MahaRERA Application

General Information

Other Than Individual

Organization

Five Star Construction Company
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

309,310
Rainbow Plaza
Shivar Chowk
Rahatani
Near Hotel Shivar Garden
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
411017

Organization Contact Details

02027206300
www.5starconstuctions.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Royal Entrada Phase IOthersResidential + Commercial6941.91138 Part 139 Part 140 Part 141 Part Wakad Taluka Mulshi Pune 411057138 Part 139 Part 140 Part 141 Part Wakad Taluka Mulshi Pune 41105732342016-10-312016-10-31
2Royal MajesticOthersResidential + Commercial4250Survey No. 29 part Rahatani Haveli Pune 17Survey No 29/1/1 29/1/2 29/1/3 29/1/4/1 29/2/221662018-03-312017-03-16

Member Information

Member Name Designation Photo
Sunil Harumal Adwani Partner View Photo
Manohar Jaduram Pherwani Partner View Photo
Tanuj Manohar Pherwani Partner View Photo
Sourabh Sunil Adwani Partner View Photo
Sunil Harumal Adwani Authorized Signatory View Photo

Project

ANP - LANDMARK
New Project
30/03/2023
No
Commercial
No
Survey No 89/1, 89/2 , 87/3/2
Survey No 117
Survey No 87
30 M Wide D P Road
Plot belongs to Five Star Construction Co
MAHARASHTRA
Pune
Pune
Mulshi
Wakad
Wakad - Hinewadi Road
Near Bhumkar Chowk
411057
3100
1
1
0
0

FSI Details

0
4053
4053.00

Bank Details

SBI BANK LTD
SBIN0004523

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 31 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Rainwater Harvesting Proposed
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 As per PCMC Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electrical Meter Room Proposed only
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 Visitors parking Proposed
Water Supply : YES 30 PCMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP Proposed
Storm Water Drains : YES 0 Proposed
Landscaping & Tree Planting : YES 0 As per PCMC Norms
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 70 STP Proposed
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ANP - LANDMARK Building A 31/03/2022 2 1 0 14 1 0 3
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 30.65 9 0
2 Restaurant 143.01 1 0
3 Shop 92.18 1 0
4 Shop 64.87 1 0
5 Shop 50.14 1 0
6 Shop 50.14 1 0
7 Office space 62.73 8 0
8 Shop 114.82 1 1
9 Shop 79.85 1 1
10 Office space 35.46 9 4
11 Office space 30.83 9 4
12 Office space 27.79 36 6
13 Office space 82.51 8 1
14 Office space 82.71 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

45
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
A Design Studio Arch Siddarth s Harishchandrakar NA Architect
Shrenik Upadhaya NA Engineer
R D Kabra And Associates NA Chartered Accountant
Balaji Construction NA Contractor

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of the allotment letter and agreement for sale
2 Proforma of the allotment letter and agreement for sale
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical