MahaRERA Application

General Information

Other Than Individual

Organization

V-RAJ BUILDCON
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO 530
LODHA SUPREMUS 2
ROAD NO 22
WAGLE ESTATE
NEW PASSPORT OFFICE THANE
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400603

Organization Contact Details

02249707211

Past Experience Details

Member Information

Member Name Designation Photo
RAJESH RADHESHYAM GUPTA Authorized Signatory View Photo
PUSHPA RADHESHYAM GUPTA Partner View Photo

Project

VIRAJ HEIGHTS
New Project
30/12/2026
Yes
Others
No
TIKA NO 20 PART, CITY SURVEY NO 1025 A PART
SINDHI COLONY BUILDING NO 12 AND 13
20 METERS WIDE DP ROAD
PWD JALTARANG OFFICE
6 METERS INTERNAL ROAD
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
KOPRI
CHENDANI
400603
5850.05
2
2
0
00

FSI Details

16973.92
2500
19473.92

Bank Details

HDFC BANK
HDFC0001235

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 145 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WILL BE DONE PRIOR TO OC
Water Conservation, Rain water Harvesting : YES 0 WILL BE DONE PRIOR TO OC
Energy management : YES 0 WILL BE DONE PRIOR TO OC
Fire Protection And Fire Safety Requirements : YES 0 WILL BE DONE PRIOR TO OC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WILL BE DONE PRIOR TO OC
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 WILL BE DONE PRIOR TO OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WILL BE DONE PRIOR TO OC
Storm Water Drains : YES 0 WILL BE DONE PRIOR TO OC
Landscaping & Tree Planting : YES 0 WILL BE DONE PRIOR TO OC
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WILL BE DONE PRIOR TO OC
Solid Waste Management And Disposal : YES 0 WILL BE DONE PRIOR TO OC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 VIRAJ HEIGHTS VIRAJ HEIGHTS 31/12/2025 1 1 0 44 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 27.90 01 01
2 1BHK 37.43 35 21
3 Shop 38.21 01 01
4 Office 38.28 03 03
5 Office 40.06 03 03
6 1BHK 40.09 27 14
7 1BHK 40.50 11 11
8 Shop 41.63 01 01
9 1BHK 42.43 16 12
10 Office 45.91 02 02
11 Shop 47.98 01 01
12 OFFICE 54.53 01 01
13 2BHK 55.16 17 06
14 2BHK 55.19 24 08
15 2BHK 55.20 27 14
16 SHOP 89.92 01 01
17 3.5BHK 95.78 05 01
18 3BHK 96 07 01
19 OFFICE 98.54 01 01
20 OFFICE 105.62 01 01
21 3.5BHK 106.27 02 01
22 OFFICE 106.30 02 02
23 SHOP 219.89 01 01
24 Shop 22.80 01 01
25 Shop 23.54 01 01
26 1BHK 40.22 34 14
27 2BHK 53.56 10 9
28 2BHK 53.57 12 11
29 2BHK 56.07 9 8
30 2BHK 57.53 19 10
31 OFFICE 72.21 3 3
32 OFFICE 73 3 3
33 OFFICE 106.01 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 7
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 2
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 1
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 VIRAJ HEIGHTS REHAB BUILDING 31/08/2024 0 1 0 30 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 11.84 01 01
2 Shop 12.12 01 00
3 Shop 11.92 01 00
4 Shop 11.31 01 00
5 1 BHK 27.88 62 49
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 19
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31.9

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
NEXSTEP CONSULTANTS NA Architect
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
NARESH THAKURDAS HUNDLANI A51700002411 Real Estate Agent
NITIN ANANT MORE A51700010387 Real Estate Agent
LIVNEST TECHNOLOGIES PRIVATE LIMITED A51700015221 Real Estate Agent
Mukesh Soni NA Chartered Accountant
Diwakar R Pathak NA Engineer
Stead Realty Advisory Private Limited A51800035736 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
VIRAJ HEIGHTS High Court Of Bombay 156 Others No Other PIL 2018 Disposed off
NA
VIRAJ HEIGHTS Court of Upper Collector and Appellate Authority SRO-SR49 Civil No Appeal NA 2018 Disposed off
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
14 Architect’s Certificate of Percentage of Completion of Work (Form 1)
15 Architect’s Certificate of Percentage of Completion of Work (Form 1)
16 Architect’s Certificate of Percentage of Completion of Work (Form 1)
17 Architect’s Certificate of Percentage of Completion of Work (Form 1)
18 Architect’s Certificate of Percentage of Completion of Work (Form 1)
19 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
2 Other – Finance
3 Other – Finance
1 Other – Technical
2 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000161263 BALAJI BUYERS ASSOCIATION View Orders
2 CC006000000161263 BALAJI BUYERS ASSOCIATION View Orders