MahaRERA Application

General Information

Other Than Individual

Organization

MAZAGAON DOCK SAI CO-OP HSG SOC LTD
Societies
NA
Do you have any Past Experience ?
No

Address Details

PLOT NO.3
SUB PLOT NO.K
SECTOR-21 (TRANS RAILWAY AREA)
NEW PANVEL(WEST)
NEAR K MALL
MAHARASHTRA
Konkan
Raigarh
Panvel
New Panvel
410206

Organization Contact Details

02206177500

Past Experience Details

Member Information

Member Name Designation Photo
RAVINDRA B BHAGAT Chairperson View Photo
ANIL PANDURANG BHAGAT Secretory View Photo
BALIRAM K BHOIR Authorized Signatory View Photo

Project

MAZAGAON DOCK SAI CO-OP HSG SOC LTD
New Project
30/06/2022
No
Residential
Yes
Sub Plot No K Plot No 3
9 mtrs wide Road
Panvel Municipal Boundaries
Open Plot
Sub Plot No D
MAHARASHTRA
Konkan
Raigarh
Panvel
New Panvel
Trans Railway Area
New Panvel (W)
410206
3810
2
1
1
557.26

FSI Details

1913.48
3801.52
5715.00

Bank Details

GS MAHANAGAR CO-OP BANK LTD
MCBL0960005

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
MAZAGAON DOCK SAI CO-OP HSG SOC LTD MAZAGAON DOCK SAI CO-OP HSG SOC LTD Societies Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Upload Agreement / MoU Copy
13 Upload Agreement / MoU Copy
14 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 30 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 AS PER APPROVED PLANS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 AS PER APPROVED PLANS
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 AS PER APPROVED PLANS
Aggregate area of recreational Open Space : YES 0 AS PER APPROVED PLANS
Open Parking : YES 0 33 OPEN PARKING
Water Supply : YES 0 AS PER APPROVED PLANS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER APPROVED PLANS
Storm Water Drains : YES 0 AS PER APPROVED PLANS
Landscaping & Tree Planting : YES 0 AS PER APPROVED PLANS
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 MAZAGAON DOCK SAI CO-OP HSG SOC LTD MAZAGAON DOCK SAI CO-OP HSG SOC LTD 31/12/2021 0 1 0 11 1 33 30
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 66.93 4 0
2 2 BHK 48.83 4 0
3 2BHK 46.65 8 0
4 2BHK 46.66 5 0
5 2BHK 44.08 11 0
6 2BHK 51.88 9 0
7 3BHK 64.26 4 0
8 2BHK 50.89 1 0
9 2BHK 39.11 1 0
10 2BHK 47.90 5 0
11 2BHK 34.39 5 0
12 3BHK 66.41 1 0
13 2BHK 35.93 4 0
14 2BHK 49.03 7 0
15 2BHK 44.09 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 10
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 MAZAGAON DOCK SAI CO-OP HSG SOC LTD MAZAGAON DOCK SAI CO-OP HSG SOC LTD 31/12/2021 0 1 0 4 1 0 37
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 65.29 2 0
2 2BHK 35.93 2 0
3 2BHK 49.03 4 0
4 OFFICE 76.36 1 0
5 OFFICE 79.61 3 0
6 OFFICE 38.74 2 0
7 OFFICE 39.48 1 0
8 OFFICE 33.81 1 0
9 OFFICE 70.60 1 0
10 OFFICE 43.10 1 0
11 OFFICE 58.50 1 0
12 3BHK 66.93 2 0
13 2BHK 34.39 2 0
14 2BHK 51.88 4 0
15 2BHK 44.08 6 0
16 2BHK 47.90 2 0
17 2BHK 46.65 5 0
18 2BHK 48.83 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
JAY PACHILAGI CONSTRUCTIONS NA Contractor
LILADHAR PARAB ARCHITECTS NA Architect
STRUCTWEL DESIGNERS & CONSULTANTS PVT LTD NA Engineer
B N DUDANI & CO NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other