MahaRERA Application

General Information

Other Than Individual

Organization

Joyville Shapoorji Housing Private Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

41/44
SP Centre
Minoo Desai Marg
Colaba
Radio Club
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400005

Organization Contact Details

02267490101

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Joyville HowrahResidentialNA13937KWIC HowrahR2B33922020-06-302020-02-25

Member Information

Member Name Designation Photo
Ranjana Agarwal Director View Photo
Subrata Dutta Gupta Director View Photo
Sandeep Awasthi Director View Photo
Anuj Puri Director View Photo
Venkatesh Gopalkrishnan Chairperson View Photo
Sriram Mahadevan Managing Director View Photo
Ashish Singh Director View Photo

Project

Joyville Hadapsar Sky-Luxe
New Project
31/12/2026
Yes
Residential
Yes
6/7/9/10/6 Part
6-7-9-10-6 Part
6-7-9-10-6 Part
6-7-9-10-6 Part
Proposed Canal Road 6-7-9-10-2
MAHARASHTRA
Pune
Pune
Haveli
Shewalewadi
Off Pune Solapur Highway
Shewalewadi
412307
2743.11
2
2
0
462.91

FSI Details

22822.14
4815.2
27637.34

Bank Details

HDFC Bank
HDFC0000060

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Joyville Hadapsar Sky-Luxe Manjri Horse Breeders' Private Limited Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 212 182 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Common for all phases
Water Conservation, Rain water Harvesting : YES 0 Common for all phases
Energy management : YES 0 As per MOEF Submission
Fire Protection And Fire Safety Requirements : YES 0 As per CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Phasewise Development
Covered Parking : YES 0 Phasewise Development
Aggregate area of recreational Open Space : YES 0 Common for all phases
Open Parking : NO 0 NA
Water Supply : YES 0 Common for all phases
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Common for all phases
Storm Water Drains : YES 0 Common for all phases
Landscaping & Tree Planting : YES 0 Common for all phases
Street Lighting : YES 0 Internal road street lighting only
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Common for all phases
Solid Waste Management And Disposal : YES 0 Phasewise Development

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Joyville Hadapsar Sky-Luxe Tower 2 31/12/2026 1 1 2 20 1 0 84
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK Duplex 106.7 1 0
2 3 BHK Duplex 108.15 4 4
3 3 BHK Duplex 108.14 4 4
4 3 BHK Duplex 108 75 57
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 10
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Joyville Hadapsar Sky-Luxe Tower 3 31/12/2026 1 1 2 20 1 0 84
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK Duplex 108.15 4 4
2 3 BHK Duplex 108.14 4 4
3 3 BHK Duplex 108 76 66
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 10
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MSK Architect and Associates NA Architect
Mr Akshay Lalit Kasar NA Engineer
Bhavesh Nagda NA Chartered Accountant
PROPERTYPISTOL REALTY PRIVATE LIMITED A51700000043 Real Estate Agent
Makaan Hunt Pvt Ltd A52100000430 Real Estate Agent
Taushiefraja Rashid Shaikh A52100006911 Real Estate Agent
Manisha Lifespaces Consulting Pvt. Ltd. A51800008040 Real Estate Agent
VBUZZ INFRA PVT LTD A52000009542 Real Estate Agent
SMC REAL ESTATE ADVISORS PRIVATE LIMITED A51900000042 Real Estate Agent
ASHISH SUMATILAL SOLANKI A52100024819 Real Estate Agent
DHANAJI UTTAM PAWAR A52100008657 Real Estate Agent
Vinit Vijay Tiwari A50500022443 Real Estate Agent
Nikhil Sunil Harpale A52100030145 Real Estate Agent
SEEMA DEEPAK KHOMANE A52100027946 Real Estate Agent
PROPSOLUTIONS4U PRIVATE LIMITED A51900029955 Real Estate Agent
MAHESH GANESH GAIKWAD A52100035257 Real Estate Agent
PROPBIZZ REAL ESTATE A52100039446 Real Estate Agent
Mitosh Subhash Navale A52100024451 Real Estate Agent
YOGESH NARAYAN KALBHOR A52100025680 Real Estate Agent
MUKUND NAMASE A52100036061 Real Estate Agent
METRO HOMES A52100043797 Real Estate Agent
AMARDEEP UTTRESHWAR DHAS A52100005740 Real Estate Agent
Vinit Vijay Tiwari A50500022443 Real Estate Agent
PROPERTYPISTOL REALTY PRIVATE LIMITED A51700000043 Real Estate Agent
Manisha Lifespaces Consulting Pvt. Ltd. A51800008040 Real Estate Agent
SMC REAL ESTATE ADVISORS PRIVATE LIMITED A51900000042 Real Estate Agent
PROPSOLUTIONS4U PRIVATE LIMITED A51900029955 Real Estate Agent
VBUZZ INFRA PVT LTD A52000009542 Real Estate Agent
Makaan Hunt Pvt Ltd A52100000430 Real Estate Agent
AMARDEEP UTTRESHWAR DHAS A52100005740 Real Estate Agent
Taushiefraja Rashid Shaikh A52100006911 Real Estate Agent
DHANAJI UTTAM PAWAR A52100008657 Real Estate Agent
Mitosh Subhash Navale A52100024451 Real Estate Agent
ASHISH SUMATILAL SOLANKI A52100024819 Real Estate Agent
YOGESH NARAYAN KALBHOR A52100025680 Real Estate Agent
SEEMA DEEPAK KHOMANE A52100027946 Real Estate Agent
Nikhil Sunil Harpale A52100030145 Real Estate Agent
MAHESH GANESH GAIKWAD A52100035257 Real Estate Agent
MUKUND NAMASE A52100036061 Real Estate Agent
PROPBIZZ REAL ESTATE A52100039446 Real Estate Agent
METRO HOMES A52100043797 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Joyville Hadapsar Sky-Luxe Court of Civil Judge Senior Division Pune 32 Civil No Suit NA 2009 Evidence Stage
NA
Joyville Hadapsar Sky-Luxe Bombay High Court WP No 1311 2019 Civil No Writ Petition NA 2019 Pre Admission
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement