Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
PLANET 6
|
A WING
|
31/12/2026
|
0
|
1
|
0
|
12
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
26.46 |
14 |
0 |
2 |
1BHK |
26.54 |
7 |
0 |
3 |
1BHK |
27.94 |
8 |
0 |
4 |
2BHK |
42.88 |
18 |
0 |
5 |
2BHK |
43.26 |
18 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
PLANET 6
|
B WING
|
31/12/2026
|
0
|
1
|
0
|
12
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
42.87 |
16 |
0 |
2 |
2BHK |
42.89 |
16 |
0 |
3 |
3BHK |
62.96 |
9 |
0 |
4 |
3BHK |
64.89 |
9 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
PLANET 6
|
C WING
|
31/12/2026
|
0
|
1
|
1
|
12
|
3 |
16 |
385 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
28.38 |
14 |
0 |
2 |
2BHK |
42.19 |
14 |
0 |
3 |
2BHK |
44.07 |
36 |
0 |
4 |
2BHK |
46.25 |
7 |
0 |
5 |
Shop |
16.36 |
1 |
0 |
6 |
Office space |
18.48 |
1 |
0 |
7 |
Shop |
25.25 |
1 |
0 |
8 |
Office space |
27.04 |
1 |
0 |
9 |
Office space |
30.60 |
1 |
0 |
10 |
Shop |
30.72 |
2 |
0 |
11 |
Office space |
32.52 |
1 |
0 |
12 |
Shop |
33.87 |
1 |
0 |
13 |
Shop |
39.42 |
1 |
0 |
14 |
Office space |
39.83 |
4 |
0 |
15 |
Shop |
40.35 |
4 |
0 |
16 |
Shop |
44.05 |
1 |
0 |
17 |
Shop |
44.14 |
1 |
0 |
18 |
Shop |
45.39 |
1 |
0 |
19 |
Shop |
46.20 |
2 |
0 |
20 |
Office space |
47.20 |
3 |
0 |
21 |
Shop |
48.31 |
1 |
0 |
22 |
Shop |
56.85 |
1 |
0 |
23 |
Shop |
57.55 |
1 |
0 |
24 |
Office space |
58.41 |
2 |
0 |
25 |
Shop |
63.99 |
1 |
0 |
26 |
Shop |
73.97 |
1 |
0 |
27 |
Office space |
34.14 |
1 |
0 |
28 |
Office space |
35.40 |
8 |
0 |
29 |
Shop |
37.95 |
1 |
0 |
30 |
Office space |
38.64 |
4 |
0 |
31 |
Shop |
49.26 |
1 |
0 |
32 |
Shop |
50.72 |
1 |
0 |
33 |
Shop |
50.73 |
1 |
0 |
34 |
Shop |
51.40 |
1 |
0 |
35 |
Shop |
52.02 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
PLANET 6
|
D WING
|
31/12/2026
|
0
|
1
|
0
|
12
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
38.57 |
8 |
0 |
2 |
2BHK |
42.84 |
1 |
0 |
3 |
2BHK |
42.87 |
15 |
0 |
4 |
3BHK |
64.85 |
9 |
0 |
5 |
3BHK |
64.87 |
9 |
0 |
6 |
2BHK |
38.73 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
PLANET 6
|
E WING
|
31/12/2026
|
0
|
1
|
0
|
12
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
27.99 |
8 |
0 |
2 |
1BHK |
28.00 |
25 |
0 |
3 |
1BHK |
26.50 |
14 |
0 |
4 |
1BHK |
26.54 |
7 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
PLANET 6
|
F WING
|
31/12/2026
|
0
|
1
|
0
|
12
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
26.46 |
14 |
0 |
2 |
1BHK |
26.54 |
4 |
0 |
3 |
1BHK |
27.93 |
1 |
0 |
4 |
1BHK |
27.98 |
7 |
0 |
5 |
1BHK |
26.17 |
3 |
0 |
6 |
2BHK |
42.88 |
18 |
0 |
7 |
2BHK |
43.26 |
18 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|