MahaRERA Application

General Information

Other Than Individual

Organization

ASHAPURA COMBINES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

SHOP NO 4
VIKRAM APARTMENT
NEW MANEKLAL ESTATE
GHATKOPAR WEST
NEW MANEKLAL ESTATE
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400086

Organization Contact Details

02225155333

Past Experience Details

Member Information

Member Name Designation Photo
RITESH HARILAL SANGHANI Authorized Signatory View Photo
HARILAL NATHU PATEL Partner View Photo
VIPUL HARILAL PATEL Partner View Photo
ASHAPURA ENTERPRISES PRIVATE LIMITED COMPANY Partner View Photo
MANGESH DASHRATH GAIKAR Partner View Photo

Project

NEELKANTH SHRUSHTI
On-Going Project
31/12/2020
30/12/2021
No
Residential
No
SURVEY NO 86,88,90
18 MTR D P ROAD
S NO 91
ANAND SAGAR BLG
15 MTR D P ROAD
MAHARASHTRA
Konkan
Thane
Kalyan
Kalyan-Dombivali (M Corp.)
421301
4860
2
2
0
0

FSI Details

4860
0
4860.00

Bank Details

BANK OF BARODA
BARB0GHAWES

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 COMPLETED
Water Conservation, Rain water Harvesting : YES 100 COMPLETED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 COMPLETED
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 COMPLETED
CLUB HOUSE : YES 100 COMPLETED
Aggregate area of recreational Open Space : YES 100 COMPLETED
Open Parking : YES 100 COMPLETED
Water Supply : YES 100 COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 COMPLETED
Storm Water Drains : YES 100 COMPLETED
Landscaping & Tree Planting : YES 100 COMPLETED
Street Lighting : YES 100 COMPLETED
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NEELKANTH SHRUSHTI AMARNATH A B WING 31/12/2020 0 1 0 11 1 24 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 40.54 5 0
2 1 BHK 40.68 5 4
3 1 BHK 40.69 5 4
4 1 BHK 40.83 5 4
5 2 BHK 55.88 5 0
6 2 BHK 56.06 5 1
7 2 BHK 56.51 5 1
8 2 BHK 56.68 5 2
9 2 BHK 56.69 5 4
10 2 BHK 56.86 5 2
11 2 BHK 57.16 5 3
12 2 BHK 57.17 4 1
13 2 BHK 57.28 5 0
14 2 BHK 57.46 5 0
15 2 BHK 57.76 5 0
16 2 BHK 57.77 4 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 NEELKANTH SHRUSHTI VAIDYANATH 0 1 0 8 1 10 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 36.67 8 0
2 1 BHK 39.76 4 0
3 1 BHK 40.85 9 0
4 2 BHK 50.40 4 0
5 2 BHK 50.84 3 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
CREDIBLE DESIGNS NA Architect
KHR & CO NA Chartered Accountant
Shanti consultants NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement