MahaRERA Application

General Information

Other Than Individual

Organization

Rohan Developers Pvt Ltd
Company
NA
Do you have any Past Experience ?
Yes

Address Details

12/14
Gordhan Building No II
Parekh Street
Prarthna Samaj
Opp Sir H.N. Reliance Hospital
MAHARASHTRA
Konkan
Mumbai City
Ward ABCD
ABCD-400004
400004

Organization Contact Details

02266579999

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Lifescapes AashianaResidentialNA1920.58Nepean Sea Road1/5781412014-12-312016-06-22

Member Information

Member Name Designation Photo
Harresh Navnitrai Mehta Managing Director View Photo
Anuj Jitendra Mehta Authorized Signatory View Photo
Rohan Jitendra Mehta Authorized Signatory View Photo

Project

Lifescapes Shubham
On-Going Project
30/06/2022
30/06/2023
Yes
Residential
No
585, 588, 589
By Bearing CTS No 1 by 521 of Girgaum division
By Bearing CTS No 584 of Girgaum division
By Bearing CTS No 587 of Girgaum
By Bearing CTS No 543 of Girgaum divisio
MAHARASHTRA
Konkan
Mumbai City
Ward ABCD
ABCD-400004
VP ROAD
PRARTHNA SAMAJ
400004
5272.61
3
3
0
419.58

FSI Details

0
31122.15
31122.15

Bank Details

HDFC Bank
HDFC0000423

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 235 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 NA
Water Conservation, Rain water Harvesting : YES 50 80 % bldg no. 1
Energy management : YES 0 NA
Fire Protection And Fire Safety Requirements : YES 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 NA
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 NA
Storm Water Drains : YES 0 NA
Landscaping & Tree Planting : YES 0 NA
Street Lighting : YES 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 NA
Solid Waste Management And Disposal : YES 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Lifescapes Shubham Lifescapes Shubham 30/06/2022 1 1 5 29 1 0 302
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 78.32 23 15
2 2 BHK 80.33 23 16
3 2 BHK 80.54 23 13
4 2 BHK 81.15 23 12
5 2BHK 86.75 4 0
6 2BHK 86.62 4 0
7 3 BHK 105.96 27 16
8 3 BHK 106.26 27 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 80
4 Stilt Floor 70
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Lifescapes Shubham Lifescapes Amrut 1 1 0 23 1 0 25
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 34.07 1 0
2 1 RK 37.06 1 0
3 1 RK 39.42 1 0
4 1 RK 40.20 1 0
5 1 RK 43.18 1 0
6 1 RK 43.87 1 0
7 1 BHK 46.29 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 95
3 X number of Podiums 0
4 Stilt Floor 70
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 65
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

50
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 63
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Lifescapes Shubham Lifescapes Amrut Annex 0 1 0 1 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Nil 0 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
M/s. 1 Architectural Consultants NA Architect
M/s. Design Group NA Architect
Mr. Nikhil Shanghvi NA Engineer
EDELWEISS COMMODITIES SERVICES LIMITED A51800001072 Real Estate Agent
Sila South Mumbai Projects LLP A51800019893 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Lifescapes Shubham Small Causes Court at Bombay 307/450 Civil No Suit NA 2003 Matter is part heard
NA
Lifescapes Shubham Small Causes Court at Bombay 520 Civil No Suit NA 2014 Matter is part heard
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
1 Declaration about Commencement Certificate
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of the allotment letter and agreement for sale
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical