MahaRERA Application

General Information

Other Than Individual

Organization

Bhoomi Associates
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

CTS NO. 25C AND 26A
NEW VANDANA CHS LTD
EKSAR ROAD
BORIVALI WEST
NEAR MAYUR TOWER
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400091

Organization Contact Details

02228984060

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Borivali DiamondResidentialNA968Behind Diamond Talkies L T Road Borivali West Mumbai-400092596-B1392016-04-052015-12-16

Member Information

Member Name Designation Photo
Nirav Bhushan Mehta Partner View Photo
JAYESH JAYANTILAL DOSHI Partner View Photo
DEEPAK KANTILAL SHAH Partner View Photo
DEEPAK KANTILAL SHAH Authorized Signatory View Photo
JAILESH CHAMPAK DALAL Partner View Photo

Project

NEW VANDANA CO-OP HSG. SOC. LTD.
New Project
30/12/2022
No
Others
No
26A and 25C
MUNICIPAL ROAD
CTS NO 27
CTS NO 25A
EXISTING BUILDING MAYUR TOWER
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
EKSAR ROAD
BORIVALI WEST
400091
1176.70
1
1
0
0

FSI Details

2296.04
1724.70
4020.74

Bank Details

CANARA BANK
CNRB0000227

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 60 20 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 WILL BE COMPLETED BEFORE OCCUPATION
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 30 WILL BE COMPLETED BEFORE OCCUPATION
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WILL BE COMPLETED BEFORE OCCUPATION
Fitness Centre : YES 0 NA
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 CONNECTION AFTER OCCUPATION
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 40 WILL BE COMPLETED BEFORE OCCUPATION
Storm Water Drains : YES 40 NA
Landscaping & Tree Planting : YES 0 NA
Street Lighting : YES 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NEW VANDANA CO-OP HSG. SOC. LTD. NEW VANDANA 31/12/2021 0 1 0 17 1 0 60
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 11.99 1 1
2 SHOP 13.48 1 1
3 SHOP 22.63 1 1
4 1RK 20.34 1 1
5 1RK 22.65 2 2
6 1BHK 33.22 2 2
7 2BHK 63.74 1 1
8 2BHK 64.42 3 3
9 3BHK 80.21 1 1
10 4BHK 89.49 1 1
11 4BHK 89.76 2 2
12 4BHK 92.91 2 2
13 4BHK 95.45 1 1
14 1BHK 35.74 1 0
15 2BHK 54.10 8 0
16 SHOP 14.25 1 0
17 1BHK 43.37 2 2
18 2BHK 45.66 1 1
19 2BHK 63.62 2 2
20 2BHK 54.61 5 5
21 2BHK 48.94 8 4
22 2BHK 59.75 9 6
23 3BHK 82.69 7 2
24 3BHK 83.20 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 75
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 55
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

65
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 61

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Shree Krishna Interbuild NA Contractor
Synergy Architect NA Architect
M/s.Kaushik Patel (KPA) NA Architect
M/s Hiren M Tanna NA Engineer
Mr. Bakulesh J. Mehta NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement