MahaRERA Application

General Information

Other Than Individual

Organization

EKTA PARKSVILLE HOMES PVT. LTD.
Company
NA
Do you have any Past Experience ?
No

Address Details

401
HALLMARK BUSINESS PLAZA
SANT DYANESHWAR MARG
KALANAGAR, BANDRA EAST
OPP. GURUNANAK HOSPITAL
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400051

Organization Contact Details

02261152424
WWW.EKTAWORLD.COM

Past Experience Details

Member Information

Member Name Designation Photo
CHANDRA PRAKASH GOYAL Authorized Signatory View Photo
DILIP LAXMAN BORHADE Director View Photo
PRAKASH TRIBHUVANDAS TANNA Director View Photo

Project

EKTA PARKSVILLE PHASE I
On-Going Project
31/12/2019
31/12/2019
31/03/2023
Yes
Residential
No
96/178, 7A PT/7B PT, 93/177/1/2 PT, 94/182 7A PT / 7B PT, 93/177, 96/178 PT
12 METER WIDE ROAD
SUREY NO 93-178 PT 94-178 PT 96-178 PT
20 METER WIDE DP ROAD
SURVEY NO 91-176 PT 93-177 PT
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
Near Yazoo Park
Virar
401303
2842.89
9
9
0
1043.21

FSI Details

26078.7
0
26078.70

Bank Details

HDFC BANK LTD
HDFC0000835

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 655 175 90

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 COMPLETED
Energy management : YES 100 SOLAR LIGHTS PROVIDED ONLY ON LANDSCAPE AREA
Fire Protection And Fire Safety Requirements : YES 100 Work In Progress
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 COMPLETED
Children Play Area : YES 100 To Be Handed Over to Apex Body
Gazebo : YES 100 To Be Handed Over to Apex Body
Jogging Track : YES 100 To Be Handed Over to Apex Body
Shrub Beds : YES 100 To Be Handed Over to Apex Body
Aggregate area of recreational Open Space : YES 100 COMPLETED
Open Parking : NO 0 NA
Water Supply : YES 100 COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 COMPLETED.
Storm Water Drains : YES 100 COMPLETED.
Landscaping & Tree Planting : YES 100 COMPLETED
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 WORK IN PROGRESS
Solid Waste Management And Disposal : YES 100 OWN MACHINE INSTALLED

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 EKTA PARKSVILLE PHASE I CENTRAL PARK A WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP42E 19.99 1 1
2 SHOP42F 24.80 1 1
3 SHOP42B 18.55 1 1
4 1BHK 31.43 28 28
5 1BHK 34.60 28 28
6 SHOP42A 21.94 1 1
7 SHOP42C 23.06 1 1
8 SHOP42D 23.68 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 83
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 EKTA PARKSVILLE PHASE I CENTRAL PARK B WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP38 19.85 1 1
2 1BHK 34.60 28 28
3 SHOP37 17.05 1 1
4 SHOP39 20.37 1 1
5 SHOP40 17.18 1 1
6 1 BHK 31.43 28 28
7 SHOP41 21.38 1 1
8 SHOP36 20.55 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 83
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 EKTA PARKSVILLE PHASE I CENTRAL PARK C WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP31 14.88 1 1
2 SHOP22 13.16 1 1
3 SHOP23 12.29 1 1
4 SHOP24 14.35 1 1
5 SHOP33 19.84 1 1
6 SHOP32 16.83 1 1
7 SHOP28 13.61 1 1
8 2BHK 45.00 15 15
9 3BHK 74.28 15 15
10 SHOP29 7.49 1 1
11 1 BHK 34.60 56 56
12 SHOP34 15.34 1 1
13 SHOP35 20.03 1 1
14 SHOP25 13.19 1 1
15 SHOP26 17.42 1 1
16 SHOP27 16.28 1 1
17 SHOP30 16.39 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 89
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 EKTA PARKSVILLE PHASE I CENTRAL PARK D WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP18 15.26 1 1
2 SHOP19 15.69 1 1
3 1BHK 34.60 28 28
4 SHOP20 13.24 1 1
5 SHOP21 16.47 1 1
6 1BHK 31.43 28 28
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 89
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 EKTA PARKSVILLE PHASE I CENTRAL PARK E WING 31/12/2019 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP9 14.77 1 1
2 SHOP16 14.44 1 1
3 SHOP17 14.86 1 1
4 SHOP11 10.21 1 1
5 SHOP12 13.93 1 1
6 SHOP13 12.67 1 1
7 SHOP14 15.13 1 1
8 SHOP15 11.79 1 1
9 SHOP10 11.79 2 2
10 2 BHK 50.70 56 56
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 84
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 EKTA PARKSVILLE PHASE I CENTRAL PARK F WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.43 56 56
2 SHOP2 11.09 1 1
3 2BHK 50.70 28 28
4 SHOP3 19.14 1 1
5 SHOP3 19.14 1 1
6 SHOP4 11.08 1 1
7 SHOP5 8.94 1 1
8 2BHK 45.00 15 15
9 SHOP6 19.04 1 1
10 SHOP1 14.46 1 1
11 SHOP7 12.36 1 1
12 SHOP8 16.92 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 88
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.8
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
7 EKTA PARKSVILLE PHASE I CENTRAL PARK G WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.43 54 54
2 2BHK 45.00 14 14
3 3 BHK 74.28 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 84
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
8 EKTA PARKSVILLE PHASE I CENTRAL PARK H WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 50.70 12 12
2 2 BHK 47.30 14 14
3 2 BHK 47.98 28 28
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 82
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
9 EKTA PARKSVILLE PHASE I CENTRAL PARK K WING 31/12/2019 0 1 0 16 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 43.52 14 13
2 2BHK 43.45 12 7
3 2 BHK 43.63 14 12
4 2BHK 48.47 14 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AJAY WADE & ASSOCIATES NA Architect
JM Financial Products Limited A51900000277 Real Estate Agent
SANDEEP SURYANATH DUBEY A99000010980 Real Estate Agent
VAIBHAV RAMESH KULKARNI A51700003316 Real Estate Agent
RAJNIKANT M SHETH A51800002278 Real Estate Agent
SHIVSHAKTI KAMLESH SINGH A51800002793 Real Estate Agent
RAKESH SHARMA A51800006030 Real Estate Agent
MINERVA PROPERTIES A51800010405 Real Estate Agent
DINESH JANGID A51800010411 Real Estate Agent
RANJEET NAIPAL YADAV A51800011251 Real Estate Agent
KEY MANSIONS PRIVATE LIMITED A51900001761 Real Estate Agent
Vipul Harinder singh A51900006416 Real Estate Agent
Manish Manohar Lanjewar A51900014561 Real Estate Agent
VINAY SINGH A51900015465 Real Estate Agent
MOSES THOMAS NADAR A99000000329 Real Estate Agent
SUNIL NAMDEO MOTWANI A99000007740 Real Estate Agent
RAHEJA ESTATE AGENCY A51800003110 Real Estate Agent
MumbaiProperties Consulting Private Limited A51800000606 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
EKTA PARKSVILLE PHASE I BOMBAY CITY CIVIL COURT 887 Civil Yes Suit NA 2016 withdrawal
EKTA PARKSVILLE PHASE I BOMBAY CITY CIVIL COURT 889 Civil Yes Suit NA 2016 withdrawal
EKTA PARKSVILLE PHASE I BOMBAY CITY CIVIL COURT 890 Civil Yes Suit NA 2016 withdrawal
EKTA PARKSVILLE PHASE I STATE COMMISSION MAHARASHTRA 398 Others No Suit NA 2014 PENDING
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
4 Details of encumbrances
5 Details of encumbrances
6 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
11 Disclosure of sold/ booked inventory
12 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
3 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
6 Other
7 Other
8 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000000791 DHARMESH BHAU / REENA BHAU View Orders
2 CC006000000001418 Tejas Patel View Orders
3 CC006000000023361 NIDHI MEHTA View Orders
4 CC006000000054840 DAVID ALBERT D'SILVA View Orders
5 CC006000000055796 Francis Baptist D'cunha and Baptista Francis D'cunha View Orders
6 CC006000000055796 Francis Baptista D'cunha and Baptista Francis D'cunha View Orders
7 CC006000000056634 SONOO SAINANEY AND RAJ SAINANEY View Orders
8 CC006000000056960 ANTHONY MENEZES View Orders
9 CC006000000057504 Mrs. Mayuri Asar and Mrs. Bharati Asar View Orders
10 CC006000000078739 MRS LAXMI LALWANI View Orders
11 CC006000000089587 RONAK ANIL GAGLANI View Orders
12 CC006000000100250 Shakeel Ahmed Khan View Orders
13 CC006000000171485 PRAKASH BHANSALI View Orders
14 CC006000000195910 NEERA ABHAY SINGH View Orders
15 CC006000000195910 NEERA ABHAY SINGH View Orders
16 CC006000000220789 AJITKUMAR S GUPTA View Orders