MahaRERA Application

General Information

Other Than Individual

Organization

CRESCENT AMITY REALTORS PVT.LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

A/13, 1ST FLOOR
DATTANI TOWERS
KORA KENDRA , S.V.ROAD,
BORIVALI WEST
NEXT TO MC' DONALD
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400092

Organization Contact Details

91228994365
WWW.VORASKYLINE.BIZ

Past Experience Details

Member Information

Member Name Designation Photo
JIGAR SHAILESH VORA Managing Director View Photo
JYOTI SHAILESH VORA Authorized Signatory View Photo

Project

CENTRICO
On-Going Project
31/12/2020
30/12/2023
29/12/2024
Yes
Residential
No
213-A 213B 215 PT 214 214 / 1 TO 31
18 30 MTR D P ROAD
CTS NO 265 AND PROPOSED 18 30 MTR D P ROAD
SLUM STRUCTURE CTS NO 13 AND CTS NO 3 PT
CTS NO 213 AND CTS NO 216 B AND D P ROAD
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
GAUTAM BUDDHA MARG,
ORLEM MALAD WEST
400064
5432.16
2
2
0
358.56

FSI Details

17656.22
8800
26456.22

Bank Details

INDUSIND BANK LTD
INDB0000332

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 179 133 40

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 -
Water Conservation, Rain water Harvesting : YES 0 -
Energy management : YES 0 -
Fire Protection And Fire Safety Requirements : YES 40 -
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 -
FITNESS CENTRE : YES 50 -
Aggregate area of recreational Open Space : YES 0 -
Open Parking : NO 0 NA
Water Supply : YES 0 -
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 -
Storm Water Drains : YES 0 -
Landscaping & Tree Planting : YES 0 -
Street Lighting : YES 0 -
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 -
Solid Waste Management And Disposal : YES 0 -

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 CENTRICO CENTRICO SALE BUILDING 31/12/2022 0 1 7 41 1 0 162
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 408 5 3
2 4BHK 1308 77 63
3 2BHK 752 82 75
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 75
4 Stilt Floor 100
5 X number of Slabs of Super Structure 86
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

3
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 55.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 CENTRICO COMPOSITE BUILDING 1 1 0 24 1 0 17
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 25 180 0
2 1 RK 20.9 58 0
3 SHOP 10 13 0
4 RETAIL MARKET 23.20 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 88
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

75
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 72.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SILVER HOUSECON NA Contractor
VISHWAS SATODIA NA Architect
GOKANI CONSULTANTS PVT LTD NA Engineer
HYDRO MECHANICAL CONSULTANTS NA Other Professional
Vinod Mishalram Gupta A51800001705 Real Estate Agent
PROPERTY ANTHEM INDIA A51800013105 Real Estate Agent
PUSHPAT BAFNA A51800012177 Real Estate Agent
FRANCIS SHANTWAN LOBO A51700014793 Real Estate Agent
FRANCIS SHANTWAN LOBO A51700014793 Real Estate Agent
Manan Nilesh Doshi A51800037065 Real Estate Agent
JM Financial Products Limited A51900000277 Real Estate Agent
Nilay Rajpurohit A51900003199 Real Estate Agent
Divyang Jayantilal Thadeshwar A51800001215 Real Estate Agent
ashish vijay goel A51800013907 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
CENTRICO CITY CIVIL COURT DINDOSHI 2479 Civil No Suit NA 2014 DISMISSED
NA
CENTRICO MAHARASHTRA SLUM TRIBUNAL 10 Civil No Appeal NA 2014 PENDING FOR HEARING OF CONDONATION OF DELAY APPLICATION
NA
CENTRICO CITY CIVIL COURT DINDOSHI 3165 Civil No Suit NA 2015 PENDING FOR HEARING OF NOTICE OF MOTION
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
4 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
2 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000221079 KIRTI G. SANGHVI View Orders
2 CC006000000199013 Hemant Bhavsar View Orders
3 CC006000000209434 Crescent Amity Realtors Pvt. Ltd. View Orders