MahaRERA Application

General Information

Other Than Individual

Organization

VICTOR HOMES PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

234/235/236,
BIG SPLASH
SECTOR 17
VASHI NAVI MUMBAI
BIG SPLASH
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02225555444

Past Experience Details

Member Information

Member Name Designation Photo
CURSINO JUDE AGNELO CASTELLINO Director View Photo
CURSINO JUDE AGNELO CASTELLINO Authorized Signatory View Photo

Project

LOURDES
New Project
30/12/2023
No
Others
No
CTS NO. 1041
CENTRAL AVENUE ROAD
BY LAND CTS NO 1042
BY LAND CTS NO 1040
BY LAND CTS NO 1044
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
CENTRAL AVENUE ROAD
CHEMBUR MUMBAI
400071
1125.40
1
1
0
169.06

FSI Details

0
3576.79
3576.79

Bank Details

IDBI BANK
IBKL0000765

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 30 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 0
Water Conservation, Rain water Harvesting : YES 0 0
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 0
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 0
Aggregate area of recreational Open Space : YES 0 0
Open Parking : NO 0 NA
Water Supply : YES 0 0
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 0
Storm Water Drains : YES 0 0
Landscaping & Tree Planting : YES 0 0
Street Lighting : YES 0 0
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 0
Solid Waste Management And Disposal : YES 0 0

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 LOURDES LOURDES 31/12/2022 1 1 2 13 1 0 30
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 GRD 01 SHOP 82.33 1 0
2 GRD 02 SHOP 70.71 1 0
3 RESTAURANT 189.90 1 0
4 RESIDENTIAL 5BHK 395.35 7 0
5 RESIDENTIAL 5BHK 332.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
DILIP SANGHVI CONSULTANTS LS NA Architect
REALTORS A51900004566 Real Estate Agent
RAHEJA ESTATE AGENCY A51800003110 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement