MahaRERA Application

General Information

Other Than Individual

Organization

Sai Siddhi Properties
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Shop No.1
Ajinkya Suburb
S.No.50/1B, Dinkar Pathare Vasti,
Chandan Nagar, Kharadi,
Near NEI Bus Stop,
MAHARASHTRA
Pune
Pune
Haveli
KHARADI
411014

Organization Contact Details

02024370061

Past Experience Details

Member Information

Member Name Designation Photo
Ravindra Chambanna Yaranal Partner View Photo
Adinath Hanumant Lokhande Partner View Photo
Adinath Hanumant Lokhande Authorized Signatory View Photo

Project

Sai Safalya
New Project
09/09/2019
09/09/2022
No
Residential
Yes
49/2, 49/3, 49/4 pothissa No. 24
Mahalaxmi Buiding
Tathe Plot
6 mtr road
6 mtr road
MAHARASHTRA
Pune
Pune
Haveli
DHANORI
411015
685
2
2
0
0.0

FSI Details

806.79
0
806.79

Bank Details

Vijaya Bank
VIJB0005130

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Sai Safalya Maruti Waghmare Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Sai Safalya Gautam Waghmare Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0.0 0.0 0.0
Covered Parking ( In Numbers) 16 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Rain Water Harvesting
Energy management : YES 0 Solar Hot Water System
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Meter Room
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 Two wheeler Parking
Water Supply : YES 0 Borewell and PMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 To be Connected to PMC sewerage line
Storm Water Drains : YES 90 Drain constructed
Landscaping & Tree Planting : YES 0 As per rule
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Sai Safalya Wing A 0 1 0 4 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK A203 A204 30.20 2 0
2 1 BHK A101 A301 36.22 2 0
3 1 BHK A102 A302 30.40 2 0
4 1 BHK A103 A303 30.29 2 0
5 1 BHK A104 A304 36.11 2 0
6 1 BHK A201 A202 29.99 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Sai Safalya Wing B 0 1 0 4 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK B101 B102 41.78 2 0
2 1 BHK B201 B202 40.17 2 0
3 1 BHK B301 B302 41.78 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Santosh Patil NA Engineer
Nilesh Saswade NA Architect
Suyog S Deshpande NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement