MahaRERA Application

General Information

Other Than Individual

Organization

paradisesuperstructures
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

2
Satra Plaza
Palm Beach Road
Sector 19 D Vashi
APMC Market
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02227849000
www.paradisegroup.co.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Sai MokshResidentialNA2401.68Sector 15 Kharghar Navi Mumbai481732015-08-122015-06-19
2Sai RiverdaleResidentialNA5499Sector-7 TalojaPlot no 11, 1212442017-10-182017-07-03
3Sai GangaResidentialNA1949Sector 5 UlwePlot no 21622017-05-152017-01-11
4Sai FortuneResidentialNA2349Sector 8 UlwePlot no 151992016-12-012016-11-21
5Sai SahilResidentialNA1449Sector 5 UlwePlot no 6A1502017-05-012017-04-28
6Sai HarmonyResidentialNA2650Sector 21 Ulwe Navi Mumbaiplot no 9911152016-07-312016-07-15
7Sai SapphireResidentialNA4000Sector 20 Ulwe Navi Mumbaiplot no 178, 18011622015-07-312015-07-02
8Sai SpringResidentialNA5000Sector 35 G Kharghar Navi MumbaiPlot no 5, 5A11482016-08-012016-07-21
9Sai MiracleResidentialNA4900Sector 35 E Kharghar Navi MumbaiPlot no 16, 17, 1911102016-08-012016-07-22
10Sai CrystalResidentialNA6049Sector 35 D Kharghar Navi MumbaiPlot no 45, 52, 52 A11662016-10-012016-09-30
11Sai WonderResidentialNA2200Sector 35 F Kharghar Navi MumbaiPlot no 4, 51952017-07-012017-05-09
12Sai SolitaireResidentialNA3400Sec 35 H Kharghar Navi MumbaiPlot no 4, 51832017-07-012016-06-21

Member Information

Member Name Designation Photo
Madhu Bhagwandas Bathija Partner View Photo
Amit Madhu Bathija Partner View Photo
Manish Madhu Bathija Partner View Photo
Paradise Infracon Private Limited Partner View Photo
Umesh Kumar Bhagwat Prasad Upadhyay Authorized Signatory View Photo

Project

Sai World Empire
On-Going Project
31/10/2022
30/10/2023
29/10/2024
No
Residential
Yes
survey no 93/2, 3, 4 - 94/1, 2, 3A, 3B, 4 - 102/1A, 1B, 3, 4, 5A2, 5B, 5K, 103/1A, 1B, 2A, 2B, 3
Survey no 91 92
CIDCO Land
Survey no 102 104
32 Meter Approach Road
MAHARASHTRA
Konkan
Raigarh
Panvel
Rohinjan
CIDCO ROAD
Rohinjan
410206
33188.25
4
4
0
2692.69

FSI Details

132521.83
14200
146721.83

Bank Details

Indian Overseas Bank
IOBA0001425

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Sai World Empire Blue Circle Infratech Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 1151 385 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 AS PER OCCUPANCY CERTIFICATE
Water Conservation, Rain water Harvesting : YES 100 AS PER OCCUPANCY CERTIFICATE
Energy management : YES 100 AS PER OCCUPANCY CERTIFICATE
Fire Protection And Fire Safety Requirements : YES 100 AS PER OCCUPANCY CERTIFICATE
Electrical Meter Room, Sub-Station, Receiving Station : YES 90 AS PER OCCUPANCY CERTIFICATE
Aggregate area of recreational Open Space : YES 100 AS PER OCCUPANCY CERTIFICATE
Open Parking : NO 0 NA
Water Supply : YES 100 AS PER OCCUPANCY CERTIFICATE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER OCCUPANCY CERTIFICATE
Storm Water Drains : YES 100 AS PER OCCUPANCY CERTIFICATE
Landscaping & Tree Planting : YES 50 AS PER OCCUPANCY CERTIFICATE
Street Lighting : YES 80 AS PER OCCUPANCY CERTIFICATE
Community Buildings : YES 90 AS PER OCCUPANCY CERTIFICATE
Treatment And Disposal Of Sewage And Sullage Water : YES 100 AS PER OCCUPANCY CERTIFICATE
Solid Waste Management And Disposal : YES 100 AS PER OCCUPANCY CERTIFICATE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Sai World Empire CEASER 31/10/2022 0 1 3 40 1 0 350
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 49 1 1
2 SHOP 36 1 1
3 SHOP 35 4 4
4 SHOP 39 3 3
5 SHOP 37 2 2
6 SHOP 44 1 1
7 SHOP 56 1 0
8 2BHK 67 74 41
9 3BHK 88 74 28
10 3BHK 98 74 15
11 4BHK 156 37 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 99
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Sai World Empire ALEXANDAR 31/10/2022 0 1 3 40 1 0 441
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 32 1 1
2 SHOP 35 4 4
3 SHOP 41 1 1
4 SHOP 36 2 2
5 SHOP 37 2 2
6 SHOP 44 2 2
7 SHOP 34 1 0
8 SHOP 39 1 1
9 2BHK 62 74 40
10 2BHK 67 74 43
11 3BHK 84 74 37
12 3BHK 95 74 26
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 99
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Sai World Empire NAPOLEAN 31/10/2022 0 1 3 40 1 0 350
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 36 1 1
2 SHOP 44 1 1
3 SHOP 49 1 1
4 SHOP 56 1 1
5 SHOP 35 4 4
6 SHOP 37 2 2
7 SHOP 39 3 2
8 2BHK 67 74 37
9 3BHK 88 74 36
10 3BHK 98 74 20
11 4BHK 156 37 20
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 99
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Sai World Empire CLUB HOUSE 31/10/2022 1 1 0 4 1 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 CLUB HOUSE 2502.65 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
HITEN SETHI ARCHITECTS NA Architect
MS SPACEAGE CONSULTANTS NA Architect
MS MAHIMTURA CONSULTANTS NA Engineer
ANIL VERMA AND ASSOCIATES NA Other Professional
MS ENVIRO ANALYST AND ENGINEERS PVT LTD NA Other Professional
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
Netra Realty Solutions Pvt Ltd NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
4 Details of encumbrances
5 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
21 Building Plan Approval (IOD)
22 Building Plan Approval (IOD)
23 Building Plan Approval (IOD)
24 Building Plan Approval (IOD)
25 Building Plan Approval (IOD)
26 Building Plan Approval (IOD)
27 Building Plan Approval (IOD)
28 Building Plan Approval (IOD)
29 Building Plan Approval (IOD)
30 Building Plan Approval (IOD)
31 Building Plan Approval (IOD)
32 Building Plan Approval (IOD)
33 Building Plan Approval (IOD)
34 Building Plan Approval (IOD)
35 Building Plan Approval (IOD)
36 Building Plan Approval (IOD)
37 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000023615 VISHNU PANDU RUPEKAR View Orders