MahaRERA Application

General Information

Other Than Individual

Organization

Shivram Developers
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

CTS NO.216
Alok Society
Lal Bahadur Shastri Road
Navi Peth
Navi Peth
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411030

Organization Contact Details

02024260025

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Suyog Aura Phase IResidentialNA12614.98Warje Pune 411052S No 119/8/3 Warje2872014-12-312015-02-07

Member Information

Member Name Designation Photo
Nilesh Bharat Shah Partner View Photo
Dilip Madanlal Bhootra Partner View Photo
Kalpesh Bharat Shah Authorized Signatory View Photo
Bharat Keshavlal Shah Partner View Photo
Kalpesh Bharat Shah Partner View Photo
Sunil Madanlal Bhutada Partner View Photo
Hemendra Keshavlal Shah Partner View Photo

Project

Suyog Aura Phase II
On-Going Project
31/12/2019
30/12/2021
Yes
Residential
No
Survey No.119/8/3
Marginal Open Space
Marginal Open Space
Amenity Space
Open Space
MAHARASHTRA
Pune
Pune
Haveli
Warje
Warje
Warje
411052
3768.74
2
2
0
1168.41

FSI Details

13475.41
711
14186.41

Bank Details

Bank of Maharashtra
MAHB0001444

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 74 6 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Trimix road No footpath
Water Conservation, Rain water Harvesting : YES 100 Recharge Pit
Energy management : YES 100 Solar hot water system at roof top of building
Fire Protection And Fire Safety Requirements : YES 100 Wet riser and PA System
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Meter room to be provided receiving station provid
Aggregate area of recreational Open Space : YES 100 Already developed
Open Parking : YES 100 Proposed to be sanctioned
Water Supply : YES 100 Seperate pipe line for domestic and drinking water
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP to be provided
Storm Water Drains : YES 100 Will be connected to Recharge pit
Landscaping & Tree Planting : YES 100 Landscaping Completed. Tree plantation as per NOC
Street Lighting : YES 100 LED lights
Community Buildings : YES 100 Construction of Club House Completed
Treatment And Disposal Of Sewage And Sullage Water : YES 100 STP to be provided
Solid Waste Management And Disposal : YES 100 OWC plant is in operation

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Suyog Aura Phase II A 31/12/2020 0 1 0 13 1 0 37
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RHK 61.38 1 0
2 1RHK 47.37 1 1
3 2RHK 57.16 6 6
4 2RHK 55.72 6 5
5 2RHK 57.44 6 6
6 2RHK 61.00 5 3
7 2RHK 55.45 6 5
8 2RHK 63.05 5 5
9 2RHK 61.27 6 3
10 2RHK 63.36 6 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Suyog Aura Phase II B 31/12/2020 0 1 0 13 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Paresh Koshti and Associates NA Architect
S W Mone and Associates NA Engineer
C V CHITALE NA Chartered Accountant
AKSHAY MODAK NA Chartered Accountant
S S CONSTRUCTION NA Contractor
SARIKA INFRATECH NA Contractor
TIRUPATI CONSTRUCTIONS NA Contractor
GURUDATTA ENTERPRISES NA Contractor
NEW SUMAN ENTERPRISES NA Contractor
SANKET CONSTRUCTION NA Contractor
FARIHA INTERIOR DECORATORS NA Contractor
PLASTO CEIL INDIA NA Contractor
STAR ENTERPRISES NA Contractor
R R CHAUDHARI CONTRACTOR NA Contractor
AMAN ENTERPRISES NA Contractor
CONSTROVISION ENGINEERING CONSULTANTS PVT LTD NA Contractor
SHANKAR RATHOD NA Contractor
NOOR MOHMMAOD FABRICATOR NA Contractor
DIGAMBAR DINDE NA Contractor
GURURAJ ENTERPRISES NA Contractor
ADITYA CONSTRUCTION NA Contractor
KANSARA ENTERPRISES NA Contractor
QUALCON LABORATORIES PVT LTD NA Contractor
KIRAN VILAS SHAH NA Engineer
ARIHANT CONSULTANT AND ASSOCIATES NA Other Professional
DBM WATER TECH PVT LTD NA Other Professional
Prashant Ugale A52100012660 Real Estate Agent
Jyoti Prashant Bhosale A52100012559 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Suyog Aura Phase II Senior Division 1498 Civil No Suit NA 2014 In view of the application for withdrawl the suit is disposed off
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement