MahaRERA Application

General Information

Other Than Individual

Organization

SAIRAJDEVELOP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

G-1
SAI ANAND PLAZA
MIRA BHY ROAD
MIRA ROAD EAST
OPP OLD GOLDENNEST
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401107

Organization Contact Details

02228040707

Past Experience Details

Member Information

Member Name Designation Photo
AKBAR BASIR PATHAN Authorized Signatory View Photo
HAREN CHANDULAL SHAH Partner View Photo

Project

RUHEENA APPARTMENT
On-Going Project
31/12/2020
30/12/2022
No
Others
No
S NO 17 HISSA NO 5,10
SNO 154
SNO 98 15MTR D P ROAD
SNO 16
15 MTR DP ROAD
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401104
3009.52
1
1
0
588

FSI Details

3010
877
3887.00

Bank Details

AXIS BANK
UTIB0002900

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 DONE
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 DONE
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 D0NE
Aggregate area of recreational Open Space : YES 100 DONE
Open Parking : NO 0 NA
Water Supply : YES 0 BY MBMC AFTER OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 DONE
Storm Water Drains : YES 100 DONE
Landscaping & Tree Planting : YES 100 DONE
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 DONE
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 RUHEENA APPARTMENT RUHEENA APPARTMENT A B C WING 30/06/2022 0 1 0 8 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 COMMERCIAL A WING 8.66 1 1
2 COMMERCIAL A WING 13.35 1 1
3 COMMERCIAL A WING 15.80 1 1
4 COMMERCIAL A WING 12.79 1 1
5 RESIDENTIAL A WING 34.11 7 7
6 RESIDENTIAL A WING 33.99 7 7
7 RESIDENTIAL A WING 34.71 7 7
8 RESIDENTIAL A WING 34.56 7 7
9 COMMERCIAL B WING 12.92 1 1
10 COMMERCIAL B WING 12.47 1 1
11 COMMERCIAL B WING 13.11 1 1
12 COMMERCIAL B WING 11.82 1 1
13 RESIDENTIAL B WING 33.67 7 7
14 RESIDENTIAL B WING 33.67 7 7
15 RESIDENTIAL B WING 47.64 7 7
16 RESIDENTIAL B WING 35.08 7 7
17 COMMERCIAL A WING 6.52 1 1
18 COMMERCIAL A WING 15.80 1 1
19 COMMERCIAL A WING 12.35 1 1
20 RESIDENTIAL B WING 35.72 7 7
21 RESIDENTIAL B WING 33.65 7 7
22 COMMERCIAL B WING 18.56 2 2
23 RESIDENTIAL C WING 34.69 7 7
24 RESIDENTIAL C WING 34.69 7 7
25 RESIDENTIAL C WING 34.52 7 7
26 RESIDENTIAL C WING 34.89 7 7
27 COMMERCIAL A WING 14.99 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
B A C PLANNERS PVT LTD NA Architect
B A C PLANNERS PVT LTD NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement