MahaRERA Application

General Information

Other Than Individual

Organization

HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

9-01
HDIL TOWERS
ANANT KANEKAR MARG
BANDRA(EAST)
NEAR SMALL CAUSES COURT
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400051

Organization Contact Details

02267888000
www.hdil.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1HDIL INDUSTRIAL PARKIndustrialNA32449BESIDES LAXMI MARBLES CHANDANSAR ROAD VILLAGE CHANDANSAR VIRAR EASTS NO 123 VILLAGE CHANDANSAR256272017-04-302017-07-25
2HDIL RESIDENCY PARKResidentialNA27149OPP YAZOO PARK NARANGI BYPASS ROAD VILLAGE DONGRE VIRAR WESTSURVEY NO 214 VILLAGE DONGRE711992011-08-012015-10-14
3GALAXY APARTMENTS WING ABEResidentialNA5974.45BHANDARY ESTATE KURLA EAST MUMBAI 40002413/1TO4,13/14B,PART OF 13/16,20,2133142011-12-312017-06-19
4PREMIER RESIDENCESOthersRESIDENTIAL AND COMMERCIAL15504.68PREMIER AUTO KURLA WEST MUMBAI - 400070637A/P,637/72P,637/44to46,637/53P,637/54P,637/73to77,637/87to90P1110872012-12-302017-03-09
5PREMIER EXOTICA IIOthersRESIDENTIAL AND COMMERCIAL2151.39PREMIER AUTO KIROL ROAD KURLA WEST MUMBAI 400070637/A-P1832013-06-302017-06-19
6HARMONYOthersRESIDENTIAL AND COMMERCIAL11549.20NEW LINK ROAD GOREGAON WEST MUMBAI 4001041A58B1APT12212013-06-302017-07-04

Member Information

Member Name Designation Photo
SARANG WADHAWAN Managing Director View Photo
SARANG RAKESH WADHAWAN Authorized Signatory View Photo

Project

GALAXY APARTMENTS CDF WINGS
On-Going Project
30/11/2017
31/01/2021
No
Others
No
13-PT,13/2-PT,13/3-PT
D P ROAD
REHAB BUILDING
RECREATION GROUND
INTERNAL ROAD
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
Near Bunder Bhavan
Kurla East
400070
3013.81
3
3
0
2339.98

FSI Details

18955.42
0
18955.42

Bank Details

BHARAT COOPERATIVE BANK LIMITED
BCBM0000070

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 93 73 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 TO COMMENCE
Energy management : YES 0 TO COMMENCE
Fire Protection And Fire Safety Requirements : YES 0 TO COMMENCE
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 WORK IN PROGRESS
Aggregate area of recreational Open Space : YES 0 TO COMMENCE
Open Parking : NO 0 NA
Water Supply : YES 0 TO COMMENCE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 50 WORK IN PROGRESS
Storm Water Drains : YES 0 TO COMMENCE
Landscaping & Tree Planting : NO 0 NA
Street Lighting : YES 0 TO COMMENCE
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 TO COMMENCE
Solid Waste Management And Disposal : YES 0 TO COMMENCE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 GALAXY APARTMENTS CDF WINGS WING C 2 1 0 18 1 0 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 21.59 2 2
2 RESIDENTIAL 36.60 32 32
3 RESIDENTIAL 52.25 67 67
4 SHOPS 7.82 1 1
5 SHOP 8.27 1 1
6 SHOP 15.16 2 2
7 SHOP 20.53 3 3
8 SHOP 19.87 1 1
9 SHOP 17.18 2 2
10 SHOP 16.14 2 2
11 SHOP 18.12 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

75
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 64.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 GALAXY APARTMENTS CDF WINGS WING - D 2 1 0 18 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 36.75 32 32
2 SHOPS 22.18 1 1
3 SHOPS 19.98 1 1
4 SHOPS 20.55 3 3
5 SHOPS 16.15 2 2
6 SHOPS 17.22 2 2
7 SHOPS 21.61 4 4
8 SHOPS 31.32 1 1
9 RESIDENTIAL 52.19 101 101
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 GALAXY APARTMENTS CDF WINGS WING - F 2 1 0 18 1 0 31
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 36.42 50 50
2 RESIDENTIAL 56.41 15 15
3 RESIDENTIAL 55.63 34 34
4 SHOPS 21.59 1 1
5 SHOPS 20.53 1 1
6 SHOPS 16.14 1 1
7 SHOPS 19.95 1 1
8 SHOPS 18.60 2 2
9 SHOPS 11.25 4 4
10 SHOPS 31.99 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Rashmi Construction NA Contractor
Indrajeet S. Deshmukh NA Architect
Hydro mechanical Consultants NA Other Professional
H M RAJE STRUCTURAL CONSULTANTS PVT LTD NA Engineer
ATUL K THAKKAR A51800000037 Real Estate Agent
Dipti Manohar Patil A51900003514 Real Estate Agent
Anil Ranvir Khanna A51800002265 Real Estate Agent
Ankesh Anil Khanna A51800001860 Real Estate Agent
Sabby Anil Khanna A51800002284 Real Estate Agent
Munnalal Rajmani Yadav A51800000659 Real Estate Agent
M/s. Satish Mehta & Company A51800000375 Real Estate Agent
HDFC DEVELOPERS LIMITED A51900000930 Real Estate Agent
Mahesh Amarnath Yadav A51900004200 Real Estate Agent
Akshay Sharva Construction Pvt.Ltd A51800002036 Real Estate Agent
SAMIR HARISH CHHEDA A51800001118 Real Estate Agent
MAHAVIR PRASAD TOSHNIWAL A51700003016 Real Estate Agent
JMB ENTERPRISES A51900002212 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
Honeydew Advisory Services Pvt LTD A51800004408 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
11 Copy of Layout Approval (in case of layout)
12 Copy of Layout Approval (in case of layout)
13 Copy of Layout Approval (in case of layout)
14 Copy of Layout Approval (in case of layout)
15 Copy of Layout Approval (in case of layout)
16 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000001570 Melbourne B. Trinidade View Orders
2 CC006000000054859 Manjhusha Chaugule View Orders
3 CC006000000054859 Ghanshyam Kuldeep View Orders
4 CC006000000054859 David Francis Dias View Orders
5 CC006000000054862 Sayed Akhlaque Ahmed View Orders
6 CC006000000054862 Munshiraza Shaikh View Orders
7 CC006000000054862 Ritu G. Lamba View Orders
8 CC006000000054863 Deepak Shankar Kamat View Orders
9 CC006000000054863 Gulab Dinkar Gaikwad View Orders
10 CC006000000054863 Shalki Parrikshit Chaugule View Orders
11 CC006000000054865 Dawood Abdullah Shah View Orders
12 CC006000000054865 Nakhwa Mohd Mohsin View Orders
13 CC006000000054865 Sudhir Shantaram Patil View Orders
14 CC006000000054988 Agnel Antonio Marian Pereira View Orders
15 CC006000000054988 Mrs. Mariya JacintaJoyce Pereira View Orders
16 CC006000000054988 Ramesh Dube-Patil View Orders
17 CC006000000001570 MELBA B. TRINIDADE View Orders
18 CC006000000056977 Suresh Waghmare View Orders
19 CC006000000057998 Satish Suresh Adsul View Orders
20 CC006000000078891 Leeladevi Hundia View Orders
21 CC006000000078891 Abhishek Hundia View Orders
22 CC006000000089752 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
23 CC006000000089753 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
24 CC006000000089755 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
25 CC006000000089756 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
26 CC006000000089757 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
27 CC006000000089750 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
28 CC006000000089749 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
29 CC006000000089758 HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD View Orders
30 CC006000000089910 Galaxy Apartment C Wing Purchasers Association View Orders