MahaRERA Application

General Information

Other Than Individual

Organization

NEELKANTH LIFESPACE LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO. A-0906, PLOT NO- 89 & 90
MAHAVIR ICON
SECTOR- 15
CBD BELAPUR
BELAPUR
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400614

Organization Contact Details

02227599000

Past Experience Details

Member Information

Member Name Designation Photo
RAMILA NARAYAN RAVRIYA Partner View Photo
PREMJI HIRJI KAROTRA Authorized Signatory View Photo
RAGHU AMBAVI PATEL Partner View Photo
KAILASH GOKAR KAROTRA Partner View Photo
ABDUL REHMAN ABDUL QADIR DADAN Partner View Photo
VIJAY SAVJI POLAR Partner View Photo
NATHABHAI BHIMJIBHAI ISASARIA Partner View Photo
HIRA PANCHA VAVIA Partner View Photo
BHANJI RAGHAVJI RAVRIYA Partner View Photo

Project

NEELKANTH AURA
On-Going Project
31/10/2018
31/12/2019
No
Others
No
PLOT 198C
PLOT NO 198D
15 METER PROPOSED WIDE ROAD
PLOT NO 198D 198A
30 METERS WIDE ROAD
MAHARASHTRA
Konkan
Raigarh
Panvel
Ulawe
SECTOR 23
NAVI MUMBAI
410206
749.81
1
1
0
0

FSI Details

1124.34
0
1124.34

Bank Details

IDBI BANK
IBKL0000183

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 12 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 RWH TANK IS PROVIDED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 90 AS PER PROVISIONAL FIRE NOC PROVIDED BY CIDCO
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 ELECTRIC METER ROOM WILL BE PROVIDED
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 NA
Water Supply : YES 0 PROVIDE UPTO SITE BY CIDCO
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 LINES CHAMBERS SEPTIC TANK IS PROVIDED
Storm Water Drains : NO 0 CHAMBERS
Landscaping & Tree Planting : YES 0 8NOS OF TREES
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 LATER STAGE OF WORK
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NEELKANTH AURA NEELKANTH AURA 31/12/2019 0 1 0 8 1 2 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 3 34.90 1 1
2 SHOP 4 35.72 1 0
3 SHOP 5 39.92 1 0
4 SHOP 1 11.69 1 1
5 SHOP 2 11.75 1 0
6 FLAT 18 12.19 1 0
7 FLAT 1 14.52 1 1
8 FLAT 2 17.27 1 1
9 FLAT 3 17.48 1 0
10 FLAT 4 17.22 1 1
11 FLAT 5 19.56 1 0
12 FLAT 6 20.92 1 1
13 FLAT 7 22.61 1 1
14 FLAT 8 24.57 4 3
15 FLAT 9 24.62 1 0
16 FLAT 10 24.91 3 3
17 FLAT 11 25.99 1 1
18 FLAT 12 26.42 5 5
19 FLAT 13 27.32 1 1
20 FLAT 14 28.30 1 1
21 FLAT 15 29.95 4 4
22 FLAT 16 31.40 1 1
23 FLAT 17 35.03 5 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 86.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ATUL PATEL NA Architect
SUBRAMANYA RAO NA Engineer
CA HITESH M SHAH NA Chartered Accountant
CA JYOTI B GAJRA NA Chartered Accountant
SUMAN ENTERPRISES NA Contractor
MAA SHITALA PLUMBING WORK NA Contractor
ARVIND MAVJI RUDHANI NA Contractor
SUKHAL RAWAT NA Contractor
KAMLESH PRITAMLAL MURPANA A51700014445 Real Estate Agent
Ram Mohan Iyer A51700008890 Real Estate Agent
JAIDEEP PATHRIA A51700001248 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement