MahaRERA Application

General Information

Other Than Individual

Organization

AMJ Land Developers
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Pudumjee Pulp & Paper Mills Ltd. Compound
Thergaon
Aditya Birla Hospital Marg
Chinchwad
Opposite Greens
MAHARASHTRA
Pune
Pune
Mulshi
Thergaon
411033

Organization Contact Details

02029952973
www.greenspune.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Greens - Phase - IResidentialNA28204CTS No. 5401 Opp. PPPML Thergaon Chinchwad Pune - 411033CTS No 540154702015-09-302015-09-19
2Greens - Beech GHResidentialNA7565CTS No 5401 Opp PPPML Thergaon Chinchwad Pune - 411033CTS No 540111242018-10-312018-05-19
3Greens CentreCommercialNA2450CTS No 5401 Opp PPPML Thergaon Chinchwad Pune - 411033CTS No 54011592019-06-302019-06-25

Member Information

Member Name Designation Photo
Mr Surendra Kumar Bansal Authorized Signatory View Photo
Mr Shashidharan Sethumadhavan Menon Authorized Signatory View Photo

Project

Greens Centre
New Project
30/06/2019
29/12/2020
No
Commercial
No
CTS No. 5401
Part of CTS No 5402 and 5405 and 2420
Part of CTS No 5372 and 5383 and 5358 and 5341 etc
Part of CTS No 5407 and 9 mtr road
Part of S No 22
MAHARASHTRA
Pune
Pune
Mulshi
Thergaon
Aditya Birla Hospital Marg
Chinchwad
411033
2450
1
1
0
0

FSI Details

2444.50
0
2444.50

Bank Details

Saraswat Bank
SRCB0000034

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 NA
Water Conservation, Rain water Harvesting : YES 100 NA
Energy management : YES 100 NA
Fire Protection And Fire Safety Requirements : YES 100 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Part of it completed with previous phase
Aggregate area of recreational Open Space : YES 100 Completed as per norms in previous phase
Open Parking : YES 100 NA
Water Supply : YES 100 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 NA
Storm Water Drains : YES 100 NA
Landscaping & Tree Planting : YES 100 NA
Street Lighting : YES 100 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 NA
Solid Waste Management And Disposal : YES 100 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Greens Centre Greens Centre 30/06/2019 1 1 0 5 0 50 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office Type A 43.32 36 29
2 Shop Type A 19.44 10 10
3 Shop Type B 20.11 9 9
4 Office Type B 68.23 4 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
HDFC DEVELOPERS LIMITED A51900000930 Real Estate Agent
GLOBAL REALTORS A52100000018 Real Estate Agent
Subhash Shah & Associates Architects pvt. Ltd. NA Architect
Anup Sunil Chordiya A52100006709 Real Estate Agent
Gupta Electricals & Contractor NA Contractor
Shree Vyankateswara Infrastructure NA Contractor
Shree Vyankateswara Enterprises NA Contractor
Shreenath Plumbing Works NA Contractor
Sumeet Fire Engineers Pvt. Ltd. NA Contractor
Om Sai Interiors Pvt. Ltd. NA Contractor
Vitthal Shankar Potadar NA Contractor
Mahesh Kumar NA Contractor
Johnson Lifts Private Limited NA Contractor
Kanchan Gajeshwar NA Architect
Mr Shridhar Vidwans NA Engineer
R. A. Karandikar & Co. NA Chartered Accountant
G. N. Angal & Co. NA Chartered Accountant
Strudcom consultants Pvt. Ltd. NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement