MahaRERA Application

General Information

Other Than Individual

Organization

TODAY GLOBAL HOMES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO.-1601 & 1602, 16TH FLOOR
KESAR SOLITAIRE
PLOT NO.-05, SECTOR NO.-19
PALM BEACH ROAD
SANPADA, NAVI MUMBAI
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02227575700

Past Experience Details

Member Information

Member Name Designation Photo
BHADRESH RAJESH SHAH Partner View Photo
BHAVESH RAJESH SHAH Partner View Photo
SUNIL JAGDISH AGRAWAL Partner View Photo
BHADRESH RAJESH SHAH Authorized Signatory View Photo
RAJESH BHOGILAL SHAH Partner View Photo

Project

ANANDAM PHASE - II
New Project
30/12/2024
No
Residential
Yes
PORTION OF LAND OUT OF GUT N-13, 122, 16A, 16B, 16C, 14, 21, 22, 35A, 35B, 53 AND 1111
SURVEY NO - 5-4
SURVEY NO - 1-6-D 24 MW PROP D P ROAD
SURVEY NO - 121-2
SURVEY NO - 109-0
MAHARASHTRA
Konkan
Raigarh
Panvel
Rohinjan
ROHINJAN
PANVEL
410206
11624.40
4
4
0
1828

FSI Details

41045
0
41045.00

Bank Details

ICICI BANK LTD
ICIC0006990

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II RAVINDRA PANDURANG PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II ARCHANA RAGHUNATH PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II KACHRU BHOKYA PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II YOGESH YASHWANT PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II BAIJUNATH VASANT PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II GURUNATH VASANT PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ANANDAM PHASE - II SHRIPAT KALURAM PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WILL BE PROVIDED AS PER APPROVED PLAN
Water Conservation, Rain water Harvesting : YES 0 WILL BE PROVIDED AS PER GOVT NORMS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 WILL BE PROVIDED AS PER GOVT NORMS
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 ELECTRICAL METER ROOM ONLY
Aggregate area of recreational Open Space : YES 0 WILL BE PROVIDED AS PER APPROVED PLAN
Open Parking : NO 0 NA
Water Supply : YES 0 WILL BE PROVIDED AS PER GOVT NORMS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WILL BE PROVIDED AS PER APPROVED PLAN
Storm Water Drains : YES 0 WILL BE PROVIDED AS PER APPROVED PLAN
Landscaping & Tree Planting : YES 0 TREE PLANTING ONLY
Street Lighting : NO 0 NA
Community Buildings : YES 0 WILL BE PROVIDED AS PER APPROVED PLAN
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ANANDAM PHASE - II BUILDING NO - 4 31/12/2023 0 1 3 24 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.16 52 43
2 1BHK 34.18 46 24
3 1BHK 34.66 44 35
4 2BHK 57.03 40 40
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 75
4 Stilt Floor 100
5 X number of Slabs of Super Structure 96
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 68.1
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ANANDAM PHASE - II BUILDING NO - 5A 31/12/2023 0 1 5 26 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 21.59 2 0
2 Shop 26 2 0
3 Office space 29.15 2 0
4 Office space 29.29 1 0
5 Office space 29.38 1 0
6 Office space 30.22 4 0
7 Office space 32.09 2 0
8 Shop 34.71 1 0
9 Shop 34.8 1 0
10 Shop 35.16 2 0
11 Shop 35.64 4 0
12 Shop 37.84 2 0
13 1BHK 35.24 12 3
14 1BHK 36.19 12 3
15 3BHK 76.43 82 41
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 88
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 24
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 23
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 76
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

1
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 51.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 ANANDAM PHASE - II BUILDING NO - 5 B 31/12/2023 0 1 5 26 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 21.2 2 0
2 Office space 21.98 2 0
3 Office space 23.8 1 0
4 Shop 33.08 2 2
5 Shop 35.25 3 1
6 2BHK 54.1 90 54
7 2BHK 54.26 94 58
8 Shop 35.25 1 0
9 Shop 37.7 2 0
10 Shop 25.54 2 1
11 Shop 25.92 2 1
12 Shop 28.09 1 1
13 Shop 28.73 1 1
14 Office space 24.45 1 0
15 Office space 27.47 2 0
16 Office space 29.68 4 0
17 Office space 31.89 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 56
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 8
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 9
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 48
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42.1
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 ANANDAM PHASE - II BUILDING NO - 5C 31/12/2023 0 1 5 26 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 21.59 2 0
2 Shop 26 2 0
3 Office space 29.15 2 0
4 Office space 29.29 1 0
5 Office space 29.38 1 0
6 Office space 30.22 4 0
7 Office space 32.09 2 0
8 Shop 34.71 1 0
9 Shop 34.8 1 0
10 Shop 35.16 2 0
11 Shop 35.64 4 0
12 Shop 37.84 2 0
13 1BHK 35.24 12 6
14 1BHK 36.19 12 7
15 3BHK 76.44 82 20
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 52
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 4
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 39
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SWAPNIL KALYANKAR ARCHITECTS NA Architect
STRUCTURAL CONCEPT DESIGNS PVT LTD NA Engineer
GANESH MAHADEV SUTAR A52000026365 Real Estate Agent
Riya Haresh Rochani A51700002538 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
11 Architect’s Certificate of Percentage of Completion of Work (Form 1)
12 Architect’s Certificate of Percentage of Completion of Work (Form 1)
13 Architect’s Certificate of Percentage of Completion of Work (Form 1)
14 Architect’s Certificate of Percentage of Completion of Work (Form 1)
15 Architect’s Certificate of Percentage of Completion of Work (Form 1)
16 Architect’s Certificate of Percentage of Completion of Work (Form 1)
17 Architect’s Certificate of Percentage of Completion of Work (Form 1)
18 Architect’s Certificate of Percentage of Completion of Work (Form 1)
19 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
6 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement