MahaRERA Application

General Information

Other Than Individual

Organization

AASHIYANA BUILDERS ANDDEVELOPERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

PLOT NO 11
MAHAVEER NAGAR
BAZAR PETH
BADLAPUR WEST
NEAR AMBE MATA MANDIR
MAHARASHTRA
Konkan
Thane
Ambarnath
Badlapur (M Cl)
421503

Organization Contact Details

09011084144

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1KHATRI GRAND BUILDING 4 TO 6ResidentialNA3562.26SHIRGAON BADLAPUR EASTS NO 37 Hissa no 2 and 3 s no 38 Hissa no 431062015-03-312015-04-20
2KHATRI GRANDE BUILDING 1 TO 3ResidentialNA2882.95SHIRGAON BADLAPUR EASTS NO 37 HISSA NO 2 AND 3 S NO 38 HOSSA NO43742014-01-312014-01-07

Member Information

Member Name Designation Photo
ASHOK GAURICHAND KHATRI Authorized Signatory View Photo
JAYSHREE ASHOK KHATRI Partner View Photo
ASHOK GAURICHAND KHATRI H U F Partner View Photo

Project

KHATRI GRANDE
On-Going Project
31/12/2019
31/12/2019
No
Others
Yes
S NO 37 HISSA NO 2 AND 3 S NO 38 HISSA NO4
S NO 38
ADJOINING EXISTING ROAD
S NO 37 HISSA NO 2
S NO 38 HISSA NO 3 AND 4
MAHARASHTRA
Konkan
Thane
Ambarnath
Badlapur (M Cl)
421503
4364.76
2
2
0
0

FSI Details

4364.76
0
4364.76

Bank Details

THE FEDERAL BANK LTD
FDRL0001755

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
KHATRI GRANDE PADMANABH PURSHOTTAM APTE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WORK YET NOT STARTED
Water Conservation, Rain water Harvesting : YES 0 RAIN WATER HARVESTING WORK YET NOT STARTED
Energy management : YES 0 SOLAR PANEL WORK YET NOT STARTED
Fire Protection And Fire Safety Requirements : YES 0 WORK YET NOT STARTED
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 TRANSFORMER HAS BEEN INSTALLED
Aggregate area of recreational Open Space : YES 50 PARTLY O S AREA COMPLETED OF PLOT B
Open Parking : YES 0 WORK YET NOT STARTED
Water Supply : YES 0 DRINKING WATER PROVIDED BY MJPWN AFTER O C
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 MUNICIPAL SEWERAGE LINES PROVIDED
Storm Water Drains : YES 0 WORK YET NOT STARTED
Landscaping & Tree Planting : YES 0 TREE PLANTING WORK YET NOT STARTED
Street Lighting : YES 0 MUNICIPAL STREET LIGHTH PROVIDED
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 KHATRI GRANDE KHATRIGRANDE BUILDING 7 31/12/2019 0 1 0 8 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 6.46 2 0
2 SHOP 7.29 1 0
3 SHOP 11.44 2 0
4 SHOP 11.64 1 0
5 SHOP 15.22 4 0
6 1 BHK 27.65 14 0
7 1 BHK 28.11 14 1
8 SHOP 10.82 2 2
9 1 BHK 27.90 28 1
10 SHOP 10.28 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 35
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 KHATRI GRANDE KHATRI GRANDE BUILDING 8 31/12/2019 0 1 0 8 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 7.29 1 0
2 SHOP 10.82 2 2
3 SHOP 11.64 1 1
4 SHOP 6.46 2 2
5 SHOP 11.44 2 1
6 SHOP 15.22 4 2
7 1 BHK 27.65 14 11
8 SHOP 10.28 2 2
9 1 BHK 28.11 14 11
10 1 BHK 27.90 28 26
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RAJ ASSOCITES ARCHITECT AND ENGINEERS NA Architect
Shiv prasad Maurya A51700002135 Real Estate Agent
HARSHAD MAHENDRA KAMBLE A51700011666 Real Estate Agent
SANDEEP KHAZAN MATHUR A51800000290 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement