MahaRERA Application

General Information

Other Than Individual

Organization

SPACE BUILDERS & DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1
MATAI CHAMBERS
63
ERANDWANA
NEAR MHATRE BRIDGE
MAHARASHTRA
Pune
Pune
Haveli
Karve Nagar
411004

Organization Contact Details

02025432149

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1West Wind ParkResidentialNA2850Behind Shell petrol Pump Hinjewadi41/1 Hinjewadi Pune 41105701532015-06-302015-08-25
2SBM MYSTIQUEResidentialNA634VADGOANSHERIPlot No 4601102016-04-202016-06-10
3SBM MyraResidentialNA705Vadgoansheri3301112017-12-312017-11-15

Member Information

Member Name Designation Photo
NARI MADHAVDAS MATAI Partner View Photo
DILIP LALCHAND MATAI Authorized Signatory View Photo

Project

SHIVOM REGENCY
New Project
31/03/2020
30/03/2022
No
Others
No
Survey 176
Survey No 177
Road
Survey No176 Reservation Land
30mt Road
MAHARASHTRA
Pune
Pune
Haveli
Baner
Baner Mhalunge Road
Baner Village
411045
1598
2
1
1
0

FSI Details

1189
1500
2689.00

Bank Details

HDFC BANK
HDFC0001115

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 29 0 90

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 AS PER CONSULTANT
Water Conservation, Rain water Harvesting : YES 100 AS PER CONSULTANT
Energy management : YES 75 AS PER CONSULTANT
Fire Protection And Fire Safety Requirements : YES 90 AS PER CONSULTANT
Electrical Meter Room, Sub-Station, Receiving Station : YES 90 AS PER CONSULTANT
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 90 AS PER CONSULTANT
Water Supply : YES 50 PMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 AS PER CONSULTAN
Storm Water Drains : YES 90 AS PER CONSULTANT
Landscaping & Tree Planting : YES 90 AS PER CONSULTANT
Street Lighting : YES 95 AS PER CONSULTANT
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 90 AS PER CONSULTANT
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SHIVOM REGENCY SHIVOM REGENCY UP TO 3RD FLOOR 31/03/2020 01 01 0 06 0 07 25
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 08 84.87 01 01
2 SHOP 09 101.81 01 01
3 SHOP 07 90.69 01 0
4 SHOP 01 27.93 01 01
5 SHOP 06 40.32 01 01
6 SHOP 02 31.46 01 01
7 SHOP 03 36.07 01 01
8 FLAT 01 65.69 02 01
9 FLAT 03 67.46 02 01
10 FLAT 04 66.24 01 01
11 FLAT 05 55.54 01 01
12 SHOP 04 35.77 01 01
13 SHOP 05 41.38 01 01
14 FLAT 02 55.25 02 02
15 FLAT 06 68.61 01 01
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 00
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 99
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 77.4
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 SHIVOM REGENCY SHIVOM REGENCY UP TO EIGHTH FLOOR 31/03/2020 0 0 0 05 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 FLAT 11 55.22 01 01
2 FLAT 14 51.75 01 01
3 FLAT 13 65.79 01 01
4 FLAT 15 80.77 01 01
5 FLAT 18 80.82 01 0
6 FLAT 19 62.14 01 0
7 FLAT 12 67.66 01 01
8 FLAT 07 65.8 01 01
9 FLAT 09 67.88 02 01
10 FLAT 16 62.5 01 01
11 FLAT 17 84.06 01 01
12 FLAT 20 84.38 01 0
13 FLAT 08 55.48 01 01
14 FLAT 10 65.69 01 01
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 90
3 X number of Podiums 00
4 Stilt Floor 00
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
P K CONTRUCTION NA Contractor
LAXMI CONSTRUCTION NA Contractor
MALAN ELECTRICAL NA Contractor
AVINASH NAVATHE NA Architect
G A BHILARE CONSULTANTS PVT LTD NA Engineer
SKYLINE MEP CONSULTANTS NA Other Professional
SHILPA BAGADE NA Other Professional
MILIND ENTERPRISES NA Other Professional
SHEETAL HEMAL PAREKH A52100012356 Real Estate Agent
VIKAS SITARAM KUMBHAR A52100011723 Real Estate Agent
CORAZON HOMES AND SECURITIES A52100000096 Real Estate Agent
Ameeth Kothari A52100000092 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement