MahaRERA Application

General Information

Individual

Individual

Laxman
Sopanrao
Nimhan
Sopanrao Ranu Nimhan
No

Address For Official Communication

102
ORIANA
BANER
BANER
S.N.35 Behind renualt show room
MAHARASHTRA
Pune
Pune
Haveli
Baner
411045

Contact Details

02025677778

Past Experience Details

Project

PLATINUM TOWERS
On-Going Project
30/06/2024
30/06/2024
No
Others
No
175/1/1B
Open space
s n 175 part
12 m wide road
B wing
MAHARASHTRA
Pune
Pune
Mulshi
Wakad
wakad kalewadi road
wakad
411057
4611.67
2
2
0
570

FSI Details

9262.73
4184.27
13447.00

Bank Details

BANK OF INDIA
BKID0000536

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 42 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 AS PER NORMS
Energy management : YES 100 AS PER NORMS
Fire Protection And Fire Safety Requirements : YES 100 AS PER NORMS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER NORMS
UGWT : YES 0 AS PER NORMS
WATCHMEN CABIN ENTRANCE GATE : YES 100 AS PER REQUIRMENTT
Aggregate area of recreational Open Space : YES 0 AS PER NORMS
Open Parking : NO 0 NA
Water Supply : YES 0 AS PER NORMS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER NORMS
Storm Water Drains : YES 100 AS PER REQUIRMENT
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 100 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 AS PER NORMS
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 PLATINUM TOWERS C 31/12/2023 2 1 1 15 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 48.69 2 2
2 2BHK 47.41 2 2
3 2BHK 45.75 2 2
4 2BHK 55.11 3 3
5 2BHK 55.82 3 3
6 2BHK 55.81 3 3
7 2BHK 54.85 6 6
8 2BHK 55.12 3 3
9 Shop 34.33 1 0
10 Shop 34.25 2 0
11 Shop 54.11 1 0
12 Shop 34.61 1 0
13 Shop 44.48 1 0
14 Shop 44.63 1 0
15 2BHK 45.71 3 3
16 2BHK 48.66 2 2
17 2BHK 55.80 3 3
18 2BHK 55.78 3 3
19 2BHK 44.60 2 2
20 2BHK 47.44 2 2
21 2BHK 45.58 2 2
22 2BHK 44.58 2 2
23 2BHK 54.84 6 6
24 2BHK 47.43 1 1
25 1BHK 33.5 4 4
26 1BHK 37.32 3 3
27 1BHK 37.25 3 3
28 1BHK 37.23 6 6
29 1BHK 37.01 7 7
30 1BHK 33.58 2 2
31 1BHK 37.1 3 3
32 1BHK 50.64 1 1
33 2BHK 54.57 6 6
34 1BHK 33.55 2 2
35 2BHK 48.12 6 6
36 2BHK 44.75 4 4
37 1BHK 33.36 3 2
38 1BHK 33.6 3 2
39 1BHK 33.27 6 4
40 1RK 24.73 2 1
41 1RK 27.39 2 1
42 1RK 20.49 4 2
43 1RK 27.62 2 2
44 1RK 20.74 4 2
45 1RK 23.85 6 4
46 1RK 27.61 5 3
47 1RK 29.96 3 2
48 1RK 24.96 4 2
49 1RK 24.72 2 1
50 1RK 27.85 5 3
51 1RK 24.1 4 3
52 1RK 30.12 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
DILIP G KALE & ASSOCIATES NA Architect
R K RANDHAVE CONSULTANT NA Engineer
K L N INFRA NA Contractor
WISTERIA REAL VISION PVT LTD A52100003089 Real Estate Agent
Abhijeet Bhagwan Sabale A52100014389 Real Estate Agent
Trishul Buildcon NA Contractor
ArchSachin soni NA Architect
m s joshi & associates NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement