MahaRERA Application

General Information

Other Than Individual

Organization

SUNGUARD BUILDERS LLP
Others
LIMITED LIABILITY PARTNERSHIP FIRM
Do you have any Past Experience ?
Yes

Address Details

5TH FLOOR
PRIDE HOUSE
108/7 GANESH KHIND ROAD
SHIVAJI NAGAR
NEAR PUNE UNIVERCITY
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411016

Organization Contact Details

02067091000

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1PARK IVORY PHASE IResidentialNA9290.26S NO 214 & 215 WAKAD TALUKA HAVELI DIST PUNE214 21542802017-07-312017-04-26

Other Organization Type Member Information

Name Member Type
NAVIN AGARWAL Individual

Project

PARK IVORY PHASE III
New Project
30/04/2024
Yes
Residential
Yes
S NO 214 215
BUILDING H AND OPEN SPACE
BUILDING B
PART OF LARGER LAYOUT
BOUNDARY OF LARGER LAYOUT
MAHARASHTRA
Pune
Pune
Mulshi
KALEWADI PHATA
WAKAD
411057
2506.93
1
1
0
00

FSI Details

8682.88
4812.93
13495.81

Bank Details

KOTAK MAHINDRA BANK
KKBK0001759

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
PARK IVORY PHASE III SUNGUARD BUILDERS LLP Others Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 00 00 00
Covered Parking ( In Numbers) 90 00 00

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 APPLICABLE
Water Conservation, Rain water Harvesting : YES 100 APPLICABLE
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 APPLICABLE
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 APPLICABLE
Aggregate area of recreational Open Space : YES 100 APPLICABLE
Open Parking : NO 0 NA
Water Supply : YES 100 APPLICABLE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 APPLICABLE
Storm Water Drains : YES 100 APPLICABLE
Landscaping & Tree Planting : YES 100 APPLICABLE
Street Lighting : YES 100 APPLICABLE
Community Buildings : YES 100 APPLICABLE
Treatment And Disposal Of Sewage And Sullage Water : YES 100 APPLICABLE
Solid Waste Management And Disposal : YES 100 APPLICABLE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 PARK IVORY PHASE III BUILDING A 30/04/2024 0 1 1 15 1 00 90
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 79.13 2 2
2 2BHK 79.31 2 2
3 3BHK 107.00 14 14
4 3BHK 107.96 4 3
5 2BHK 78.55 12 12
6 2BHK 74.65 1 0
7 3BHK 106.62 14 13
8 2BHK 68.46 4 1
9 2BHK 77.71 14 14
10 2BHK 78.16 12 10
11 2BHK 78.22 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
DREAMSPACE ARCHITECT NA Architect
VILAS JAGDALE NA Engineer
BRIJ MANTRI & COMPANY NA Chartered Accountant
CHAHAT DHEERAJ PARWANI A52100019093 Real Estate Agent
Susmit Sandesh Hingmire A52600025868 Real Estate Agent
GAURAV SURESH NAHTA A52100003487 Real Estate Agent
Ravi Kant Khare A52100022139 Real Estate Agent
SHAILENDRA KUMAR TIWARI A52100021499 Real Estate Agent
RISHABH JAIN A52100022928 Real Estate Agent
ABHISHEK ARVIND PATIL A52100005989 Real Estate Agent
PRASHANT NARAYANAN NAIR A52100022105 Real Estate Agent
Sanjay G Makhani A52100018386 Real Estate Agent
Vijay Gurmukhdas Makhani A52100003161 Real Estate Agent
RAMCHANDRA MAHADEV DUPARGUDE A52100021361 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
PARK IVORY PHASE III CIVIL JUDGE SENIOR DIVISION PUNE 1447 Civil No Suit NA 2016 PENDING FOR EVIDENCE
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement