Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1GANGA GLITZResidentialNA10926.39SR NO 16P AND 17 P UNDRI PUNE 16 P AND 17 P21922018-04-022017-04-29
2GANGA SPARSHResidentialNA6472.18SR NO 16 P AND 17 P UNDRI PUNE 16 P AND 17 P 21542014-04-012013-11-16
3GANGA ARCADIA OthersRESIDENTIAL AND COMMERCIAL 4279.49SR NO 22 HISSA NO 2 PLOT A KHARADI PUNE 411014SR NO 22 HISSA NO 2 PLOT A11202015-12-012015-10-31
4GANGA ARCADIA OthersRESIDENTIAL AND COMMERCIAL 2257.41SR NO 22 HISSA NO 2 PLOT A KHARADI PUNE 411014SR NO 22 HISSA NO 2 PLOT A 1282017-06-302017-06-28
5AMRUTGANGAOthersRESIDENTIAL AND COMMERCIAL40000VADGAON BK PUNE SR NO 35/1,36,37/2A,38/1,39/1B,41/1B96112013-12-302013-10-28

Member Information

Member Name Designation Photo
AMIT JAIPRAKASH GOEL Director View Photo
ATUL JAIPRAKASH GOEL Director View Photo
JAIPRAKASH RAMRATAN BAJARI Authorized Signatory View Photo

Project

GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N
New Project
30/06/2025
Yes
Residential
No
SR NO 16 P AND 17 P UNDRI PUNE
12 M WIDE ROAD
24 M WIDE PROPOSED ROAD
SR NO 16 P AND 17 P
12 M WIDE ROAD
MAHARASHTRA
Pune
Pune
Haveli
KADNAGAR
UNDRI
411060
9849.53
6
1
5
984.9

FSI Details

7161.30
30000
37161.30

Bank Details

ICICI
ICIC0004103

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 140 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 AS PER ARCHITECT CERTIFICATE
Water Conservation, Rain water Harvesting : YES 0 AS PER ARCHITECT CERTIFICATE
Energy management : YES 0 AS PER ARCHITECT CERTIFICATE
Fire Protection And Fire Safety Requirements : YES 0 AS PER ARCHITECT CERTIFICATE
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 AS PER ARCHITECT CERTIFICATE
Aggregate area of recreational Open Space : YES 0 AS PER ARCHITECT CERTIFICATE
Open Parking : NO 0 NA
Water Supply : YES 0 AS PER ARCHITECT CERTIFICATE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER ARCHITECT CERTIFICATE
Storm Water Drains : YES 0 AS PER ARCHITECT CERTIFICATE
Landscaping & Tree Planting : YES 0 AS PER ARCHITECT CERTIFICATE
Street Lighting : YES 0 AS PER ARCHITECT CERTIFICATE
Community Buildings : YES 100 AS PER ARCHITECT CERTIFICATE
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER ARCHITECT CERTIFICATE
Solid Waste Management And Disposal : YES 100 AS PER ARCHITECT CERTIFICATE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N BUILDING J 1 -10 FLOORS 31/12/2024 0 1 0 10 1 0 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 43.57 40 38
2 1BHK 28.77 79 76
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 97
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 72
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 96
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 51
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80.6
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N BUILDING J 11-15 FLOORS and STILT 31/12/2024 0 0 0 6 0 0 8
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 27.8 2 0
2 1BHK 27.83 2 0
3 1BHK 28.77 43 43
4 2BHK 43.57 22 22
5 2BHK 42.79 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 79
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 96
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

75
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 83
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N BUILDING K 1-14 FLOORS and stilt , 15 th floor 31/12/2024 0 1 0 14 1 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 28.19 4 0
2 2BHK 43.37 2 2
3 2BHK 43.57 62 61
4 2BHK 60.39 62 62
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 42
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N BUILDING L 1-14 FLOORS, STILT AND 15 TH FLOOR 31/12/2024 0 1 0 16 1 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 118.48 32 32
2 2BHK 59.61 32 29
3 3BHK 99.23 16 16
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N BUILDING M 1-14 FLOORS , STILT AND 15 TH FLOOR 31/12/2024 0 1 0 16 1 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.61 64 61
2 3BHK 118.48 32 32
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 30
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 13
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N BUILDING N 1-14 FLOORS, STILT AND 15 TH FLOOR 31/12/2024 0 1 0 15 1 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.61 32 31
2 3BHK 118.48 32 32
3 3BHK 119.02 16 16
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 6
4 Stilt Floor 26
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 23.2

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SHINDE PLUMBING CONTRACTOR NA Contractor
SPACE DESIGNER SYNDICATE NA Architect
I M PATEL NA Engineer
A K CHANDERIA &CO NA Chartered Accountant
G A BHILARE CONSULTANT PVT LTD STRUCTURAL CONSULTANT NA Other Professional
URJAL CONSULTANT PVT LTD PLUMBING CONSULTANT NA Other Professional
ZOPATE ELECTRICAL CONSULTANT PVT LTD NA Other Professional
Square Yards Consulting Private Limited A09600037017 Real Estate Agent
ABDULLA FAKHRUDDIN A52100030780 Real Estate Agent
pritesh amrutlal kankariya A52200009618 Real Estate Agent
CORAZON HOMES AND SECURITIES A52100000096 Real Estate Agent
HUSAIN LAKHTARWALA A51700008084 Real Estate Agent
Sagar Devidas Wani A52100022645 Real Estate Agent
Hussain Abbas A52100033449 Real Estate Agent
Prop Rising A52100028949 Real Estate Agent
Ganesh Ramesh Shrivardhankar A52800033469 Real Estate Agent
Paresh Sureshrao Mamidwar A52100038204 Real Estate Agent
Ramsharan Madho Mandal A52100019330 Real Estate Agent
Nobroker Technologies Solutions Private Limited A51800026821 Real Estate Agent
Amrit Nandkishore Suri A52100034791 Real Estate Agent
Latifa Munaf Inamdar A52100005347 Real Estate Agent
Hrishikesh Sargar A52100020118 Real Estate Agent
PREM RAMAKANT MANE A52100035478 Real Estate Agent
Amol Dilip Godse A52100004553 Real Estate Agent
KUMAR GAURAV SINGH A52100013994 Real Estate Agent
VIVEK SUNIL KADUSKAR A52100026801 Real Estate Agent
STANDFORD REAL ESTATE LLP A52100032868 Real Estate Agent
IMRAN IBRAHIM SHAIKH A52100021505 Real Estate Agent
Mohinderpal Singh Wahan A52100016021 Real Estate Agent
Anis Shergadwala A52100004465 Real Estate Agent
CHANDRAKANT VITHAL GAIKWAD A52100002273 Real Estate Agent
Taher Ali Fakhruddin Bapu A52100022696 Real Estate Agent
Paresh Sureshrao Mamidwar A52100038204 Real Estate Agent
SANA WASIM SHAIKH A52100032204 Real Estate Agent
ASGHAR ALI NOMANI A52100039156 Real Estate Agent
Abhishek Ashok Tripathi A52100026024 Real Estate Agent
SANKALP SANJAY BHANDARE A52100032764 Real Estate Agent
Mustafa Mufazzal kachwala A52100013856 Real Estate Agent
MUJAMMIL LAYAKALI PATHAN A52100032348 Real Estate Agent
Pooja Santosh Kale A52100028109 Real Estate Agent
DEEGEE REALTY ADVISORS PRIVATE LIMITED A52100031355 Real Estate Agent
Juzer Firoz Karbalai A52100025782 Real Estate Agent
Apna Ghar Lifespaces LLP A52100008848 Real Estate Agent
SHIVAJI BALWANT SHINDE A52100016572 Real Estate Agent
Mehran Anjum Parwani A52100009891 Real Estate Agent
Shakruddin Mujawar A52100000742 Real Estate Agent
MANISH C KANKARIA A52100004190 Real Estate Agent
DWELLING RBS (OPC) PRIVATE LIMITED A52100041641 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 666 Civil No Suit NA 2013 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 361 Civil No Suit NA 2015 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 64 Civil No Suit NA 2013 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 699 Civil No Suit NA 2014 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 357 Civil No Suit NA 2015 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 1901 Civil No Suit NA 2015 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 1157 Civil No Suit NA 2019 PENDING
NA
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N CIVIL COURT PUNE 32 Civil No Suit NA 2016 PENDING
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement