MahaRERA Application

General Information

Other Than Individual

Organization

ROYAL REALTORS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

6TH FLOOR
SHAH TRADE CENTRE
RANI SATI MARG
MALAD EAST
NEAR WESTERN EXPRESS HIGHWAY
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400097

Organization Contact Details

02267193333
royalrealtorsgroup.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1ROYAL SAPPHIREResidentialNA877.5DOMNIC COLONY ROAD NO 3 ORLEM MALAD WEST MUMBAI 400064CTS NO 97, 97/1 TO 381302016-02-112016-02-11
2ROYAL CRYSTAL A WINGResidentialNA1185.92TRIVENI NAGAR KURAR VILLAGE MALAD EAST MUMBAI 400097708 729 730 730/1 TO 2 731 732 732/1 TO 5 7331802017-06-012017-06-28

Member Information

Member Name Designation Photo
PREMJI HARAKHACHAND SHAH Partner View Photo
HIMMATLAL GANESHLAL KACHHARA Partner View Photo
DEVEN PREMJI SHAH Authorized Signatory View Photo

Project

ROYAL PRISTO
New Project
30/12/2026
Yes
Residential
Yes
712 713 714 715 AND OTHER AS PER LOI
EXISTING BLDG
18 3 MT WIDE DP ROAD
13 4 MT WIDE PROPOSED DP ROAD
EXISTING BLDG
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
SANTOSHI MATA TEMPLE ROAD
VAISHETPADA KURAR VILLAGE MALAD EAST
400097
12860.8
2
2
0
893.65

FSI Details

23083.42
9695.65
32779.07

Bank Details

HDFC BANK
HDFC0009373

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ROYAL PRISTO POPAT MARUTI GHANWAT Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 187 93 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 SHALL BE COMPLIED BEFORE OC
Water Conservation, Rain water Harvesting : YES 0 SHALL BE COMPLIED BEFORE OC
Energy management : YES 0 SHALL BE COMPLIED BEFORE OC
Fire Protection And Fire Safety Requirements : YES 0 SHALL BE COMPLIED BEFORE OC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 SHALL BE COMPLIED BEFORE OC
Aggregate area of recreational Open Space : YES 0 SHALL BE COMPLIED BEFORE OC
Open Parking : YES 0 SHALL BE COMPLIED BEFORE OC
Water Supply : YES 0 SHALL BE COMPLIED AFTER OC BY MCGM
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 SHALL BE COMPLIED BEFORE OC
Storm Water Drains : YES 0 SHALL BE COMPLIED BEFORE OC
Landscaping & Tree Planting : YES 0 SHALL BE COMPLIED BEFORE OC
Street Lighting : YES 0 SHALL BE COMPLIED BEFORE OC INSTALLED BY MCGM/US
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 SHALL BE COMPLIED BEFORE OC
Solid Waste Management And Disposal : YES 0 SHALL BE COMPLIED BEFORE OC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ROYAL PRISTO ROYAL PRISTO 31/12/2025 1 1 3 31 1 33 187
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP NO 4 27.52 1 1
2 SHOP NO 1 39.42 1 1
3 TYPE5 40.61 15 6
4 TYPE6 40.44 15 4
5 TYPE7 58.8 15 2
6 TYPE8 63.19 15 7
7 TYPE9 63.26 10 2
8 SHOP NO 2 31.47 1 1
9 SHOP NO 18 17.1 1 0
10 TYPE10 46.22 10 1
11 SHOP NO 5 28.45 1 0
12 SHOP NO 6 27.17 1 0
13 SHOP NO 7 21.57 1 1
14 SHOP NO 8 24.36 1 1
15 SHOP NO 10 27.76 1 1
16 SHOP NO 17 29.43 1 1
17 SHOP NO 9 24.36 1 1
18 OFFICE NO 1 30.33 1 0
19 OFFICE NO 2 23 1 0
20 OFFICE NO 3 20.77 1 0
21 OFFICE NO 4 23.18 1 0
22 OFFICE NO 5 20.59 1 0
23 OFFICE NO 6 23.46 1 0
24 OFFICE NO 7 21.9 1 0
25 OFFICE NO 8 21.9 1 0
26 OFFICE NO 9 20.78 1 0
27 OFFICE NO 11 85.18 1 0
28 OFFICE NO 10 19.63 1 1
29 DEPARTMENTAL STORE G 299.66 1 0
30 COMM OFFICE 2ND FLR 445.56 1 1
31 DEPARTMENTAL STORE F 407.7 1 0
32 DAIGONSTIC CENTER 61.46 1 0
33 INTERMEDIATE BASEMEN 434.95 1 0
34 TYPE17 44.44 5 2
35 TYPE1 59.99 45 30
36 TYPE2 59.64 30 14
37 TYPE3 42.29 30 20
38 TYPE4 41.96 30 18
39 TYPE11 45.79 10 0
40 TYPE12 44.27 5 0
41 TYPE13 62.54 5 2
42 TYPE15 36.24 1 0
43 TYPE16 37.36 1 0
44 TYPE18 41.12 1 1
45 SHOP NO 3 25.9 1 0
46 TYPE14 30 384 255
47 SHOP NO 11 25.92 1 1
48 SHOP NO 12 25.92 1 1
49 SHOP NO 13 24.58 1 1
50 SHOP NO 14 23.13 1 0
51 SHOP NO 15 26.15 1 0
52 SHOP NO 16 26.53 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

25
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 65
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ROYAL PRISTO ROYAL PARV 31/12/2025 1 1 1 26 0 0 14
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP TYPE 4 6.5 1 0
2 SHOP TYPE 20 10.62 1 0
3 SHOP TYPE 26 22.25 1 0
4 SHOP TYPE 4 4.48 1 0
5 SHOP TYPE 35 11.79 1 0
6 SHOP TYPE 48 14.02 1 0
7 SHOP TYPE 49 52.97 1 0
8 SHOP TYPE 52 12.64 1 0
9 SHOP TYPE 64 11.63 1 0
10 FLAT NO 16 24.29 1 1
11 FLAT NO 17 21.7 1 0
12 FLAT N 1 38.09 1 1
13 FLAT N 6 45.25 1 1
14 FLAT N 8 40.76 1 0
15 FLAT NO 9 37.41 1 0
16 FLAT N 10 32.84 1 0
17 FLAT N 11 29.63 1 0
18 FLAT N 17 42.34 1 0
19 FLAT N 18 36.49 1 0
20 FLAT N 22 39.74 1 0
21 FLAT N 21 30.35 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 94

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SATPANTH ASSOCAITES NA Contractor
SKYTECH CONSULTANTS NA Architect
AESTHETIC ENGINEERS NA Engineer
MITESH GADA NA Engineer
J D SHAH & ASSOCIATES NA Chartered Accountant
SANGHAVI AND ASSOCIATES AND CONSULTANTS PVT LTD NA Engineer

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
ROYAL PRISTO BOMBAY HIGH COURT 1460 Civil No Writ Petition NA 2019 The Writ Petition is dismissed
NA
ROYAL PRISTO BOMBAY HIGH COURT 1171 Civil No Writ Petition NA 2019 The Writ Petition is dismissed
NA
ROYAL PRISTO CITY CIVIL COURT DINDOSHI 1153 Civil No Suit NA 2017 PENDING
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
4 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
6 Proforma of Allotment letter
7 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000302999 Mahesh Eknath Patole View Orders