MahaRERA Application

General Information

Other Than Individual

Organization

OM NAMAH SHIVAY DEVELOPERS PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

28
RAJABAHADUR BUILDING 1ST FLOOR
BOMBAY SAMACHAR MARG
FORT
BSE
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400023

Organization Contact Details

02266236300

Past Experience Details

Member Information

Member Name Designation Photo
NARINDERPAL ROSHANLAL GUPTA Authorized Signatory View Photo

Project

NG GRAND PLAZA PHASE I
On-Going Project
15/12/2019
15/12/2019
No
Residential
No
PLOT NUMBER 9
PLOT NO 6
34 WIDE ROAD
PLOT NO 10
PLOT NO 8
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400701
5265.39
2
2
0
0

FSI Details

7892
0
7892.00

Bank Details

KOTAK MAHINDRA BANK
KKBK0000957

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 261 29 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 IN PROGRESS
Water Conservation, Rain water Harvesting : YES 0 IN PROGRESS
Energy management : YES 0 IN PROGRESS
Fire Protection And Fire Safety Requirements : YES 70 IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 20 IN PROGRESS
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 40 IN PROGRESS
Storm Water Drains : YES 40 IN PROGRESS
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 0 IN PROGRESS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NG GRAND PLAZA PHASE I NG GRAND PLAZA A 0 1 2 40 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHKTYPE1 66.95 30 4
2 3BHKTYPE2 73.21 41 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 70
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 10
4 Stilt Floor 100
5 X number of Slabs of Super Structure 70
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 NG GRAND PLAZA PHASE I NG GRAND PLAZA B 0 1 2 40 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHKTYPE1 50.02 28 6
2 2BHKTYPE2 57.28 38 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 70
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 10
4 Stilt Floor 80
5 X number of Slabs of Super Structure 60
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SATISH V AHUJA NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement