3 |
3BHKULTIMA |
82.86 |
30 |
26 |
4 |
3BHKULTIMA |
78.68 |
1 |
0 |
5 |
3BHKULTIMA |
82.24 |
1 |
0 |
6 |
2BHKULTIMA |
70.03 |
1 |
0 |
7 |
2BHKULTIMA |
66.47 |
1 |
0 |
8 |
5BHKULTIMA |
119.61 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
25 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO S
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
73 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKULTIMA |
82.24 |
1 |
0 |
2 |
2BHKULTIMA |
70.03 |
1 |
0 |
3 |
2BHKULTIMA |
66.47 |
1 |
0 |
4 |
2BHKULTIMA |
68.17 |
1 |
0 |
5 |
5BHKULTIMA |
119.61 |
1 |
0 |
6 |
5BHKOPTIMA |
125.58 |
1 |
0 |
7 |
3BHKULTIMA |
80.27 |
34 |
14 |
8 |
3BHKULTIMA |
82.86 |
30 |
27 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
26 |
PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T
|
URBANO T
|
30/06/2019
|
0
|
1
|
0
|
18
|
0 |
16 |
91 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHKULTIMA |
86.12 |
1 |
0 |
2 |
3BHKULTIMA |
86.47 |
1 |
0 |
3 |
2BHKULTIMA |
56.54 |
1 |
0 |
4 |
2BHKULTIMA |
60.96 |
15 |
9 |
5 |
2BHKULTIMA |
61.26 |
34 |
20 |
6 |
2BHKULTIMA |
60.91 |
15 |
7 |
7 |
2BHKOPTIMA |
54.64 |
17 |
4 |
8 |
2BHKOPTIMA |
52.82 |
1 |
0 |
9 |
2BHKOPTIMA |
56.38 |
17 |
1 |
10 |
2BHKULTIMA |
52.86 |
1 |
0 |
11 |
2BHKULTIMA |
61.47 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|