MahaRERA Application

General Information

Other Than Individual

Organization

MAZAGAON DOCK SAI CO-OP HSG SOC LTD
Societies
NA
Do you have any Past Experience ?
No

Address Details

PLOT NO.3
SUB PLOT NO.K
SECTOR-21 (TRANS RAILWAY AREA)
NEW PANVEL(WEST)
NEAR K MALL
MAHARASHTRA
Konkan
Raigarh
Panvel
New Panvel
410206

Organization Contact Details

02206177500

Past Experience Details

Member Information

Member Name Designation Photo
RAVINDRA B BHAGAT Chairperson View Photo
ANIL PANDURANG BHAGAT Secretory View Photo
BALIRAM K BHOIR Authorized Signatory View Photo

Project

MAZAGAON DOCK SAI CO-OP HSG SOC LTD
New Project
30/12/2022
30/12/2024
No
Residential
Yes
Sub Plot No K Plot No 3
9 mtrs wide Road
Panvel Municipal Boundaries
Open Plot
Sub Plot No D
MAHARASHTRA
Konkan
Raigarh
Panvel
New Panvel
Trans Railway Area
New Panvel (W)
410206
3810
2
1
1
557.26

FSI Details

3801.52
1913.48
5715.00

Bank Details

GS MAHANAGAR CO-OP BANK LTD
MCBL0960005

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
MAZAGAON DOCK SAI CO-OP HSG SOC LTD MAZAGAON DOCK SAI CO-OP HSG SOC LTD Societies Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Upload Agreement / MoU Copy
13 Upload Agreement / MoU Copy
14 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 30 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 AS PER APPROVED PLANS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 AS PER APPROVED PLANS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER APPROVED PLANS
Aggregate area of recreational Open Space : YES 100 AS PER APPROVED PLANS
Open Parking : YES 100 33 OPEN PARKING
Water Supply : YES 100 AS PER APPROVED PLANS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER APPROVED PLANS
Storm Water Drains : YES 100 AS PER APPROVED PLANS
Landscaping & Tree Planting : YES 0 As per approved plans
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 MAZAGAON DOCK SAI CO-OP HSG SOC LTD MAZAGAON DOCK SAI CO-OP HSG SOC LTD 31/12/2021 0 1 0 11 1 33 30
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 39.11 1 1
2 2BHK 46.66 5 5
3 3BHK 64.26 4 4
4 3BHK 66.93 4 4
5 2BHK 48.83 4 4
6 2BHK 46.65 8 8
7 2BHK 50.89 1 1
8 3BHK 66.41 1 1
9 2BHK 35.93 4 2
10 2BHK 44.09 4 4
11 2BHK 44.08 11 9
12 2BHK 47.90 5 4
13 2BHK 49.03 7 7
14 2BHK 51.88 9 9
15 2BHK 34.39 5 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 MAZAGAON DOCK SAI CO-OP HSG SOC LTD MAZAGAON DOCK SAI CO-OP HSG SOC LTD 31/12/2021 0 1 0 4 1 0 37
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 45.20 1 0
2 2BHK 45.38 1 0
3 2BHK 51.94 4 4
4 2BHK 56.15 2 2
5 3BHK 74.44 2 2
6 2BHK 52.08 1 1
7 2BHK 55.35 2 1
8 2BHK 55.30 1 1
9 3BHK 73.01 1 1
10 1BHK 37.97 2 1
11 1BHK 30.65 2 2
12 2BHK 53.98 4 4
13 2BHK 55.53 2 1
14 2BHK 52.63 4 3
15 2BHK 55.5 3 3
16 2BHK 57.64 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
JAY PACHILAGI CONSTRUCTIONS NA Contractor
LILADHAR PARAB ARCHITECTS NA Architect
STRUCTWEL DESIGNERS & CONSULTANTS PVT LTD NA Engineer
B N DUDANI & CO NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
6 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
7 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement