Common areas And Facilities, Amenities |
Available |
Percent |
Details |
Internal Roads & Footpaths :
|
YES
|
100
|
Common for Banglow and Bhumi Kshitij of 9 mtrs wid
|
Internal Roads & Footpaths :
|
YES
|
100
|
Common for Banglow and Bhumi Kshitij of 9 mtrs wid
|
Internal Roads & Footpaths :
|
YES
|
100
|
Common for Banglow and Bhumi Kshitij of 9 mtrs wid
|
Water Conservation, Rain water Harvesting :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Water Conservation, Rain water Harvesting :
|
YES
|
0
|
Will be completed on completion
|
Energy management :
|
YES
|
0
|
Prov solar wtr heater connection in common bthroom
|
Energy management :
|
YES
|
0
|
Solar
|
Fire Protection And Fire Safety
Requirements :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Fire Protection And Fire Safety
Requirements :
|
YES
|
0
|
Will be completed on completion
|
Electrical Meter Room, Sub-Station, Receiving Station :
|
YES
|
0
|
Will be completed as per MSEDCL Norms
|
Electrical Meter Room, Sub-Station, Receiving Station :
|
YES
|
0
|
Will be completed on completion
|
GYM AREA WITHIN THE PREMISES ON FIRST FLOOR :
|
YES
|
00
|
AS PER IOD SANCTION
|
GYM AREA WITHIN THE PREMISES ON FIRST FLOOR :
|
YES
|
30
|
AS PER IOD SANCTION
|
Aggregate area of recreational Open Space :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Aggregate area of recreational Open Space :
|
YES
|
0
|
Will be completed on completion
|
Open Parking :
|
NO
|
0
|
NA
|
Water Supply :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Water Supply :
|
YES
|
0
|
Will be completed on completion
|
Sewerage (Chamber, Lines, Septic Tank , STP) :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Sewerage (Chamber, Lines, Septic Tank , STP) :
|
YES
|
25
|
Will be completed as per PCMC Norms
|
Sewerage (Chamber, Lines, Septic Tank , STP) :
|
YES
|
50
|
Will be completed on completion
|
Storm Water Drains :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Storm Water Drains :
|
YES
|
0
|
Will be completed on completion
|
Landscaping & Tree Planting :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Landscaping & Tree Planting :
|
YES
|
0
|
Will be completed on completion
|
Street Lighting :
|
YES
|
0
|
Will be completed
|
Street Lighting :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Community Buildings :
|
NO
|
0
|
NA
|
Treatment And Disposal Of Sewage And Sullage Water :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Treatment And Disposal Of Sewage And Sullage Water :
|
YES
|
50
|
Will be completed as per PCMC Norms
|
Treatment And Disposal Of Sewage And Sullage Water :
|
YES
|
50
|
Will be completed on completion
|
Solid Waste Management And Disposal :
|
YES
|
0
|
Will be completed as per PCMC Norms
|
Solid Waste Management And Disposal :
|
YES
|
20
|
Will be completed as per PCMC Norms
|
Solid Waste Management And Disposal :
|
YES
|
20
|
Will be completed on completion
|