MahaRERA Application

General Information

Other Than Individual

Organization

BRAMHA MULTICON PVT LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

250 /251
BRAMHA HOUSE
M.G. ROAD
PUNE
NEAR KOHINOOR RESTRAUNT
MAHARASHTRA
Pune
Pune
Pune City
Pune (CB)
411001

Organization Contact Details

02026330485
WWW.BRAMHAREALTY.IN

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1BRAMHA SKYCITY PHASE- 1ResidentialNA18931.78SERVEY.NO 25 25A VILAGE- DHANORI TALUKA- HAVELI DIST- PUNE25 25A62702016-09-302016-09-30
2BRAMHA SKYCITY PHASE- 1ResidentialNA18931.78SERVEY.NO 25 25A VILAGE- DHANORI TALUKA- HAVELI DIST- PUNE25 25A62532016-09-302017-07-28

Member Information

Member Name Designation Photo
VISHAL SURENDRAKUMAR AGRAWAL Authorized Signatory View Photo
VISHAL SURENDRAKUMAR AGARWAL Managing Director View Photo
SURENDRAKUMAR BRAMHADUTT AGRAWAL Chairperson View Photo
SURENDRAKUMAR BRAMHADUTT AGRAWAL Authorized Signatory View Photo
Shivani Vishal Agarwal Director View Photo

Project

BRAMHA SKYCITY PHASE 3
New Project
01/04/2026
Yes
Residential
Yes
25 AND 25A
NALA GARDEN
INTERNAL PROJECT ROAD
INTERNAL PROJECT ROAD
INTERNAL PROJECT ROAD
MAHARASHTRA
Pune
Pune
Haveli
DHANORI
DHANORI VILLAGE ROAD
DHANORI
411014
4098.74
2
2
0
409.87

FSI Details

6993.16
2732.72
9725.88

Bank Details

UNION BANK OF INDIA
UBIN0907006

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
BRAMHA SKYCITY PHASE 3 VISHNU CO-OPERATIVE HOUSING SOCIETY LIMITED Societies Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 92 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 YET TO START
Water Conservation, Rain water Harvesting : YES 0 YET TO START
Energy management : YES 0 YET TO START
Fire Protection And Fire Safety Requirements : YES 0 YET TO START
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 YET TO START
CLUB HOUSE AND GYM : YES 0 COMMON FOR PROJECT
SWIMMING POOL : YES 0 COMMON FOR PROJECT
Aggregate area of recreational Open Space : YES 0 YET TO START
Open Parking : YES 0 YET TO START
Water Supply : YES 0 YET TO START
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 YET TO START
Storm Water Drains : YES 0 YET TO START
Landscaping & Tree Planting : YES 0 YET TO START
Street Lighting : YES 0 YET TO START
Community Buildings : YES 0 COMMON COMMUNITY BUILDING FOR THE PROJECT
Treatment And Disposal Of Sewage And Sullage Water : YES 0 YET TO START
Solid Waste Management And Disposal : YES 0 YET TO START

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 BRAMHA SKYCITY PHASE 3 S1 31/01/2026 1 1 0 14 1 0 46
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 64.97 11 0
2 2BHK 64.90 24 0
3 3BHK 78.95 11 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 00
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 BRAMHA SKYCITY PHASE 3 S2 31/01/2026 1 1 0 14 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 78.95 11 0
2 2BHK 64.90 24 0
3 2BHK 64.97 11 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
REZA KABUL ARCHITECTS PVT LTD NA Architect
J W CONSULTANT LLP NA Engineer
SUPRIYA ABHIJIT MUNDADA NA Chartered Accountant
REALIST HOMES A52100042967 Real Estate Agent
S P REALTY A52100040822 Real Estate Agent
Ashwin Ambadas Satpute A52100038463 Real Estate Agent
NASREEN MERCHANT A52100038960 Real Estate Agent
TUSHAR SHIVAJI BHINGARDIVE A52100028267 Real Estate Agent
SHUBHAM AVINASH GHORPADE A52100034548 Real Estate Agent
Sohail Salim Lakhamsey A52100030747 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
11 Disclosure of sold/ booked inventory
12 Disclosure of sold/ booked inventory
13 Disclosure of sold/ booked inventory
14 Disclosure of sold/ booked inventory
15 Disclosure of sold/ booked inventory
16 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement