MahaRERA Application

General Information

Other Than Individual

Organization

Provenance Land Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

1/136
Four Seasons Hotels
Dr. E Moses Road
Worli
Opposite Jijamata Nagar
MAHARASHTRA
Konkan
Mumbai City
Ward GSouth
GSouth-400018
400018

Organization Contact Details

02224818910
www.mumbairesidences.com

Past Experience Details

Member Information

Member Name Designation Photo
Adarsh Rajkumar Jatia Managing Director View Photo
Rajkumar Subhkaran Jatia Chairperson View Photo
Adarsh Rajkumar Jatia Authorized Signatory View Photo

Project

Four Seasons Private Residences Phase - 1
On-Going Project
31/12/2020
31/12/2020
30/12/2022
No
Residential
No
1H/136
CS no 5-136
CS no 1B-136
CS no 1F-136 and 1G-136
CS no 1-136
MAHARASHTRA
Konkan
Mumbai City
Ward GSouth
GSouth-400018
Dr E Moses
Worli
400018
4069.37
1
1
0
610.41

FSI Details

9405.11
0
9405.11

Bank Details

HDFC Bank Limited
HDFC0000501

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 113 29 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Completed
Water Conservation, Rain water Harvesting : YES 100 Completed
Energy management : YES 100 Completed
Fire Protection And Fire Safety Requirements : YES 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Completed
Aggregate area of recreational Open Space : YES 100 Completed
Open Parking : NO 0 NA
Water Supply : YES 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 100 Completed
Landscaping & Tree Planting : YES 100 Completed
Street Lighting : YES 100 Completed
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Four Seasons Private Residences Phase - 1 Four Seasons Residences 30/12/2022 2 1 0 45 0 0 113
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Simplex 2401 258.03 1 1
2 Simplex 2501 258.03 1 1
3 Duplex5BHK 2701 445.82 1 1
4 Duplex5BHK 4401 462.02 1 1
5 Simplex 1701 248.10 1 1
6 Simplex 3801 258.03 1 0
7 Simplex 1901 249.38 1 0
8 Simplex 4601 261.78 1 1
9 Simplex 3701 258.03 1 1
10 Simplex 4101 260.94 1 1
11 Simplex 401 205.64 1 0
12 Simplex 402 40.71 1 0
13 Simplex 501 246.35 1 0
14 Simplex 601 246.35 1 0
15 Simplex 2601 213.90 1 1
16 Simplex 2602 44.13 1 1
17 Simplex 2901 258.03 1 1
18 Simplex 3001 258.03 1 1
19 South Duplex 3201 395.24 1 1
20 Simplex 801 246.35 1 0
21 Simplex2BHK 1001 179.91 1 0
22 Simplex 1101 249.38 1 0
23 Simplex 1201 247.05 1 0
24 Simplex 1401 162.74 1 1
25 Simplex 1402 40.11 1 1
26 Penthouse 4201 462.57 1 1
27 Simplex 701 246.35 1 0
28 Simplex2BHK 1801 141.53 1 1
29 Simplex2BHK 1802 38.67 1 1
30 Simplex 2101 247.05 1 1
31 Simplex 2001 247.05 1 1
32 North Duplex 3401 379.48 1 1
33 Simplex 1403 44.20 1 1
34 Simplex 1501 248.10 1 0
35 Simplex 1601 248.10 1 0
36 Duplex5BHK 3501 402.18 1 1
37 Simplex 4701 261.78 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RSP Design Consultants India Private Limited Project Architect NA Architect
Capacite Infraprojects Private Limited NA Contractor
Sterling Engineering Consultants Private Limited NA Engineer
360 degrees A51800002698 Real Estate Agent
Kwality Developers Private Limited A51900003001 Real Estate Agent
JONES LANG LASALLE RESIDENTIAL PRIVATE LIMITED A51900000108 Real Estate Agent
bhujanga gopal shetty A51800000240 Real Estate Agent
RAMAKANT RAMSANEHI TIWARI A51800003481 Real Estate Agent
CBRE South Asia Private Limited A51600003050 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
Knight Frank (India) Private Limited A51900000099 Real Estate Agent
MAK KOTWAL REALTY A51900003562 Real Estate Agent
RAMAKANT RAMSANEHI TIWARI A51800003481 Real Estate Agent
FOREST REALTY A51900003397 Real Estate Agent
MATRIX RECON PRIVATE LIMITED A51900004184 Real Estate Agent
4th Gen Realty LLP A51900002870 Real Estate Agent
Shashank Mehendale & Associates Licensed Surveyor NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout) and Building Plan Approval (IOD)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement