MahaRERA Application

General Information

Other Than Individual

Organization

Gagan Housing And Landmarks LLP
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

4th Floor
Arthvishwa Building
Lane No 5
Koregaon Park
above IDBI Bank
MAHARASHTRA
Pune
Pune
Haveli
KOREGAON PARK
411001

Organization Contact Details

02026153031

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Gagan SignetOthersResidential + commercial9888.26Kondhawa Bk Tal. Haveli Pune 41104866/11/131902020-06-302020-06-30

Member Information

Member Name Designation Photo
Vijay Ramesh Jasuja Partner View Photo
Rahul Sureshchand Garg Partner View Photo
Rohit Surshchand Garg Authorized Signatory View Photo

Project

Gagan Klara
New Project
30/03/2024
30/03/2025
No
Others
Yes
Survey No 38 Hissa No 8A Balewadi
Road
Survey No 38 Hissa No 5
Survey No 38 Hissa No 7
Survey No 38 Hissa No 8 Part and 9
MAHARASHTRA
Pune
Pune
Haveli
Hi Street
Balewadi
411045
8900
4
4
0
829.06

FSI Details

31436.75
0
31436.75

Bank Details

HDFC
HDFC0002054

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Klara Shri. Dnyneshwar Ramchandra Balwadkar Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Klara Shri. Namdev Ramchandra Balwadkar Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Gagan Klara Ananda Ramchandra Balwadkar Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 323 235 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 50 0
Water Conservation, Rain water Harvesting : YES 50 0
Energy management : YES 0 0
Fire Protection And Fire Safety Requirements : YES 50 0
Electrical Meter Room, Sub-Station, Receiving Station : YES 8 0
SWIMMING POOL : YES 0 0
Aggregate area of recreational Open Space : YES 0 0
Open Parking : YES 0 0
Water Supply : YES 0 0
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 0
Storm Water Drains : YES 90 0
Landscaping & Tree Planting : YES 0 0
Street Lighting : YES 0 0
Community Buildings : YES 30 0
Treatment And Disposal Of Sewage And Sullage Water : YES 100 0
Solid Waste Management And Disposal : YES 95 0

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Gagan Klara Building D - Commercial And MHADA 30/09/2023 2 1 0 12 0 0 67
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Studio 28 11 0
2 Studio 29 12 0
3 MHADA 27.7 3 0
4 Office space 60 2 1
5 Shop 46.91 1 1
6 MHADA 24.47 3 0
7 MHADA 28.61 3 0
8 Shop 39.46 1 1
9 Office space 26.01 3 1
10 Office space 26.06 1 0
11 Office space 26.07 1 0
12 Office space 26.1 2 0
13 Studio 22.64 5 0
14 Studio 23.21 6 0
15 Studio 25.99 6 0
16 Office space 26.12 1 0
17 Office space 49.09 1 0
18 Office space 31.88 2 2
19 Studio 26.73 5 0
20 Shop 67.64 1 1
21 Shop 72.72 1 0
22 Office space 26.15 1 1
23 Office space 31.71 2 2
24 Office space 31.72 2 2
25 Office space 31.74 1 1
26 Office space 31.77 2 2
27 Office space 60 1 0
28 MHADA 27.67 3 0
29 Office space 66.93 2 2
30 MHADA 26.05 3 0
31 MHADA 26.73 4 0
32 Studio 29.18 6 0
33 Studio 20.77 6 0
34 Shop 48.51 1 1
35 Shop 62.83 1 1
36 Shop 64.7 1 1
37 MHADA 20.61 3 0
38 MHADA 22.64 4 0
39 Shop 114.58 1 0
40 MHADA 29.23 3 0
41 MHADA 30.55 3 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 83
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 18
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

8
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 15
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Gagan Klara Wing A 30/09/2023 2 1 0 22 1 0 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 63.38 2 0
2 3BHK 86.61 1 1
3 3BHK 87.25 2 2
4 3BHK 94.83 1 1
5 2 BHK 62.78 20 14
6 1 BHK 52.09 3 2
7 2 BHK 62.4 20 19
8 2 BHK 63 17 17
9 2 BHK 63.65 18 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 88
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 87
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

84
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 57
11 Overall Percentage of Completion of the work done For the entire Building /Wing 71.6
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Gagan Klara Wing B 30/09/2023 2 1 0 22 1 0 80
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 51.92 3 2
2 2 BHK 62.82 10 9
3 2 BHK 62.84 17 14
4 2 BHK 63.43 10 9
5 2 BHK 63.44 20 18
6 2 BHK 63.48 11 7
7 2 BHK 64.05 9 7
8 3BHK 87 2 2
9 3BHK 87.25 1 1
10 3BHK 95.13 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 82
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

83
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 57
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Gagan Klara Wing C 30/09/2023 2 1 0 22 1 0 80
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 90.35 30 27
2 3BHK 90.45 9 8
3 3 BHK 90.7 34 30
4 2BHK 89.44 1 1
5 2BHK 85.81 3 3
6 2 BHK 74.67 3 3
7 3BHK 122.38 4 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 85
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 87
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

82
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 51
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
R R Malwadkar NA Architect
Design Werkz Engineering Pvt Ltd NA Engineer
IMRAN MOHAMMED A52100016058 Real Estate Agent
YOGESH YADAV A52100013755 Real Estate Agent
ATUL SAVADIA A52100007035 Real Estate Agent
SONERAO SATISH PANDHARE A52100017494 Real Estate Agent
MAYANK BARHOLIA A52100003500 Real Estate Agent
Realtors Compass A52100001849 Real Estate Agent
Sandeep Harikesh Tiwari A52100003446 Real Estate Agent
Vijay Ganesh Rai A52100014625 Real Estate Agent
NEHA SINGH A52100011953 Real Estate Agent
AMIT KUMAR MANGALAM A52100005479 Real Estate Agent
PROPTIGER MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
AMIT ANIL KULKARNI A52100009654 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
21 Building Plan Approval (IOD)
22 Building Plan Approval (IOD)
23 Building Plan Approval (IOD)
24 Building Plan Approval (IOD)
25 Building Plan Approval (IOD)
26 Building Plan Approval (IOD)
27 Building Plan Approval (IOD)
28 Building Plan Approval (IOD)
29 Building Plan Approval (IOD)
30 Building Plan Approval (IOD)
31 Building Plan Approval (IOD)
32 Building Plan Approval (IOD)
33 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
8 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
2 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement